Final auction parameters, T-1 and T-4 Capacity Market auctions
Published 10 February 2026
Table 1: Final auction parameters
| T-1 Auction for delivery in 2026/27 | T-4 Auction for delivery in 2029/30 | |
|---|---|---|
| Auction target capacity | 6.3 GW | 39.4 GW |
| Demand curve: minimum capacity at price cap | 5.3 GW | 37.9 GW |
| Demand curve: maximum capacity at £0 | 7.3 GW | 40.9 GW |
| Reliability Standard | 3 hours LOLE | 3 hours LOLE |
| Net CONE | £49/kW/yr | £49/kW/yr |
| Price Cap | £75/kW/yr | £75/kW/yr |
| Price Taker Threshold | £25/kW/yr | £25/kW/yr |
| 15-year agreement threshold | N/A[footnote 1] | £350/kW[footnote 2] |
| 9-year agreement threshold (for eligible Declared Low Carbon CMUs only) | N/A[footnote 1] | £205/kW[footnote 3] |
| 3-year agreement threshold (for non-Three Year Zero Capex Threshold CMUs) | N/A[footnote 1] | £65/kW[footnote 4] |
| 3-year agreement zero threshold (for eligible Three Year Zero Capex Threshold CMUs only)[footnote 5] | N/A[footnote 1] | £0/kW |
| Indexation | N/A[footnote 1] | 2024/25 |
-
Multi-year agreements are not awarded in the T-1 auction. ↩ ↩2 ↩3 ↩4 ↩5
-
The 15-year agreement threshold is adjusted from the previous T-4 value (for the 2028/29 Delivery Year) for inflation, indexed to the 2024/25 inflation level, and rounded to the nearest £5. ↩
-
As noted in the July 2025 auction parameters, the 9-year agreement threshold has been introduced for the upcoming auctions, as described in the Phase 2 response update. The threshold is set as the midpoint between the 3-year (for non-Three Year Zero Capex Threshold CMUs) and 15-year agreement thresholds, rounded to the nearest £5. ↩
-
As per July 2025, the 3-year agreement threshold (for non-Three Year Zero Capex Threshold CMUs) was decreased to £65/kW to facilitate lifetime extensions as described in this consultation response. ↩
-
As defined in Rule 1.2 of the Capacity Market Rules, as described in the Phase 2 response update. ↩