Statutory guidance

Co-ordinating street works

Code of practice for local authorities who have a duty to co-ordinate works in the highway, and for undertakers on how to co-operate in the process.

Documents

Code of practice for the co-ordination of street works and works for road purposes and related matters: March 2026

Request an accessible format
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email webmasterdft@dft.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

This code of practice provides practical guidance on the responsibilities of authorities and undertakers under the New Roads and Street Works Act (1991) (NRSWA).

It applies from 10 April 2026 and helps:

  • local authorities to coordinate works in the highway under section 59 of NRSWA
  • undertakers to fulfil their duty to co-operate in this process under section 60 of NRSWA

It reflects the Traffic Management Permit Scheme (England) (Amendment) Regulations 2026, which grants electric vehicle chargepoint operators access to street works permits on the same basis as statutory undertakers.

The code also reflects the Street and Road Work Charges and Penalties Regulations 2025, which:

  • increased the level of fixed penalty notices for street works offences
  • extended overrun charges to weekends and bank holidays where work extends beyond the agreed duration