Statutory guidance

SR2019 No 1: installation of mooring pile in a main river

Standard rules for installation of mooring pile in a main river.

Applies to England

Documents

SR2019 No 1: installation of mooring pile in a main river

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email enquiries@environment-agency.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Generic Risk Assessment for SR2019 No 1: installation of mooring pile in a main river

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email enquiries@environment-agency.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

These rules allow you to install a mooring pile into a main river.

These rules do not allow the activity:

  • within 8 metres of a flood defence
  • within 50m of another mooring pile
  • during the fish breeding season
Published 1 August 2019