How to apply

This section gives the information needed to apply for Countryside Stewardship Mid Tier using an application pack.

Before you apply, you must check and update any of your information in the Rural Payments service, and then request your application pack as explained above.

Before you start, check that your pack contains the following:

  • Mid Tier (MT) application form for 2022

  • annexes

  • Farm Environment Record (FER) map/Options map

  • Environmental Information (EIM) map

  • Historic Environment Farm Environment Record (HEFER) guidance letter.

If you’ve downloaded the pack or received it by email, save it to your computer and fill in the form and annexes on your screen. Print 2 copies of the Options/FER map, mark the options and environment features on them and scan them into your computer. Then email your completed form, annexes and maps to us. Read Step 8 for more information.

The HEFER guidance leaflet will tell you how to generate a HEFER from Historic England using the HEFER self-service portal. If you have requested an application pack over the phone, we will request the HEFER on your behalf. You do not need to return the HEFER to us.

If you’ve received your pack by post, fill in the application form, annexes and maps and either post them to us, or you can scan them into your computer and send them to us by email. Read step 8 for more information.

To apply for Countryside Stewardship (CS) Mid Tier in England in 2022, follow the sections below:

  • complete your application; then

  • confirm your information and apply.

Complete your application form, annexes and maps

This section tells you how to fill in your CS Mid Tier application form, annexes and supporting maps.

Step 1 – Start your application form

If you’ve received the pack by email, after you’ve saved it to your computer, fill in the form on your screen.

If you’ve received the pack by post:

  • use black ink and CAPITAL LETTERS. Do not use pencil or felt-tip pen

  • do not cross through whole pages or remove pages

  • do not use correction fluid. Correct mistakes and initial and date them. Completely fill any checkbox containing a mistake and put an ’X’ or a tick in the correct box

  • you must sign your application at Section 4 if you are submitting a paper application by post.

Front Page

The type of agreement you are applying for

Check the box next to ‘Mid Tier’.

Proposed agreement title

Enter the title that you want the proposed agreement to be known by, for example the land or farm name.

Your application ID is pre-populated

If this is blank, contact us for help.

Section 1: Application details

Fill in this section with your details.

1 Your SBI is already pre-populated.

2 (a) Confirm whether you are acting on behalf of the business. If ‘Yes’, you must make sure that you have the correct permission level in the Rural Payments service. Anyone with ‘Business Details: Full permission’ for the business can give you ‘CS (Applications) Submit’ permission.

3 Fill in (a) with the name of the applicant. This should be the same as the name on the ‘Start Here’ tab in the Annex. If (b) ‘Business name’ is pre-populated, check that the Business name and SBI are for the correct business. If it isn’t pre-populated, fill in the Business name.

Fill in (c) and (d) with the main contact name and business name if these are different to the applicant at a) and the printed business name at b).

Please contact us immediately with any changes to your contact information at c) and d).

Please make any other change in the Rural Payments service.

Section 2: Farm business details

4 (a) Confirm whether you have management control of all land in the application for the entire length of the proposed agreement and can meet the Declaration and Undertakings in Section 4. If ‘Yes’ go to Question 5. If ‘No’ go to Question 4 (b).

4 (b) Fill in a ‘Countryside Stewardship Land Ownership and Control’ form with each person who would take over your responsibilities if you cease to have management control over any of the land. This would normally be the landlord or another person with management control. Confirm you’re including this with your application, then go to Question 4 (c).

You can get a copy of the Countryside Stewardship Land Ownership and Control form on GOV.UK, or call us to ask for a paper copy if you cannot get online.

4 (c) Confirm if any of the counter signatories are a Public Body, for example, local authorities, National Park authorities, public corporations. If ‘Yes’ go to Question 4 (d). If ‘No’ go to Question 5.

4 (d) Tick ‘Yes’ to confirm you have supplied a copy of your tenancy agreement with the application.

Read Section 3.2 ‘Management control, eligibility and scheme rules’ in the CS Mid Tier and Wildlife Offers manual. Go to Question 5.

5 Obligations of your tenancy agreement to carry out environment management cannot be funded by Countryside Stewardship. Check that your application does not cover work that is required through any such obligations, and once you are sure this is the case, tick ‘Yes’ to confirm that this application is not seeking funding for these activities.

6 Confirm whether or not you’re applying for the Basic Payment Scheme (BPS) on any of the land parcels in this Mid Tier application in the current calendar year.

If ‘No’ you must give compatible land use codes in Annex 1, as described in Step 4 of this guidance. After you’ve done this confirm by ticking ‘Yes’.

7 Tick ‘Yes’ at (a) if someone else is claiming for BPS on any land parcels in this application. Then tell us if you are the landlord or tenant for the parcels being claimed by someone else at (b). Read section 3.3.1 in the CS Mid Tier and Wildlife Offers manual on GOV.UK.

Otherwise tick ‘No’ and go to Question 8.

8 Confirm whether or not you are a member of a Countryside Stewardship Facilitation Fund (CSFF) facilitated group.

If ‘Yes’ you must keep evidence of endorsement from the CSFF coordinator, and you should send this to RPA with your application.

For more information read Section 4.8.3 ‘Advice from a Countryside Stewardship Facilitation Fund Coordinated Group’ in the CS Mid Tier and Wildlife Offers manual on GOV.UK.

Also read ‘Guide to Countryside Stewardship: facilitation fund’ on GOV.UK.

9 If your application includes capital items or options to improve water quality or air quality you need to discuss these with Catchment Sensitive Farming (CSF) as their approval may increase your overall score.

To confirm that you’ve done this, tick ‘Yes’ and then give the name of the Catchment/River Basin. If your application doesn’t include any of these, tick ‘No’.

For more information search for ‘Catchment Sensitive Farming: reduce water and air pollution’ on GOV.UK.

Section 3: Organic Support (if relevant)

If you are not applying for organic support, go to Step 2.

Fill in this section if you’re applying for organic support, conversion and maintenance. 10. If your non-organic application for Mid Tier is not successful, confirm whether or not you want to continue with your application for just the organic options by ticking ‘Yes’ or ‘No’.

For more information read Section 4.4.7 ‘Organic conversion and management’ in the CS Mid Tier and Wildlife Offers manual on GOV.UK.

Continue your application through Steps 2-6 before you complete the declaration on your application form at Step 7.

Step 2 - Your Historic Environment Farm Environment Record (HEFER)

If you have Scheduled Monuments or other historic features on your land, you will need a Historic Environment Farm Environmental Record (HEFER) that is less than 3 years old and covers all the land in your application.

If you have received your application pack online, you will need to register and generate a HEFER from the HEFER portal.

Follow the instructions in the HEFER guidance leaflet, included in your application map, to generate a HEFER from the HEFER portal.

If you requested an application pack over the phone, we will request the HEFER for you and send it to you as soon as it is available.

Step 3 – Your Farm Environment Record (FER) map(s)

If you received a combined FER/Options map, you should photocopy it or print 2 copies. Use one copy to show your farm environment features and areas as explained in this section (and the other copy to show your options, as explained at Step 4).

Your FER map must show all the land parcels you’re including in your application.

You must mark on the FER map:

  • any land parcels in your application that are at moderate to high risk of runoff or soil erosion

  • all environmental features and areas in the land parcels in your application

  • all land parcels under your SBI that will be used for rotational options during the whole 5 year period of the agreement

  • all Sites of Special Scientific Interest (SSSI) or Scheduled Monuments (SM) within your control under your SBI.

If you have an FER map from a previous Countryside or Environmental Stewardship agreement and there has been little or no change to the environmental features on your land, you may be able to use that map (updated as necessary as explained under ‘Mark your environmental features and areas on your map’).

If you do not have an FER map from a previous Countryside or Environmental Stewardship agreement or there have been changes to the environmental features on your land, mark them on a copy of the FER map included in the application pack.

Remember that cross compliance requirements apply across the whole holding.

Land parcels with ‘moderate to high runoff and soil erosion risk’

Before you complete the FER, you should consider whether any of your land is at risk from surface runoff and soil erosion. You must do this for all of the land parcels on the holding. The risk assessment should be based on inherent risk, proximity and connection to a waterbody, such as a pond, lake, ditch, stream or river and on managed risk.

To do this use the assessment form on GOV.UK, search for ‘Runoff and soil erosion assessment: Countryside Stewardship’. Or use the guidance below.

Inherent Risk

Focuses on the risk of pollution associated with the topography, soils and naturally occurring land conditions. Inherent risk can be greatly reduced if the management and use of that land is done in a way sympathetic to the natural limitations. For example, a field of great inherent risk due to slope and soil texture might be of only moderate importance if that field were to be under woodland or extensive grassland management.

Factors to consider when defining the inherent risk include:

  • soil texture (risk of detachment or poor infiltration)

  • steepness of slope angles and slope length should be assessed to determine the relative overall risk of an area of land

  • flooding frequency: land that floods is susceptible to erosion and runoff, particularly when under cultivation.

This runoff may carry very fine soil particles, soluble pollutants such as plant nutrients and pesticides or manures to watercourses. The observed water runoff is usually, but not always, discoloured. The following detail is a guide to field classification for risk of runoff based on slope.

Soil type – all soils

Steep slopes greater than 7° (greater than 12.3% gradient) – High runoff risk

Moderate slopes 3° to 7° (5.25 to 12.3% gradient) – Moderate runoff risk

Gentle slopes 2° to 3° (3.5 to 5.25% gradient) – Lower runoff risk

Slope length, soil texture and flooding frequency must then be considered, and risk class adjusted accordingly. For example, lighter soils on moderate slopes may be at high risk of runoff leading to soil erosion. Land that floods regularly (inundated at least 1 year in 3) must be regarded as being at high risk of erosion and runoff (even at less than 2° slope).

Proximity and connection to a waterbody

This must be considered. Fields that pose a relatively high inherent risk for producing pollution may actually be less significant if those fields are not well connected to a watercourse or waterbody. Therefore, the risk may need to be increased or decreased depending on the closeness or connection to a waterbody.

For example:

  • fields directly adjacent to a watercourse or waterbody are likely to increase the risk and likelihood of pollution. Also, there may be increased risk where drains, ditches, tracks or other flow paths directly connect a field to a watercourse, waterbody or sensitive aquatic habitat

  • where there is at least one field between this field and a watercourse or waterbody and there are no flow pathways, the risk is unlikely to be higher than moderate.

Little connection between this field and the waterbody decreases the risk of pollution and this is likely to lower the risk class.

Managed risk

This is primarily defined by land use and history of runoff and pollution problems on that field. Signs of surface water runoff that may be associated with each of the risk classes are described below:

  • High Risk Areas – runoff or ponding seen in most years during wet periods

  • Moderate Risk Areas – runoff seen in some years during wet periods and in most years during very wet periods

  • Lower Risk Areas – runoff seen in some years during very wet periods.

The criteria given for the risk assessment are guidelines and professional judgement should be used to upgrade or downgrade a site, taking into account additional factors such as:

  • soil structure (sensitivity to compaction, detachment and transport)

  • organic matter content (higher organic matter content usually increased infiltration)

  • valley features which tend to concentrate runoff water

  • long unbroken slopes (150m or longer)

  • rainfall (intensity relative to infiltration)

  • land use.

Using the risk assessment you must now mark on the FER, in brown hatching, all fields that have been identified as at moderate or higher risk of surface runoff and soil erosion.

Mark your environmental features and areas on your map

You need to mark all of your environmental features and areas on the FER map(s) (as shown in the map key). Walking your holding will help you see which land parcels are suited to Countryside Stewardship options. This may also help you to identify where to mark the environmental features on your FER map(s). Your Environmental Information map (EIM), which is also included in your application pack, may indicate features that you need to mark on your FER map(s).

Make sure your FER map(s) are clear and accurate.

If you want to use a previous Countryside or Environmental Stewardship (CS or ES) FER map, consider the need for any updates (see below) and decide whether the updated map will be clear and easy to understand. For former ELS/HLS agreements the combined FER/FEP map may contain significant information not required for CS. If this is the case you may prefer to complete a new CS FER map.

Use the colours on the FER map’s key. Confirm that you have a feature by marking the corresponding blank symbol on the right side of the map key with the coloured pencil you have used to mark that feature. You must submit the completed map(s) as part of your application.

Please read the specific information below for the following features.

Marking ‘boundaries with trees’

Only boundaries with, on average, one or more eligible trees for every 100 metres need to be marked as ‘boundaries with trees’.

For example, a hedgerow of 400 metres would need to have at least four eligible trees along its length. Eligible trees are those that are native species, standing within 1 metre of a hedgerow and over 30 centimetres diameter at breast height.

These boundaries should be marked with a green cross over the boundary line, as shown in the FER map’s assigned colour key (in-field trees still need to be counted and marked as shown in the key).

If you are using an FER map from an earlier ES agreement and it shows the number of hedgerow trees, you do not need to change it.

Marking hedges

On accepting a CS agreement you will be agreeing that you will not cut more than 50% of hedges in any one year. This is a scheme baseline requirement that covers all hedges in Mid Tier and Higher Tier agreements. It covers all hedges marked on the FER map which meet the following CS hedge definition:

‘Any planted boundary lines of shrubs (a woody plant where the distance between the ground and the base of the leafy layer is less than 2 metres) which are over 20 metres long and less than 5 metres wide (between major woody stems at the base) and are composed of at least 80% native shrubs’.

This does not apply to road and trackside hedges that need to be cut annually or more frequently for public safety. To mark the cutting regime of the hedges on the FER map you will need to use two different types of marking as indicated in the FER map’s assigned colour key, as detailed below:

  • Hedgerow (meets 50% annual cutting limitation). These hedges are managed as the baseline requirement of the scheme – no more than 50% of these hedges are cut in any one year. This includes hedges that are included in CS capital or revenue options and therefore have specific management prescriptions. These specific prescriptions should be followed by the Agreement Holder and checked on inspection, rather than the baseline requirement

  • Hedgerow (exempt from the cutting limitation). For hedges that need more regular cutting to maintain public safety.

Updating a Countryside Stewardship (CS) or Environmental Stewardship (ES) FER map

If you are using a FER map from an earlier CS or ES agreement, you must check that it is up to date before submitting it with your CS application. If the earlier CS or ES FER map does not include all the land parcels in your application, you must update your CS FER map for those new land parcels as explained at 3) below.

Please check and update it as follows:

1) On the earlier CS or ES FER map:

  • strike out any land on the earlier CS or ES FER map that is not to be included in the CS application

  • add any new features not showing on the earlier CS or ES FER map (for example, a new pond)

  • identify any hedgerows that are exempt from the 50% annual cutting limitation, by marking them using the symbols indicated on the CS FER map key.

2) Compare the new CS FER map key with your existing CS or ES FER map key:

If there are any features listed on the CS FER map key that are not on the ES FER map key mark them on the ES FER map, using the symbols given in the CS FER map key. (Some earlier ES FER maps did not include earth banks, scrub, bracken, boulders and rocky outcrops).

3) On the CS FER map: Mark the environmental features and soil erosion risk on any new land parcels not included in the earlier CS or ES FER map.

4) Sign and date the updated ES FER map, to confirm it is complete and accurate. If you have made any annotations to the CS FER map you will need to include both the ES FER and CS FER maps with the application. The updated map(s) must be clear and understandable. If we find that a FER map is not clear and understandable, we will not be able to accept it.

Step 4 – Your options map(s) and your options and capital items annexes

We suggest you complete the annexes and the options maps alongside each other. This means you can add your option or capital item in the annex then immediately mark it on the map as you go along.

Before you start:

  • Options and capital items – choose these using the guidance in Section 2.2 ‘Grants available in Mid Tier’ and Section 4.4 ‘How to choose options and capital items’ in the CS Mid Tier and Wildlife Offers manual on GOV.UK. Read more information about individual options in Countryside Stewardship grants, also on GOV.UK.

  • Options map – if you receive one combined FER/Options map, you should photocopy it or print 2 copies. Use one to show your options as explained in this section (and the other to show your farm environment features and areas, as explained in the previous section)

  • Options annex – if you receive your application pack by post and do not have enough space to add all of your options or capital items to the data sheet table in an annex, create continuation sheets by photocopying the relevant annex before you use it. Where you have used continuation sheet(s), please indicate this on the relevant data sheet and enter the total number of continuation sheets used. For example, Sheet 1 / Total 3; Sheet 2 / Total 3; Sheet 3 / Total 3.

If you cannot print or photocopy, please use your own continuation sheet(s), and make sure you include all of the information required in the related data sheet.

Please call us if you have any issues printing or photocopying.

Complete the CS options map for options and capital items

For each CS non-rotational option (including capital items) you want to include, complete the CS Options map(s) as follows:

  • mark every instance of the option using the appropriate colour in the Options map key

  • write the option code, using a black pen, on or against the option in each place where you have marked it on your Options map(s).

Take care to measure option lengths or areas and then calculate values accurately as errors may lead to your payment being reduced and penalties being applied.

For double-sided hedges, you should add the hedge twice and mark it on both sides of the boundary. This is only allowed where both sides of the boundaries land parcels are mapped in the Rural Payments service. If one side has not been mapped, you are only allowed a single sided hedge.

Complete the application annexes

Important: if you’ve received your application pack by email, the annexes are an Excel spreadsheet. The land parcel information is pre-populated in Annex 1. The information you choose at Annex 1 pre-populates again for you to choose from in the other annexes where relevant.

If you’ve received your application pack by post, the annexes are on paper. The land parcel information is pre-populated in Annex 1. However, you must write all other information relating to your application onto the other annexes.

You must fill in the first 4 tabs in the Annex:

  • ‘START HERE’ – The SBI and Application ID are pre-populated. Fill in the name of the applicant. This should be the same as the name at question 3a on the application form

  • Annex 1 – Land summary

  • Annex 2 – Options

  • Annex 3 – Capital items

If you’re applying for Mid Tier water quality capital items only, you do not need to fill in Annex 2.

(The detail in the red ‘Grant totals’ and ‘Application summary’ tabs is for information only. Read Step 5 for more information.)

Annex 1: Land summary

You must check that this annex has been pre-populated with all of the land parcels registered to your SBI.

If you find that some of your eligible land parcels are not shown in this annex, check whether they are shown on the map(s) in your application pack. If they are shown on the map(s), add the details of the land parcel to this annex. If they are not shown on the map(s) contact us.

Delete any land parcels that you do not want to include in your application. (Highlight the row of information for that land parcel and press delete. Or on a paper annex cross through the row.)

Important: make sure you include any land parcels that:

  • you’re using for rotational arable options during the whole period of the agreement

  • contain Sites of Special Scientific Interest (SSSI) or Scheduled Monuments (SM) within your control under your SBI, even if you are not applying for options on them.

The SBI and the first 3 columns are pre-populated.

You must fill in the annex as explained below.

Field parcel ref/OS Map Sheet Ref/National Grid no.

This is pre-populated. It is the Ordnance Survey (OS) Map sheet reference and National Grid field number. It must contain a 10-character reference, made up of 2 letters, 4 numbers and the final 4 numbers indicating the centre of the land parcel (for example, LP12345678). We need the whole reference to identify the land parcel.

Parcel name

This is pre-populated, but you can amend it. This is the name of the land parcel (if it is known by one) to help you identify it. If you do not have a name for your parcel, repeat the field parcel reference. There must be either a name for each land parcel or a parcel reference in every row under ‘Parcel name’.

Total land parcel size (ha)

This is pre-populated with the total area of the land parcel based on the area registered in the Rural Payments service.

Does this parcel contain an SSSI?

For each land parcel, confirm whether there is a Site of Special Scientific Interest (SSSI) on the land parcel. Click into the box in this column, then click the small dropdown arrow that appears. Then confirm either ‘Yes’, or ‘No’. Do not delete any land parcels that are in an SSSI.

Does this parcel contain a Scheduled Monument?

For each land parcel, confirm whether there is a scheduled monument on the land parcel. Click into the box in this column, then click the small dropdown arrow that appears. Then confirm either ‘Yes’, or ‘No’. Do not delete any land parcels that contain a scheduled monument.

LFA Status

For each land parcel, click into the box in this column, click the dropdown arrow, then choose the code for the relevant ‘less favoured area’ from the list. Read the key at the top of the annex.

Will rotational options be included on this parcel?

For each land parcel confirm whether there will be rotational options on the land parcel at any point during the 5 year period of the agreement. Click into the box in this column, then click the small dropdown arrow that appears to confirm ‘Yes’ or ‘No’. If you do not confirm ‘yes’ in this annex then you will not able to choose a rotational option for this land parcel in the Options tab. Do not delete any land parcels that support rotational options during the period of the agreement.

Run off/soil erosion risk?

For each land parcel confirm whether there is a moderate to high risk of run off or soil erosion. Click into the box in the column, click the dropdown arrow, then confirm either ‘Yes’, or ‘No’. For more information about runoff/soil erosion read Step 3 – Your Farm Environment Record (FER) map(s).

Land use code for land not declared or claimed for BPS (if applicable)

You do not need to fill in the land use code for every land parcel in your Mid Tier application if you are applying for BPS in the same year. However, you must fill in the land use code for any land parcel in your Mid Tier application that is not included in your BPS application. The land use codes for the land parcel must be compatible with the options you are applying for in your Mid Tier application. A list of land use codes is on GOV.UK, search for ‘Rural Payments: land guidance’.

Is this parcel included in the Wild Pollinator & Farm Wildlife Package? (Y/N)

For each land parcel confirm whether you will be including it in the Wild Pollinator & Farm Wildlife Package (WPFWP). Click into the box in the column, click the dropdown arrow, then confirm either ‘Yes’, or ‘No’. For more information about the WPFWP, read Section 2.2.5 and Annex 4 of the CS Mid Tier and Wildlife Offers manual.

Annex 2: Options

You require prior endorsement for the use of some Mid Tier options. Read more information in the CS Mid Tier and Wildlife Offers manual on GOV.UK.

For organic options, make sure that you have also completed Step 1 and Section 3 of the application form and read Section 4.4.7 ‘Organic conversion and management’ in the CS Mid Tier and Wildlife Offers manual on GOV.UK.

Important: if you’ve received your application pack by post, the annexes are on paper. You will need to write in all required information onto the annexes.

If you received an application pack by email, Annex 2 is an Excel spreadsheet.

Land Parcel details

Parcel name

For each land parcel, click into the box in this column, click the dropdown arrow, then choose the relevant ‘Parcel name’ from the list. The relevant information will appear in the ‘Field Parcel’ and ‘Total land parcel size (ha)’ columns.

On a paper annex there is no pre-populated information, therefore you must write all of the information into the relevant boxes for the land parcels you’re including in your application.

Field parcel

The information in this column comes from Annex 1 and appears automatically when you choose the ‘Parcel name’.

Total land parcel size (ha)

The information in this column comes from Annex 1 and appears automatically when you choose the ‘Parcel name’.

Option details

Rotational or Non-rotational option?

For each land parcel confirm whether the option is rotational or non-rotational. Click into the box in this column, then click the small dropdown arrow that appears to confirm either ‘Rotational’ or ‘Non-rotational’. Do not delete any land parcels that support rotational options during the 5 year period of the agreement.

Option

For each land parcel choose the option you want to apply for. For example, ‘AB8 Flower-rich margins and plots’. Click into the box in this column, click the small dropdown arrow, then choose the option from the list.

Unit

The unit the option is measured in will appear automatically when you choose an option in the previous column. For example, tonne, metres or hectares ‘ha’.

Quantity

Enter the number of units you’re applying for. Do this to 4 decimal places for tonnes and hectares (ha), and whole numbers for metres.

Payment details (Excel annexes only)

Payment rate

This is the value of each unit for the option you’ve chosen. It appears automatically when you fill in the ‘Option’ column.

Value

This is the value for the number of units you’ve entered. It appears automatically when you fill in the ‘Quantity’ column.

The ‘Application summary’ and ‘Grant totals’ tabs give useful information about the options and items that you have chosen and the financial value of your application. The information in them appears automatically as you fill in annexes 1 to 3.

Step 5 – Continue your application form

Section 4: Declaration and undertakings

Complete this section to confirm that you have read and understood the requirements of the Countryside Stewardship Mid Tier scheme and the undertakings that you are making when submitting your application.

Read the declaration, undertakings and warning carefully.

Sign in the box, and enter your name in block letters, your capacity (for example, Company Director, Agent) and the date you’re signing the application.

If you’re submitting your application by email you do not need to sign the application in this section.

Before you submit your application, make sure:

  • You have the correct permission levels in the Rural Payments service.

  • You’ve attached any other required supporting documents, evidence, or permissions and consents applied for.

  • You’ve told us the number of continuation sheets you’ve used (if applicable).

Step 6 – Checklist – use this to confirm that you have read and completed everything needed

Before you submit your application, you can use this checklist to help you make sure that you have done everything you need to do.

You’ve read and understood the CS scheme rules and requirements in the CS Mid Tier and Wildlife Offers manual, including the terms and conditions at Annex 1.

You, and the land that you are including in your application, are eligible for CS – read Section 3: ‘Who can apply and what land is eligible’ section in the CS Mid Tier and Wildlife Offers manual.

You’ve registered all of the land in your application in the Rural Payments service, checked all the details are correct and submitted an RLE1 form for any land that is not already registered.

The application does not have to cover the whole holding, but it must include all land parcels that will support rotational options for the whole period of the agreement and all Scheduled Monuments (SM) within your control.

Cross compliance requirements apply across the whole holding.

You have the correct permission levels in the Rural Payments service to complete and submit this application.

To authorise an agent to act on your behalf of this business, anyone with ‘Business Details – Full permission’ for the business can give an agent ‘CS Applications – Submit’ permission.

You’ve completed Annex 1.

You’ve given the following details in your Annex 1a:

  • all land parcels at moderate to high risk from runoff or soil erosion

  • land use codes for all the land parcels in this Mid Tier application. Unless you are applying for BPS this year, then you only need to give the land use codes for any land parcels in your Mid Tier application that are not in the BPS application.

  • all land parcels, including those with yards and tracks, you want to consider for soil and water (water quality) and resource protection options and capital items

  • all land parcels you want to be considered for the Wild Pollinator and Farm Wildlife Package

  • all land parcels containing SSSIs or Scheduled Monuments

  • all organic land parcels

You’ve completed the following maps for an Agri-environment application:

  • a Farm Environment Record (FER) map including:
  • all features and area on the land parcels included in your application
  • all land parcels containing Scheduled Monuments
  • all land parcels containing SSSIs
  • all land parcels at moderate to high risk from runoff or soil erosion

  • an Options map for the multi-year options in your Agri-environment application

You’ve filled in Section 4: Declaration and undertakings of the application form. (You only need to sign in the box if you are submitting a paper application form by post.)

You know what supporting documents you must submit with your application. You’ve completed and attached them where necessary:

  • CS Land Ownership and Control form(s) - read Question 4

  • a copy of your tenancy agreement (if you have a public body landlord) – read Question 4

  • written support from Catchment Sensitive Farming – read Question 9

  • the required evidence if someone else applies for BPS on any land in your Wildlife Offers application – read Question 7 and about dual use in Section 3.3.1 in the  CS Mid Tier and Wildlife Offers manual.

You understand what evidence is needed for your application; this depends on the options you choose.

For more information about evidence read the ‘How to Apply’ section and section 6.4 in the CS Mid Tier and Wildlife Offers manual on GOV.UK. For information about evidence for each option and capital item read Countryside Stewardship grants on GOV.UK.

You’ve attached any other required supporting documents, evidence, or permissions and consents applied for.

You’ve told us the number of continuation sheets you’ve used (if applicable).

Step 7 – Supporting documents and evidence

We must receive your application and supporting documents by midnight on 29 July 2022. We may also need to receive some evidence by this date – read below.

Supporting documents

For example:

  • Options map
  • FER map
  • Woodland Support agreement map
  • Land Ownership and Control form(s)
  • Written support from Catchment Sensitive Farming

Maps

For more information about what to include in your maps, read ‘Step 3 – Your Farm Environment Record (FER) map(s)’ and ‘Step 4 – Your options map(s) and your options and capital items annexes’ or read ‘Section 4: How to Apply’ in the CS Mid Tier and Wildlife Offers manual for 2022 on GOV.UK.

Evidence

We may need to receive some evidence by midnight on 29 July 2022, and some you may need to keep until we ask you for it. Read about the evidence requirements for each relevant option or capital item in Countryside Stewardship grants on GOV.UK.

How to submit your supporting documents or evidence

You can scan and email all the documents to RPA. You must put your SBI and Application ID on all documents.

The maximum size of emails we can accept is 32MB. If the email exceeds this limit, please send a further email and use the same subject heading. Add the number of emails at the end of the subject heading, for example, 1 of 3, 2 of 3, 3 of 3.

For security reasons, we cannot accept discs, USB pen drives or other external storage media.

You can submit digital photos by email, but do not scan printed photos as the quality is not good enough.

Or you can post the documents to us using the address in ‘More information and contacts’ below.

For more information read Step 8 – Submit your application.

Step 8 – Submit your application

All of the following must reach RPA by the application deadline (midnight on 29 July 2022):

  • all sections of the completed application form
  • all relevant completed annexes
  • all completed maps and any other supporting documents
  • any evidence that Countryside Stewardship grants shows must be submitted.

For all applications you must:

  • put your SBI and Application ID on everything you send to us
  • have the correct permission level (at least ‘CS Applications – Submit’) in the Rural Payments service.

Submit your application by email

If you received your application pack by email,  ‘reply’ to that email, attaching your completed documents to it. You’ll need to scan the completed maps and supporting documents first. By ‘replying’ to the email we sent to you, rather than sending us a new email, your application will be automatically forwarded to the correct team and won’t wait in a queue to be sorted manually.

If you downloaded your application pack or received it by post, you can submit it by email. Scan all the documents, attach them to an email and send the email to ruralpayments@defra.gov.uk. The subject of your email must be ‘Mid Tier application 2022’.

You must put your SBI and Application ID number in your email as well as on everything you attach to the email.

Make sure that the email address you’re sending your application from is registered for your business in the Rural Payments service.

Send your application by post

If you received your application pack by post and cannot submit it by email, you can post it to:

Rural Payments Agency (Countryside Stewardship),
PO Box 324,
Worksop
S95 1DF

Remember to sign your paper application at Section 4 before you submit it.

We recommend that you get proof of posting for any documents you send to us by post. You should keep a copy of everything you send to us.

What happens next?

After we have received your application we will check that:

  • you meet the eligibility requirements
  • all the necessary details have been given in your application form and annexes
  • all of your maps have been completed.

If your application fails any of the above checks, we will contact you to explain what’s wrong and how you can correct it (if relevant).

CS Mid Tier is competitive, which means that not everyone who applies will be successful. We use a scoring process based on environmental benefits to select successful applicants.

If your application has been successful

We will write to you and let you know. Successful applications will become live Mid Tier agreements on 1 January 2023.

If your application has not been successful

You can appeal. For more information read the ‘Disputes, appeals and complaints’ section in the CS Mid Tier and Wildlife Offers manual for 2022.