Closed consultation

Accelerating electricity network connections for strategic demand

We are analysing your feedback

Visit this page again soon to download the outcome to this public feedback.

Summary

We're seeking views on proposals to amend the connections process to address speculation and prioritise future capacity for strategic demand, including data centres.

This consultation ran from
to

Consultation description

This consultation sets out proposals to use powers taken in the Planning and Infrastructure Act 2025 to implement reforms to the process for managing demand-side connections to the electricity network.

It presents measures to address speculation and prioritise future capacity for strategic demand, including data centres.

It covers:

  • the rationale for intervention
  • the appropriate legislative vehicle
  • the scope of application
  • the potential timing of implementation

The consultation is open to all, but we would like views in particular from:

  • industry stakeholders
  • regulated parties
  • connecting customers
  • the wider public

Documents

Updates to this page

Published 11 March 2026
Last updated 12 March 2026 show all updates
  1. Updates to Implementation section to give clarity on timing for distribution prioritisation measures.

  2. Worked examples in Annex 4 updated.

  3. First published.