Decision by the Secretary of State on an application by Norfolk Boreas Limited (RWE Renewables UK Limited).
Documents
Details
Decision by the Secretary of State that Requirement 13 of the Development Consent Order, relating to the Air Defence Radar Mitigation Scheme, has been discharged.
Date of decision
22 September 2026
Company
Norfolk Boreas Limited (RWE Renewables UK Limited)
Location
94km north-east of Great Yarmouth
Type of project
Post-consent condition discharge of Norfolk Boreas Offshore Wind Farm Order 2021 (as amended), as made under the Planning Act 2008
Maximum output
Up to 1,800 MW.