Decision

Mona Offshore Wind Farm: development consent order, Planning Act 2008

Decision on an application for an offshore wind farm under the Planning Act 2008.

Applies to England

Documents

Mona Offshore Wind Farm decision

Details

Decision by the Secretary of State on an application for an offshore wind farm with up to 96 wind turbines with an output of over 350 megawatts (MW) of renewable energy and up to 4 offshore substation platforms which would be located in the east Irish Sea; and landfall on the North Wales coastline with onshore export cables connecting to the proposed onshore substation with a connection to the Bodelwyddan National Grid substation.

Date of decision:

4 July 2025

Company / location:

Mona Offshore Wind Limited
Sunbury On Thames
Middlesex
England

Type of project:

Development consent order for an offshore wind farm under the Planning Act 2008.

Minimum output:

350 MW

Updates to this page

Published 4 July 2025

Sign up for emails or print this page