Ivy Lodge overhead line (EWT664), S37 Consent, Electricity Act 1989
Screening decision to upgrade approximately 500m of an existing 11kV overhead line from single phase to three phase.
Applies to England
Documents
Details
Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.
Date of decision
25 July 2025
Location
Ivy Lodge
Cirencester
Cotswolds
Type of project / consent requested
Section 37 consent to install or keep installed an electric line.