This technical note (‘technical note 4’) investigates option A for a new Lower Thames Crossing, considering its integration with the M25 and A282 and associated traffic management and operational issues. The note responds to part of a brief to Jacobs/AECOM provided by the Department for Transport.

Published 15 July 2014