Decision

MN-Woolmer Forest SSSI overhead line, S37 Consent, Electricity Act 1989

Screening decision to replace one wooden pole as part of an 11kV, 2600 metres overhead line.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

8 January 2026

Location

Woolmer Forest
Hampshire

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 8 January 2026

Sign up for emails or print this page