105191-190/ Allhallows overhead line, S37 Consent, Electricity Act 1989

Screening decision to dismantle 8 existing poles and install 5 intermediate poles and 3 section poles. 10 stays and blocks to be installed. Upgrade 3 spans to 3-phase of 410m, 11kV line.

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

7 May 2026

Location

Rochester
Kent

Type of project/consent requested

Section 37 consent to install or keep installed an electric line.

Updates to this page

Published 7 May 2026