Decision

East Anglia ONE North Offshore Windfarm - Variation 1

Details of East Anglia ONE North Offshore Windfarm variation 1 decision.

Documents

Formal Variation Request- 06 October 2025

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

MMO DML Variation Decision Cover Letter

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Notice of Variations for Schedule 13

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Notice of Variations for Schedule 14

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Amended DMLs for Schedule 13 of the East Anglia (EA) ONE North Offshore Wind Farm Order 2022

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Amended DMLs for Schedule 14 of the East Anglia (EA) ONE North Offshore Wind Farm Order 2022

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email communications@marinemanagement.org.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

In April 2022 the Secretary of State for the Department for Business, Energy and Industrial Strategy (BEIS) granted consent for the East Anglia (EA) ONE North Offshore Wind Farm Order 2022 (“the Order”) which included, in Schedules 13 and 14, Deemed Marine Licences (DMLs) in accordance with Section 149 of the Planning Act 2008.

This wind farm has the benefit of development consent. The pre-application, examination and DCO documents can be found on the Planning Inspectorate’s website.

On 06 October 2025 the Marine Management Organisation (MMO) received a request from Scottish Power Renewables to vary the Deemed Marine Licences (DML) contained within Schedules 13 and 14 of EA ONE North Offshore Wind Farm Order 2022.

The MMO’s decision was to vary the DMLs as detailed in the Notices of Variation, effective from 04 February 2026.