Five Estuaries Offshore Wind Farm: development consent order, Planning Act 2008
Decision on an application for an offshore wind farm electricity generating station under the Planning Act 2008.
Applies to England
Documents
Details
Decision on behalf of the Secretary of State, by Alan Whitehead (Minister for Energy Security and Net Zero) on an application for the construction and operation of an offshore wind farm with grid connection capacity of up to 1080MW, including up to 79 turbines, off the coast of Suffolk and Essex.
Date of decision
17 December 2025
Company / location
Five Estuaries Offshore Wind Farm Limited
Swindon
Wiltshire
England
Type of project
Development consent order for an offshore wind farm under the Planning Act 2008.
Maximum output
1080 MW