Building Safety Remediation: monthly data release - January 2026
The 99th monthly data release regarding building safety remediation.
Applies to England
Documents
Details
This data release reports on building safety remediation, current at 31 January 2026. There is also an accompanying dashboard.
It includes remediation progress of buildings in the ACM programme, Building Safety Fund (BSF), Cladding Safety Scheme (CSS), developer remediation contract, and reported by registered providers of Social Housing. It also includes data on local authority enforcement action taken against 11m+ buildings with cladding defects.
The release includes the estimated number of residential buildings 11 metres and over in height in England that have or had unsafe cladding requiring remediation, as of January 2025.
The management information tables also include data on the progress of the Waking Watch Relief and Replacement Funds.
Updates to this page
-
The reported number of completed 18m+ buildings in the 'Overall remediation' and 'Overall remediation progress' sections of the data release has been reduced by 13 following the identification of an error. These buildings are now correctly reported as underway rather than complete. Figures 2-6, Table 5, and text in the relevant sections of the data release have been updated to show corrected information. In the management information tables, Combined_2 and Combined_4 - Combined_8 have all been corrected. In the Remediation dashboard, the 'Portfolio' page has been corrected.
-
First published.