Decision

Norfolk Boreas offshore wind farm: non-material change, Planning Act 2008

Decision by the Secretary of State on an application for non material changes regarding an offshore wind farm.

Applies to England

Documents

Norfolk Boreas offshore wind farm decision (link to National Infrastructure Planning site)

Details

Decision by the Secretary of State on an application for non material changes regarding an offshore wind farm.

Date of decision

20 September 2022

Company / location

Norfolk Boreas Limited and Norfolk Vanguard East Limited
Approximately 73km off the Norfolk coast

Non material consent under the Planning Act 2008.

Maximum output

Not applicable.

Published 20 September 2022