Guidance

Compliance audit 2020 to 2021: breach severity list, accessible version

Updated 27 January 2021

This guidance was withdrawn on

This has been withdrawn due to a change in policy.

Applies to England

1. General breaches

Item number Breach Severity level
1 Comprehensive scheme file containing all relevant documents (as set out in the CFG) not provided medium
2 Key document not on file: requested by lead auditor but not provided high
3 Key document not on file: provided following request by Lead auditor, but not within 2 weeks of request medium
4 Key document not on file: provided within 2 weeks of request low
5 Incorrect processing route in IMS high
6 The development costs are lower than the contractual commitment, and no variation has been agreed medium
7 Quality standards documentation on file does not meet the requirements set out in the contract and/or bid medium
8 Incorrect IMS data has been entered but there are no value for money implications. Examples might include typographical errors, or a failure to update the system with revised information low
9 Incorrect IMS data has been entered with value for money implications medium
10 Grant payments(s) claimed in respect of units funded through a planning obligation (including section 106 agreements) high

2. Pre-development breaches

Item number Breach Severity level
11 Valid valuation (as set out in the CFG) not obtained in respect of a scheme for which it was required high
12 Acquisitions
Valuation report not valid at exchange of contracts
medium
13 Insufficient evidence of good title over development land, and no defective title indemnity insurance in place high

3. Development breaches

Item number Breach Severity level
14 Acquisition grant payment claimed in advance of need.
This applies where the grant recipient did not have a freehold or long leasehold interest at the point when Acquisition grant was claimed
high
15 Start on Site grant payment claimed in advance of need.
This applies where, at date of Start on Site claim:
• the works contract was not signed and/or dated by all parties
• contractual possession was not passed to contractor
• secure legal interest had not been obtained (for example no proof of ownership/lease/building under licence)
• Start on Site works were not commenced according to CFG definition
high
16 No form of building contract (or works orders for works carried out by internal Direct Labour Organisation or similar), where works sum exceeds £10K high
17 Adequate insurance arrangements to insure scheme for full cost of works not in place during development medium

4. Post-development breaches

Item number Breach Severity level
18 Practical Completion grant payment claimed in advance of need: this applies where the final grant claim preceded Partial Possession/Practical Completion (as defined in the CFG) high
19 At Practical Completion grant claim:
• there was no evidence of building regulations approval
• there was no evidence of building regulations sign-off completion certificate
• house builder warranty (National House Building Council or equivalent) final certificate not granted
high
20 Pre-commencement conditions and planning conditions precedent (except landscaping) or other specified consents have not been signed off/discharged by Practical Completion, and there is no evidence that the provider:
• has taken necessary steps to obtain them
• is waiting only for the relevant authority to issue them and
• is not aware of any reason why such consents will not be given or issued
medium
21 Adequate insurance arrangements to insure scheme for its Full Replacement Value not in place after development medium
22 The number of units built is lower than the contractual commitment, and no variation has been agreed high
23 The built units achieve a lower standard than that contractually agreed, and no variation has been agreed medium
24 The occupancy levels are lower than the contractual commitment, and no variation has been agreed medium
25 Conditions relating to management agreements have not been complied with medium
26 Affordable and social rent
The rents charged do not match the contractual commitments and/or programme requirements, and no variation has been agreed
medium
27 Affordable and social rent
Rents charged do not match those in IMS
medium

5. Sale breaches

Item number Breach Severity level
28 Shared ownership
Lease does not include all of the required fundamental clauses set out in the Shared Ownership chapter of the Capital Funding Guide
medium
29 Shared ownership
Adherence to applicant eligibility and/or financial assessment policies not evidenced
medium
30 Shared ownership
Rents not calculated according to the requirements of the CFG
medium
31 Shared ownership
Rent not calculated as the relevant percentage of unsold equity set out at bid stage
medium

6. Specialised housing breaches

Item number Breach Severity level
32 Additional conditions not complied with, and no waiver sought medium
33 The contractual requirement to register a restriction on title with Land Registry, indicating a requirement to gain HCA consent to dispose, has not been met medium

7. Additional breaches

Item number Breach Severity level
34 Other breach (including other funding conditions within contract not complied with) low
35 Other breach (including other funding conditions within contract not complied with) medium
36 Other breach (including other funding conditions within contract not complied with) high

8. Voluntary right to buy breaches

Item number Breach Severity level
37 Relevant documents not evident on file
Data not evident on internal systems
low
38 Systematic failure to evidence paperwork / data or adherence to procedures medium
39 Incorrect claim made for compensation, for example wrong amount claimed in IMS in relation to actual discount calculated
Claim for compensation made against a non-existent sale
high