GLOS/41/JOH/LAWSFM4882936 overhead line, S37 Consent, Electricity Act 1989

Screening decision to upgrade approximately 592 metres of an existing 2 wire 11 kV overhead line to 3 wires, replace four poles on a like for like basis and install an H Pole to support a 200kVa pole mounted transformer.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

14 March 2025

Location

Gloucestershire

Section 37 consent to install or keep installed an electric line.