Consultation outcome

HS2 property compensation consultation 2013

This was published under the 2010 to 2015 Conservative and Liberal Democrat coalition government
This consultation has concluded

Detail of outcome

Following this consultation the government will introduce an HS2 property package as outlined in the HS2 property compensation consultation 2013 for the London to West Midlands route: decision document.

More about the new property package of measures:

Feedback received

Analysis and advisory work on a potential property bond scheme for property owners affected by plans for HS2

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email HS2enquiries@hs2.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

HS2 property compensation consultation 2013: consultation summary report

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email HS2enquiries@hs2.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Quality assurance review of HS2 property compensation consultation 2013 response analysis activity: final analysis report by the Consultation Institute

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email HS2enquiries@hs2.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Detail of feedback received

PWC’s property bond report was used to inform our decision about whether to set up a property bond scheme for eligible property owners affected by the HS2 Phase One line of route.

The consultation summary report by Dialogue by Design provides an overview of responses to the 2013 property compensation consultation for Phase One of HS2 between London and the West Midlands. A total of 17,780 responses were received for this consultation. Two hundred responses were from organisations; the remainder were submitted by members of the public.

We have also published the Consultation Institute’s quality assurance review of Dialogue by Design’s consultation response analysis activity.


Original consultation

Summary

This consultation seeks your views on the government’s proposals for property compensation schemes proposed along the HS2 Phase One line of route between London and the West Midlands.

This consultation ran from
to

Consultation description

This consultation seeks your views on the government’s proposals for property compensation schemes proposed along the HS2 Phase One line of route between London and the West Midlands.

Project phase

Phase One: between London and the West Midlands

Maps

You can view and access maps made available in support of this consultation via the links below, with the maps grouped in volumes and by the areas they relate to along the HS2 Phase One line of route from London to the West Midlands:

The sequence of maps follows the volume key plan, which should be consulted first prior to viewing subsequent maps in the volume. Please note that in map volumes 2 to 6 the last map from the previous volume is included as the first map in the next volume of maps for continuity purposes.

Updates to safeguarding in Bromford and Northolt

On 24 October 2013, updated safeguarding directions were issued for sections of the Phase One line of route between London and the West Midlands in Bromford and Northolt. They were updated following the outcome of our design refinement consultation for these areas. There will be further outcomes from the consultation in due course.

Maps showing the updated safeguarding area can be viewed on the HS2 website:

Information regarding the design refinement consultation can also be viewed on the HS2 website:

Consultation materials

All documents are provided in their original file size and in support of this consultation.

Where needed, low resolution versions of documents are provided due to the file size of some documents.

Additional documents

Documents

Consultation document

Consultation summary document

How to respond

Response form

Published 12 September 2013
Last updated 9 April 2014 + show all updates
  1. Consultation response and decision documents published.

  2. The page was updated to include information and links to the HS2 website following the publishing of updated safeguarding directions. They were updated following one of the outcomes of our Design Refinement consultation for Bromford and Northolt.

  3. First published.