Decision
Murlach Development (redevelopment of Skua, part of the Marnock-Skua field)
Project Summary
Documents
Details
Murlach Development (redevelopment of Skua, part of the Marnock-Skua field) - BP Exploration Operating Company Limited - 2022 - ES/2022/002 - (Determined)
Key Dates
- Date Environmental Statement received by the department - 8 April 2022
- Public notice commencement date - 21 April 2022 and 29 April 2022
- Public notice closing date - 30 May 2022
- Further information public notice commencement date -
- Further information public notice closing date -
Environmental Statement & associated documents
- Summary of the Project – Received Date 8 April 2022
- Environmental Statement – Received Date 8 April 2022
- Public Notice – Received Date 21 April 2022
- Replacement Public Notice – Received Date 29 April 2022
Further Information
- Secretary of State request for provision of further information - 31 August 2022, 30 November 2022 and 23 May 2023
- Developer response to Secretary of State request for provision of further information - 21 October 2022, 19 April 2023 and 25 May 2023
- Further information public notice
Decision made by the Secretary of State
- Secretary of State notice under regulation 16(1) - 12 September 2023
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - Letter to the developer - 22 August 2023
- Secretary of State decision to agree to or refuse to agree to the OGA granting of consent - 22 August 2023