How to apply for a great crested newt mitigation licence or request a change to an existing licence (A14)
Updated 29 October 2026
Applies to England
You should only apply for a licence if the start date of the work is within 3 months. This is because conditions on site could change between the licence being issued and work starting, and your licence might not cover all of the impacts.
If you need advice on whether your proposal is likely to meet licensing requirements, you can use the pre-submission screening service.
To apply for a mitigation licence, you must complete an online application form. In the form you’ll be asked to complete and upload:
-
a method statement – to show what you’ll do to reduce the impacts of the proposed work on great crested newts
- relevant maps and figures as specified in the method statement
- a work schedule – to show when you’ll do the activities and in what order
- a signed declaration from either the applicant (the person, company or organisation who will hold the licence), the named ecologist, or both
You may also need to provide:
- information about the licence purpose, if it is not for imperative reasons of overriding public interest (IROPI)
- a reasoned statement to show that the activity fits the criteria and that there is no satisfactory alternative – read the section ‘Check whether you need a reasoned statement’ to find out whether you need one
- references to show that the ecological consultant has the necessary experience to apply for a mitigation licence (references will not be needed if they’ve been named on a mitigation licence for great crested newts issued in the last 3 years)
You must also get all necessary consents and include copies of them.
If the work is part of a phased development (requiring more than one licence application) or multi-plot development, you must provide a:
- great crested newt master plan
- habitat management and maintenance plan
To understand what needs to be included in your master plan, you can use the archived guidance on great crested newt master plan requirements as a guide.
To provide the relevant supporting evidence with your application:
- Download each required document and save it to your device.
- Complete each document with all the necessary information.
- Rename and upload the completed documents when prompted in the online application form.
Natural England will usually decide whether to issue a licence within 30 working days of receiving your application.
Use the European protected species (EPS) licensing policies
As part of your mitigation licence application, you may be able to use the EPS licensing policies to:
- reduce the level of survey you need to carry out
- reduce the mitigation requirements
- improve flexibility on where you create habitats as a compensation measure
Find out when and how to use European protected species policies to benefit EPS.
Check whether you need a reasoned statement
You may need to complete and upload a reasoned statement as part of your licence application, depending on your planned activity and its purpose. Some activities have exemptions.
Housing developments
You do not need a reasoned statement if you are using the great crested newt district level licensing scheme for a housing development.
If you’re applying for an A14 licence for a housing development, you only need to include a reasoned statement if your planned activity is any of the following:
- on or adjacent to special areas of conservation (SACs) or sites of special scientific interest (SSSIs) with great crested newts as the qualifying feature
- affecting a large great crested newt population (100 or more at peak count)
- in the red zone of any district level licensing scheme
All other great crested newt licence applications for housing developments do not need a reasoned statement.
Public utility works
A public utility supplier can be a public or private company that provides public services such as:
- energy (gas and electricity)
- water
- waste
- transport (road and rail)
- communications infrastructure
You do not need to include a reasoned statement if great crested newts and their habitats will be affected by:
- repair, maintenance, restoration or renovation of existing infrastructure
- removal of infrastructure that’s no longer needed, such as road signage or cabling
- replacement or upgrading of existing public utility infrastructure
- essential works to prevent serious damage to property, preserve public health and safety, or to allow continued intended and appropriate use of the infrastructure
If you are constructing or installing new infrastructure such as laying pipes and cables or putting up road signs or telegraph poles, you do not need to include a reasoned statement where:
- the impact to great crested newts is temporary and the habitat will be restored to its original or a comparable state once works are complete
- there is negligible permanent habitat loss – as a guide, less than one square metre for the footprint of each road sign or telegraph pole installed
- the same resource, shelter, protection and suitability as a breeding site or resting place will be available when works are complete
You only need to include a reasoned statement for works to install new infrastructure that will cause a permanent loss of great crested newt habitat.
Maintain, repair or improve public buildings, or develop public land
Public buildings and public land includes buildings and land owned or leased by the government, their departments, agencies and arm’s length bodies, such as:
- schools
- hospitals
- prisons
- courts
- airfields
It does not include the Public Forest Estate or SSSIs.
You do not need to include a reasoned statement where great crested newts and their habitats will be affected by:
- repairs and maintenance
- restoration
- renovation
- redevelopment of an existing building, which may include demolition before redevelopment, as long as it remains in use as a public building
- extending or adding new buildings within the grounds of the existing developed site
- essential works to prevent serious damage to buildings (including contents), preserve public health and safety, or to allow the building to be continued to be used as it was intended
You must include a reasoned statement with your licence application if you are extending public buildings beyond existing boundaries, changing them to private use, or developing land for private use.
Complete the reasoned statement form
Unless your activity meets one of the exemptions, you must upload an EPS reasoned statement in your application.
If your activity meets one of the exemptions listed in the previous section, you do not need to complete a reasoned statement. You must say in your application which exemptions applies.
Apply for a licence
Before applying for a licence you should know or have ready:
- your most recent application reference number, if you’ve applied before
- the main purpose and details of the proposed work and any consents, planning commitments, approvals and conditions
- the Companies House registration number or registered charity number, if applying as an organisation
- the applicant’s details and an alternative contact’s details, if you want to give one
- the contact details, experience, qualifications and references for the named ecologist – they must be registered to use a great crested newt class survey licence level 1 (CL08) or higher, or equivalent
- the site details and location
- details of previous licences and other licence applications for the site or project
- details of the licensable activities you’re applying for, including the dates of the work
- maps and figures to support your application – you’ll be told in the application what you need to provide, depending on your answers
- signed declaration forms from the applicant and named ecologist
You may need to provide evidence that supports your reason for applying, for example a letter or report that explains the issue, or photographs.
What happens next
The applicant, named ecologist and any additional named contacts will receive an acknowledgement email confirming:
- the application reference number
- the expected charge for the licence, based on the information in the application form
We aim to give the licence decision within 30 working days. If you are applying early or under exceptional circumstances, we will review your application to confirm if we can accept it.
Request a change to an existing licence
For all changes, you must:
- complete the licence modification request form
- include the licence reference number
- have both the ecologist and the licensee sign the form
- include any amended documents or figures, dated appropriately, as stated on your request form (highlight changes within documents and strikeout deleted text)
For a change of licensee, you must include:
- a letter or email from the previous licensee explaining what is proposed
- a letter or email from the new licensee confirming that they accept the agreed mitigation proposals relating to the licence
- the change of licensee or named ecologist form with section 1 completed by the new licensee
If the licensee is a company or organisation and you need to request a change to the named contact, then you should do this by sending a letter or email to Natural England.
When you request the change, you should include the:
- licence reference number
- name of the new named contact
- named contact’s position in the company or organisation
- named contact’s telephone number
- named contact’s email address
You do not need to complete the modification form to request a change to the named contact.
For a change of named ecologist, you must include:
- a letter or email from the previous ecologist explaining what is proposed
- a letter or email from the new ecologist confirming that they accept the agreed mitigation proposals relating to the licence
- the change of licensee or named ecologist form with section 2 completed by the new ecologist
If your licence was issued before 2015, meaning it includes a licensed method statement, you must:
- provide a summary of progress stating what has been completed and what is left to complete
- provide a summary of the animals captured or disturbed during the licensed works so far
- include a list of the changes to the licensed method statement and other documents
- state whether there are any implications for the ‘favourable conservation status’ of the licensed species as a result of the proposed changes
- include an updated method statement, dated appropriately, with all changes clearly highlighted (even if you only need to modify the work schedule)
- include all maps and figures that support your method statement
Licence charges
You may need to pay for this licence, or a change to your licence for certain development work. At the end of the online application, or after submitting your licence modification form, you’ll be told:
- if you need to pay
- how much you’ll pay
When you may not need to pay
You may be exempt from licence charges under The Wildlife Licence Charges (England) Order 2025 if the main purpose of your great crested newt mitigation licence application is to:
- preserve public health or safety
- prevent the spread of disease
- prevent serious damage to property
- conserve a historic property
- complete a householder home improvement project to a single home
How much it will cost
If you are not exempt, the cost of a new A14 licence is a variable price depending on the time taken to assess your application.
Natural England will calculate how much you pay, based on how long it takes to assess your application. You’ll pay £219 towards compliance checks, plus £121 per hour spent assessing your application (rounded up to the nearest 15 minutes).
We do not check every licence for compliance, but this fee helps cover the cost of compliance checks across all licences.
The cost of a variably priced licence depends on the time needed to assess it.
Complex cases are likely to cost more. Factors that can increase the complexity of a case include:
- projects using unusual, new or contentious methods, including the use of sniffer dogs
- issues with ecologist experience or poor references
- surveys that do not follow guidance or are limited or constrained
- phased or multi-plot developments
- use of licensing policies
- applications that have incomplete or inaccurate details
- applications where compliance issues have been identified or have previous police involvement
- applications without relevant planning consents in place
- applications that affect a protected site
- applications that require a habitat management and maintenance plan
- applications where there will be a moderate to high impact on a large or regionally important population of great crested newts or where there will be the loss of more than 2 waterbodies where great created newts breed
- applications that require more significant site safeguards, such as a Natural Environment and Rural Communities (NERC) Act agreement
Resubmitting an application
If you resubmit your application after a ‘further information request’ and your licence is not exempt, you must pay both:
-
the variable price for assessing your original application
-
the variable price for assessing your resubmitted application
Modifying an existing licence
If you need to modify your existing licence, you will pay the variable price, unless your licence is exempt.
Terms and conditions
Read the terms and conditions for paying for a wildlife licence.
How to pay
Natural England will send you an invoice if they approve your application.
You can pay by:
- electronic bank transfer
- debit or credit card by telephone – except American Express
- cheque
Your invoice will give details for these payment methods.
You need to include the invoice number with your payment so Natural England can match it to your application.
VAT does not apply to charges for wildlife licences.
Natural England accepts purchase orders. If you want Natural England to add a purchase number to your invoice, you must include it in the invoice details in your application form.
How to report your actions
You must report any actions you took using this licence.
You must report no later than 2 weeks after your licence expires, even if you’ve taken no action. You may also be asked to submit interim reports.
Send your completed form by post or email to Natural England using the details on the form.
The report form you must use depends on when your licence was granted. If it was granted:
- before summer 2013, use the European protected species return form
- after summer 2013, use the great crested newt licence report form found on Great crested newts: apply for a mitigation licence (A14)