Helios Renewable Energy Project: decision on an application for development consent under the Planning Act 2008
Decision on an application for a solar farm in North Yorkshire under the Planning Act 2008.
Applies to England
Documents
Details
Decision by the Secretary of State on an application by Enso Green Holdings D Limited for the construction, operation (including maintenance), and decommissioning of ground-mounted solar photovoltaic arrays with a total capacity of 190 megawatts (MW).
Date of decision
3 December 2025
Company / location
Enso Green Holdings D Limited
South of Selby, North Yorkshire
Type of project
Development consent order for a photovoltaic solar farm under the Planning Act 2008.
Maximum output
190 MW