TA5 1UD, NNB Generation Company (HPC) Limited: environmental permit issued - EPR/ZP3238FH/V004

View the permit issued for Hinkley Point C Power Station, Near Bridgwater under the Industrial Emissions Directive.

Applies to England

Documents

Permit: NNB Generation Company (HPC) Limited

Request an accessible format
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email enquiries@environment-agency.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Decision document: NNB Generation Company (HPC) Limited

Request an accessible format
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email enquiries@environment-agency.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

The Environment Agency publish permits that they issue under the Industrial Emissions Directive (IED).

This decision includes the permit and decision document for:

  • Operator name: NNB Generation Company (HPC) Limited
  • Installation name: Hinkley Point C Power Station
  • Permit number: EPR/ZP3238FH