Full details of auction parameters and interconnector de-rating factors
Published 15 July 2025
Table 1: Auction parameters
T-1 Auction for delivery in 2026/27 | T-4 Auction for delivery in 2029/30 | |
---|---|---|
Auction target capacity | 5.8 GW | 39.1 GW |
Demand curve: minimum capacity at price cap | 4.8 GW | 37.6 GW |
Demand curve: maximum capacity at £0 | 6.8 GW | 40.6 GW |
Reliability Standard | 3 hours LOLE | 3 hours LOLE |
Net CONE | £49/kW/yr | £49/kW/yr |
Price Cap | £75/kW/yr | £75/kW/yr |
Price Taker Threshold | £25/kW/yr | £25/kW/yr |
15-year agreement threshold | N/A[footnote 1] | £350/kW[footnote 2] |
9-year agreement threshold (for eligible Declared Low Carbon CMUs only) | N/A[footnote 1] | £205/kW[footnote 3] |
3-year agreement threshold (for non-Three Year Zero Capex Threshold CMUs) | N/A[footnote 1] | £65/kW[footnote 4] |
3-year agreement zero threshold (for eligible Three Year Zero Capex Threshold CMUs only)[footnote 5] | N/A[footnote 1] | £0/kW |
Indexation | N/A[footnote 1] | 2024/25 |
Table 2: Interconnector de-rating factors (DRF)
T-1 auction for the 2026/27 delivery year[footnote 6] | T-1 auction for the 2026/27 delivery year[footnote 6] | T-4 auction for the 2029/30 delivery year | T-4 auction for the 2029/30 delivery year | ||
---|---|---|---|---|---|
Interconnector | Connection capacity (GW) | NESO range (%) | DRF (%) | NESO range (%) | DRF (%) |
IFA (France) | 2 | - | - | 54-92 | 62 |
IFA2 (France) | 1.1 | - | - | 54-92 | 64 |
ElecLink (France) | 1 | - | - | 54-92 | 68 |
BritNed (Netherlands) | 1.2 | - | - | 46-90 | 67 |
Moyle (Northern Ireland) | 0.5 | - | - | 7-85 | 60 |
EWIC (Republic of Ireland) | 0.5 | - | - | 7-85 | 60 |
Greenlink (Republic of Ireland) | 0.5 | - | - | 7-85 | 60 |
NemoLink (Belgium) | 1 | - | - | 54-92 | 68 |
NSL (Norway) | 1.4 | - | - | 51-89 | 70 |
VikingLink (Denmark) | 1.4 | - | - | 32-86 | 63 |
Neuconnect (Germany) | 1.4 | - | - | 40-88 | 63 |
-
Multi-year agreements are not awarded in the T-1 auction. ↩ ↩2 ↩3 ↩4 ↩5
-
The 15-year agreement threshold is adjusted from the previous T-4 value (for the 2028/29 Delivery Year) for inflation, indexed to the 2024/25 inflation level, and rounded to the nearest £5. ↩
-
The 9-year agreement threshold has been introduced for the upcoming auctions, as described in the Phase 2 response update. The threshold is set as the midpoint between the 3-year (for non-Three Year Zero Capex Threshold CMUs) and 15-year agreement thresholds, rounded to the nearest £5. ↩
-
The 3-year agreement threshold (for non-Three Year Zero Capex Threshold CMUs) was decreased to £65/kW to facilitate lifetime extensions as described in this consultation response. ↩
-
As defined in Rule 1.2 of the Capacity Market Rules, as described in the Phase 2 response update. ↩
-
For the T-1 auction, all interconnectors expected to be operational for 2026/27 already hold capacity agreements for the 2026/27 delivery year. ↩ ↩2