Guidance

Inspecting street works

Code of practice for highway authorities on how to carry out inspections of street works.

Documents

Code of practice for street works inspections: April 2023

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email webmasterdft@dft.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

This code of practice gives guidance on inspecting street works including:

  • investigatory inspections and works
  • improvement plans
  • fee arrangements
  • reports
  • inspections involving coring

Inspections take place when works are:

  • in progress, making sure appropriate signs and barriers are in place to protect workers and road users
  • finished, making sure the site has been properly cleared and the road reinstated to a proper standard

The third edition of the code came into force on 1 April 2023, replacing all previous versions. It reflects:

  • the changes the government committed to implement following this consultation, in particular:

    • use performance to calculate the number of sample inspections of reinstatements carried out each year, so that poor performers are inspected more frequently
    • amend the way an inspection unit is calculated
    • consolidate the fee that needs to be paid for reinspections of reinstatements that have failed a previous inspection
Published 21 July 2011
Last updated 31 March 2023 + show all updates
  1. Changes following the third edition of the code, 1 April 2023.

  2. First published.