Potter House - High Flatts 66kV overhead line rebuild, S37 Consent, Electricity Act 1989
Screening decision to replace a 66kV H pole with a single pole and rebuild 150 metres of 66kV overhead line.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
29 May 2025
Location
High Flatts farm
Durham
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.