Section 16 of the Business and Planning Act 2020 inserts section 74B into the Town and Country Planning Act 1990. It provides a temporary, fast track deemed consent route to apply to a local planning authority to vary existing conditions, or the details submitted under a condition, that limit construction site working hours. If that application is refused by the local planning authority then there is a right of appeal.

Before deciding to submit the appeal, it would be advisable to consider the government guidance as well as any reasons for refusal given by the local planning authority.

How to appeal:

Documents you must provide:

  • supporting information submitted to the local planning authority
  • any supporting statement submitted by the appellant should be limited to 1,000 words and directly address the reason for refusal
  • if helpful include photographs showing the location of any properties alleged to be affected by the proposed increase in hours
  • any statement from the local planning authority should also not exceed 1,000 words

How the appeal will be dealt with:

  • the appeal should be validated within 7 days - if not please contact the Planning Inspectorate
  • in order to receive the appeal, seek comments from third parties and statements from the local planning authority and allow for final comments from the appellant the legislation prescribes a minimum of 7 weeks
  • an Inspector will be appointed as soon as possible
  • we do not expect that site visits will be required
  • decisions will be despatched as soon as is feasible once the prescribed processes have been completed
  • if the appeal is allowed, then the planning restrictions on construction working hours will be amended temporarily

You can contact the Planning Inspectorate at enquiries@planninginspectorate.gov.uk