Decision

Sizewell C Variation 3

Details of Sizewell C Variation 3

Documents

Formal Variation Request - 10/03/2026

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

MMO DML Variation Cover Letter

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Notice of Variations for Schedules 21

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Amended DML for Schedule 21 of The Sizewell C (Nuclear Generating Station) Order 2022

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

On 20 December 2022 the Secretary of State for Business, Energy and Industrial Strategy granted consent for the Sizewell C (Nuclear Generating Station) Order 2022, which contains within Schedule 21 a deemed marine licence (DML) in accordance with Section 149 of the Planning Act 2008. The Sizewell C (Nuclear Generating Station) Order 2022 has since been amended in September 2023.

The pre-application, examination and development consent order (DCO) documents for this project can be found on the Planning Inspectorate’s website.

On 10 March 2026 the Marine Management Organisation (MMO) received a request from Sizewell C Limited to vary the DML contained within Schedule 21 of the Sizewell C (Nuclear Generating Station) Order 2022.

This variation request concerned changes to the wording of Condition 36(3). This change provides Sizewell C with the option to submit a request to the MMO to undertake impact piling activities between May and August of any year, which would otherwise be restricted by Condition 36(3).

The MMO’s decision was to vary the DML as detailed in the Decision Letter and Notice of Variation, effective from 27 March 2026.