Participants who have not complied with their legal requirements and received a civil penalty:

Deluxe Laboratories Limited

Failure to surrender sufficient allowances for the 2014/15 compliance year by 31 October 2015, contrary to Article 77 of the CRC Order 2013.

Penalty £5,000 (published January 2017).

Aquaterra Leisure

Failure to surrender sufficient allowances for the 2013/14 compliance year by 31 October 2014, contrary to Article 100 of the CRC Order 2010.

Penalty £250 (published January 2017).

Aquaterra Leisure

Failure to submit an annual report for the 2014/15 compliance year by 31 July 2015, contrary to Article 74 of the CRC Order 2013.

Penalty £500 (published January 2017).

ALS Testing Services (UK) Limited

Failure to submit an annual report for the 2014/15 compliance year by 31 July 2015, contrary to Article 74 of the CRC Order 2013.

Penalty £13,500 (published January 2017).

The University of Hull

Failure to submit an annual report for the 2014/15 compliance year by 31 July 2015, contrary to Article 74 of the CRC Order 2013.

Penalty £6,150 (published January 2017).

Mansion Student Accommodation Fund

Failure to submit an annual report for the 2014/15 compliance year by 31 July 2015, contrary to Article 74 of the CRC Order 2013.

Penalty £2,580 (published January 2017).

-99p Stores Limited

Failure to submit an annual report for the 2014/15 compliance year by 31 July 2015, contrary to Article 74 of the CRC Order 2013.

Penalty £13,500 (published January 2017).

Transport for London

Failure to surrender sufficient allowances for the 2013/14 compliance year by 31 October 2014, contrary to Article 100 of the CRC Order 2010.

Penalty £20,000 (published November 2016).

Havelock Europa PLC

Failure to surrender sufficient allowances for the 2013/14 compliance year by 31 October 2014, contrary to Article 100 of the CRC Order 2010.

Penalty £5,000 (published November 2016).

MacDermid Continental Investments Limited

Failure to surrender sufficient allowances for the 2013/14 compliance year by 31 October 2014, contrary to Article 100 of the CRC Order 2010.

Penalty £2,500 (published November 2016).

VTX Holdings Limited

Failure to surrender sufficient allowances for the 2013/14 compliance year by 31 October 2014, contrary to Article 100 of the CRC Order 2010.

Penalty £2,500 (published November 2016).

Flamingo Land Resort Limited

Failure to submit an annual report for the 2013/14 compliance year by 31 July 2014, contrary to Article 47 of the CRC Order 2010.

Penalty £2,940 (published November 2016).

Champneys Henlow Limited

Failure to surrender sufficient allowances for the 2013/14 compliance year by 31 October 2014, contrary to Article 100 of the CRC Order 2010.

Penalty £10,000 (published November 2016).

The Planning Inspectorate

Failure to submit an annual report for the 2013/14 compliance year by 31 July 2014 contrary to Article 47 of the Order 2010.

Penalty £2,850 (published March 2016).

Merkur Casino UK Limited

Submitting an inaccurate report for the 2012/13 reporting year contrary to Article 47 of the Order 2010.

Penalty £3,466 (published March 2016).

Stobart Transport and Distribution Limited (formerly Stobart Holdings Ltd)

Submitting an inaccurate report for the 2012/13 reporting year contrary to Article 47 of the Order 2010.