Reformed National Pricing delivery plan: Chapter 2 - Siting and Investment Levers
Published 21 April 2026
The Department for Energy Security and Net Zero (DESNZ) is consulting on potential reforms to the Reformed National Pricing (RNP) siting and investment levers, including how these could be combined, as outlined in Chapter 2 of the RNP Delivery Plan.
It is important that these policy levers support delivery of the Strategic Spatial Energy Plan (SSEP) to reduce total system costs and consumer bills by influencing the location of new generation and storage projects in line with the SSEP’s requirements. This consultation therefore seeks views on potential reforms to the key siting and investment levers as part of RNP.
Please note that Ofgem (as the authority on Transmission Network Use of System Charges) has launched a Call for Input (closing on 26 May) setting out in more detail how the regulatory levers of network and connections charging could be reformed to align with RNP and support delivery of the SSEP. The Call for Input seeks views on additional design options and considers the treatment of legacy arrangements as part of the transition to any new regime. Feedback on these issues should be directed to the Ofgem Call for Input.
Please also note that, as referenced in Chapter 4 of the RNP Delivery Plan, the National Energy System Operator (NESO) published its Balancing and Settlement Call for Input (which closed on 14 April) as part of the wider RNP package. The focus was on reforming how the electricity grid is balanced, how power is dispatched and how settlements are calculated, and it considered issues separate from those raised in this consultation.
General information
Consultation details
Issued: 21 April 2026
Respond by: 2 June 2026
How to respond
Quality assurance
This consultation has been carried out in accordance with the government’s consultation principles.
If you have any complaints about the way this consultation has been conducted, please email: bru@energysecurity.gov.uk.
Consultation questions
Read Chapter 2 of the Reformed National Pricing (RNP): delivery plan.
Identifying Levers
Q 1a. Do you agree with the key levers that we have identified for supporting the delivery of the SSEP? Please provide rationale and evidence for your answers.
Q 1b. Do you think there are any other levers missing or alternatives that should be considered? If so, please list them and provide rationale and evidence for your suggestion.
Categorisation of levers
Q 2. Do you agree with how we have categorised the levers? Specifically
a. in your view, should Network Build, Seabed Leasing and Planning Reform be categorised as enabling levers; and
b. in your view should the Connections Regime, Locational Charging and Generation and Storage Investment Support Mechanisms be categorised as primary levers?
If no, please provide rationale and evidence for your answers.
Lever options – how to combine the levers
Q 3. What are your views on the overall strategic approach we have used for combining the levers into an options framework? For example, the logic and structure underpinning the options including the grid for how to combine the primary levers (Table 1).
Assessment criteria
Q 4. To what extent do you agree or disagree with the criteria we have used to assess the options? Please provide rationale and evidence to support your answer with particular reference to any other criteria that could be included in the assessment.
Initial assessment
Q 5. Do you agree with our preference for Options 2a, 2b, and 3 being suitable for further development with Options 0, 1 and 4 being discounted? Are there aspects of Options that you either think work particularly well, or that we should consider further? Please provide comments and further evidence to support your answer.
Q 6. How do you think the risks and disadvantages identified under Options 2a, 2b and 3 (as outlined above in this document) could be addressed?
Individual Levers – Connections Regime
Q 7a. Do you think it would be practical to set Connections Capacity Thresholds for Options 2a, 2b and 3, by SSEP technology and zone?
Q 7b. How should these thresholds be determined? Please provide rationale to support your answer.
Q 8a. Should we set the CCT at a level higher relative to the CSNP planning line to allow for project attrition and competition in investment support schemes? (i.e. the difference between Option 2a and 2b).
Q 8b. If we set the CCT above the SSEP Pathway, what additional safeguards might be needed to ensure we keep within the SSEP Pathway uncertainty range?
Individual Levers – Locational Charging
Q 9. What are your views on the role of locational charging, and interactions with our investment support schemes?
Note that detailed questions on potential TNUoS and connection charging reforms are covered in Ofgem’s recent Call for Input.
Individual Levers – Government investment support mechanisms
Q 10. For Options 2a, 2b and 3, what, if any, changes or reforms would be needed to government investment support mechanisms (such as the Contracts for Difference, Capacity Market etc), and if so, what specific reforms would be needed?