Decision

CW52209 Hydes Lane, Hinckley overhead line, S37 Consent, Electricity Act 1989

Screening decision to install two new 132kV towers with sealing end platforms to create a looped connection for the 49.5MV battery storage site at Hydes Lane.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

10 April 2025

Location

Hydes Lane
Hinckley
Leicestershire

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 10 April 2025

Sign up for emails or print this page