Decision

East End FBS163 overhead line, S37 Consent Electricity Act 1989

Screening decision to upgrade an existing pole mounted transformer to a 200 kVA and install one pole to an existing pole to form a H pole.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

25 September 2024

Location

New Forest
Hampshire

Section 37 consent to install or keep installed an electric line.