TCM1000610 - How to check the number of days in the UY period through function 'Award View'

Step 1

On the ‘Function Menu’

  • select ‘Award’ on the toolbar
  • select ‘View’. You will be taken to the ‘Key Entry Data - Applicant’ screen
  • enter the customer’s Nino
  • select the ‘Latest’ checkbox
  • select ‘OK’
  • go to Step 2.

Step 2

On the ‘AMBS - Award Summary - Sterling’ screen

  • select ‘View Calculation’. You will be taken to the ‘AMBS - View Calculation - Sterling’ screen
  • select ‘View Elements’. You will be taken to the ‘AMBS - View Elements - Sterling’ screen
  • the number of days in the UY period is listed under the heading ‘Days’

Note: If a customer has had any changes in circumstances resulting in an award change, you will need to add the number of days in each period together.

  • select ‘Cancel’ to close the claim.