Decision

New poles to support section of overhead line, Ebernoe, West Sussex: screening decision, section 37 consent, Electricity Act 1989

Screening decision by the Secretary of State on installation of 5 new poles to support an approximate 600 metre section of 33kv overhead line.

Applies to England

Documents

Details

Screening Decision by the Secretary of State for an application for Section 37 consent for the installation of 5 new poles supporting a 33kv overhead line, in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Location

Land south of Streel’s Lane
Ebernoe
West Sussex
GU28 9LD

Date of decision

21 September 2022

Section 37 consent to install or keep installed an electric line.

Published 21 September 2022