Building Safety Remediation: monthly data release - November 2024
Published 19 December 2024
Applies to England
Date of next publication: 9.30am on Thursday 23 January 2025.
All figures in this release can also be found in an interactive dashboard.
Headlines
Overall remediation
As at the end of November 2024, there are 4,998 residential buildings 11 metres and over in height identified with unsafe cladding whose remediation progression is being reported on in this release, an increase of 164 since the end of October 2024.
Since the department first began reporting on all five remediation programmes in October 2023, 1,201 more buildings with unsafe cladding are being reported on in this release.
Overall, 2,397 buildings (48%) have either started or completed remediation works. Of these, 1,463 buildings (29%) have completed remediation works. The number of buildings reported to have started or completed remediation works has decreased since October 2024, mainly due to data revisions from some Registered Providers of social housing.
Figure 1: Of the 4,998 buildings identified with unsafe cladding, 2,397 (48%) have started or completed remediation works, of which 1,463 (29%) have completed remediation works. This includes remediation progress on high rise (18m+) and mid-rise (11-18m) buildings in height.
Note: From October 2023 onwards combined remediation progress is shown across the BSF, ACM programme, Cladding Safety Scheme, developer remediation contract and as reported by registered providers of social housing. The total number of buildings does not sum to the total number of buildings reported in each respective section of the data release due to crossover between schemes.
The increase in the number of reported completions between May and June 2024 is largely due to a change in methodology in reporting social housing sector remediation, which from June 2024 includes social housing buildings that had completed remediation independently of government funding and monitoring schemes before March 2024.
ACM remediation – monthly update (as at end November 2024) since previous publication
As at 30 November 2024 of the 514 high-rise (18 metres and over in height) residential and publicly owned buildings with ACM cladding systems, unlikely to meet Building Regulations, 492 (96%) have either started or completed remediation works, an increase of two since the end of October.
Of these, 444 buildings (86%) have completed ACM remediation, including those awaiting building control sign-off, no change since the end of October.
There are 22 buildings yet to start ACM remediation (4% of all buildings), a decrease of two since the end of October. One building is vacant so does not pose a risk to resident safety, 17 occupied buildings have forecast start dates, two further buildings have had local authority enforcement action taken against them, and the remaining two buildings have come into scope in recent months.
Building Safety Fund (BSF) – monthly update (as at end November 2024) since previous publication
As at 30 November 2024, of the 809 high-rise (18 metres and over in height) residential buildings proceeding with an application for funding through the Building Safety Fund, 164 buildings (20%) have started remediation works and 357 buildings (44%) have completed remediation on unsafe non-ACM cladding, including those awaiting building control sign-off.
Overall, 521 high-rise buildings (64%) in the BSF have either started or completed remediation works on non-ACM cladding, an increase of three since the end of October. Of these, 357 buildings (44% of buildings) have completed remediation works, an increase of five since the end of October.
Cladding Safety Scheme (CSS) – monthly update (as at end November 2024) since previous publication
As at 30 November 2024, 492 buildings 11 metres and over in height have been assessed as eligible for the Cladding Safety Scheme (including 109 buildings that have transferred from the BSF), an increase of 32 since the end of October. Of these, 46 buildings (9%) have either started or completed remediation works, an increase of 15 since the end of October. Of these, 16 buildings (3%) have completed remediation works, including those awaiting building control sign-off, an increase of 2 since the end of October.
The CSS continues to investigate and pull in potentially eligible buildings. There are a further 2,046 buildings 11 metres and over in height in the pre-eligible stages of the Cladding Safety Scheme, which launched fully in July 2023. Of these, 345 buildings are progressing through eligibility checks, and 1,701 buildings are in the pre-application stage.
Developer remediation – data received from developers as at 31 October 2024. Data received from other programmes relating to developer-led remediation is as at 30 November 2024
Data received from developers is accurate as at 31 October 2024, except for one developer (Frasers Property) who did not submit data within the deadline. For this developer, the data release uses the data they submitted as at 31 July 2024.
As at 30 November 2024, 1,746 buildings 11 metres and over in height have been identified as having life-critical fire safety defects (including cladding and non-cladding defects) which developers have committed to remediate or pay to remediate (where the cladding remediation works are being carried out in a government funded remediation programme), an increase of 117 since reported in the October data release.
Of these, developers reported that 850 (49%) have either started or completed remediation works, an increase of 78 since reported in the October data release. Of these, 439 (25% of buildings) are reported to have completed remediation works, an increase of 26 since reported in the October data release.
When excluding buildings reported with only non-cladding defects, there are 1,536 buildings which developers have reported as having unsafe cladding, of which 790 (51%) are reported to have started or completed remediation, including 397 (26% of buildings) which are reported to have completed remediation.
Social housing sector – data received from Registered Providers of social housing as at 30 September 2024, data received from other programmes relating to social housing sector remediation is as at 30 November 2024
As at 30 November 2024, 2,606 social buildings 11 metres and over in height have been identified as having life-critical fire-safety cladding defects. This is an increase of 67 since reported in the October data release. These have been identified using survey data submitted by Registered Providers of social housing and data on buildings the department is monitoring under other government programmes (ACM programme, BSF, CSS and Developer Remediation contract).
Of these, 1,176 (45%) are reported to have started or completed remediation works - this is 120 lower than the number reported in the October data release. This fall in the number reported is driven by Registered Providers making revisions to their data returns following the addition of more detailed questions on start and completion dates. The status of 187 buildings were changed to not having cladding defects or from having started or completed remediation to not having started remediation. In addition, Registered Providers added 67 buildings with cladding defects that have started or completed remediation or updated the status of buildings with cladding defects from not having started remediation to having started or completed remediation.
As at 30 November 2024, 728 (28% of buildings) have completed remediation, an increase of 24 since reported in the October data release.
Enforcement – monthly update (as at 25 November 2024) since previous publication
As at 25 November 2024, local authority enforcement action has been, or is being, taken under the Housing Act 2004 against 499 buildings over 11m with unsafe cladding, an increase of 16 since the end of October.
Introduction
This Data Release provides data on:
- Remediation progress across MHCLG’s Building Safety Remediation portfolio, covering buildings in the ACM programme, Building Safety Fund, Cladding Safety Scheme, developer remediation contract and reported by registered providers of social housing
- Progress with remediation of high-rise (18 metres and over in height) residential buildings (including student accommodation and hotels) and publicly owned buildings with ACM cladding systems unlikely to meet Building Regulations in the ACM programme
- Progress with remediation of high-rise residential buildings with non-ACM cladding systems assessed as eligible for funding from the Building Safety Fund
- Progress with the applications for and remediation of medium-rise (11 – 18 metres in height) residential buildings in England, and Northern Ireland, and high-rise residential buildings outside of London with non-ACM cladding systems in the Cladding Safety Scheme
- Progress of remediation of residential buildings 11 metres and over in height with life-critical fire safety risks under the developer remediation contract
- Progress of remediation of residential buildings 11 metres and over in height with unsafe cladding reported by registered providers of social housing
- Enforcement action taken by local authorities against high-rise residential buildings with unsafe cladding under the Housing Act 2004.
The data in Figure 1 and the overall remediation progress section of the data release, shows the combined remediation progress across MHCLG’s Building Safety Remediation portfolio, covering buildings and accounting for crossover in the ACM programme, Building Safety Fund, Cladding Safety Scheme, developer remediation contract and reported by registered providers of social housing.
The figures in this publication are correct as at the specified dates. Remediation progress on the ACM programme, BSF and CSS will be updated monthly, and remediation progress on the developer remediation contract and registered providers of social housing will be updated quarterly.
Enquiries
Contact: BuildingSafetyData2@communities.gov.uk
Media enquiries: 0303 444 1209
User Engagement
We are committed to improving and broadening this data release further in the months ahead and would welcome feedback both on the revised content of this data release and what could be further done in the future. Please contact BuildingSafetyData2@communities.gov.uk
Dates of future publications
The publication dates for the next three months are:
- 23 January 2025
- 20 February 2025
- 20 March 2025
Building Safety overview
This data release publishes data across all government remediation activities to give an overview of the status of progress to remediate unsafe cladding on residential buildings over 11m in England. This includes:
- Data relating to the Aluminium Composite Material (ACM) cladding programme – those highest risk buildings that are high-rise buildings with unsafe, ‘Grenfell-style’ ACM cladding
- Data relating to the Building Safety Fund, which funds the remediation of eligible high-rise residential buildings with other forms of unsafe cladding
- Data relating to the Cladding Safety Scheme, which funds the remediation of residential buildings over 11m in height with unsafe cladding
- Data relating to developer-led remediation, which reports on those buildings that developers have agreed to remediate
- Data on residential buildings over 11m in height that are the responsibility of registered social housing providers.
Overall remediation progress
Figure 2: 2,397 residential buildings (48% of identified buildings) have started or completed remediation on unsafe cladding, of which 1,463 (29% of identified buildings) have completed remediation works.
Remediation Stage | Number of buildings | Percentage | Cumulative Number | Cumulative Percentage |
---|---|---|---|---|
Remediation complete | 1463 | 29% | 1463 | 29% |
Remediation underway | 934 | 19% | 2397 | 48% |
In programme | 2601 | 52% | 4998 | 100% |
Total | 4998 | 100% | 4998 | 100% |
Table 1 Remediation progress for buildings monitored by MHCLG in the ACM programme, Building Safety Fund, the CSS, the developer remediation contract, and social housing surveys, England, 30 November 2024.
Overall remediation: key statistics
Of the 4,998 residential buildings 11 metres and over in height with unsafe cladding the department is monitoring, as at 30 November 2024:
- 1,463 buildings (29%) have completed remediation, including those awaiting building control sign off
- 934 buildings (19%) have started remediation
- 2,601 buildings (52%) have not started remediation
Since the end of October 2024:
- The department is monitoring the remediation progress of 164 more buildings.
- 22 fewer buildings are known to have started or completed remediation, and 27 more buildings are known to have completed remediation.
- Excluding the 126 buildings which Registered Providers of social housing have revised the remediation status of which were previously reported as having started or completed remediation, 104 more buildings across the programmes are known to have started or completed remediation.
Since the end of November 2023:
- The department is monitoring the remediation progress of 1,174 more buildings, largely due to more buildings being identified with unsafe cladding in the CSS, and reported by developers and social housing registered providers.
- 794 more buildings are known to have started or completed remediation, of which 686 more buildings are known to have completed remediation.
There are an estimated 272,000 dwellings in the occupied private and social sector 11m+ residential buildings with unsafe cladding that the department are monitoring. Of these an estimated 91,000 dwellings are in buildings that have completed remediation, and an estimated 57,000 additional dwellings are in buildings that have started remediation. An estimated 124,000 dwellings are in buildings that have not started remediation.
Figure 3: Progress of remediating unsafe cladding differs across the programmes due to the differing maturity of the schemes.
Overall remediation by height
Figure 4: 56% of the 18m+ buildings the department is monitoring the remediation progress of have started or completed remediation on unsafe cladding, compared to 36% of 11-18m buildings
Overall remediation by tenure
Figure 5: 45% of the social buildings the department is monitoring the remediation progress of have started or completed remediation on unsafe cladding, compared to 49% of the private buildings.
The ‘Other’ bar includes high-rise buildings with unsafe ACM that are hotels, student accommodation and public buildings.
Overall remediation by location
Figure 6: Most buildings that the department are monitoring the cladding remediation of are concentrated around urbanised areas in England, particularly the urban areas of Greater London, Greater Manchester, West Yorkshire and the south coast
Local authorities with 10 or fewer 11m+ buildings monitored with unsafe cladding are excluded from this map as their inclusion could lead to the identification of buildings with unsafe cladding.
ACM remediation
Information in this section is correct as at 30 November 2024 and shows a monthly update from the previous publication.
Figure 7: 96% of the 514 identified ACM clad high-rise buildings have started or completed remediation, with 92% having had their ACM cladding removed and 86% having completed remediation.
Remediation Stage | Number of buildings | Percentage | Cumulative number | Cumulative Percentage |
---|---|---|---|---|
Remediation Complete | 416 | 81% | 416 | 81% |
Remediation Complete awaiting building control sign off | 28 | 5% | 444 | 86% |
Remediation started – cladding removed | 31 | 6% | 475 | 92% |
Remediation started | 17 | 3% | 492 | 96% |
Remediation plans in place | 18 | 4% | 510 | 99% |
Intent to remediate | 1 | <1% | 511 | 99% |
Remediation plan unclear | 3 | 1% | 514 | 100% |
Total | 514 | 100% | 514 | 100% |
Table 2: Remediation status of buildings with ACM cladding systems unlikely to meet Building Regulations, 30 November 2024
ACM Remediation: key statistics
As of 30 November 2024, the department has identified 514 high-rise residential and publicly owned buildings identified with ACM cladding systems unlikely to meet Building Regulations, no change since the end of October.
- 444 buildings (86% of all buildings) have completed ACM remediation – no change since the end of October. Of these, 416 buildings (81% of all buildings) have received building control sign off – no change since the end of October.
- 492 buildings (96% of all buildings) have started or completed ACM remediation – an increase of two since the end of October. Of these, 475 buildings (92% of all buildings) have removed ACM cladding – no change since the end of October.
There are an estimated 26,700 – 30,000 dwellings in private and social sector buildings that have completed remediation, and a further 5,300 – 5,400 dwellings in occupied private and social sector buildings that have yet to be remediated.
Driving ACM remediation forward
There are 22 buildings yet to start ACM remediation (4% of all buildings) – a decrease of two since the end of October. One building is vacant so does not pose a risk to resident safety.
Remediation Stage | All occupied buildings yet to start remediation | Of which: | |||
---|---|---|---|---|---|
Enforcement action | Enforcement action supported by Joint Inspection Team | Forecast start available | Forecast to start by the end of December 2024 | ||
Total | 21 | 10 | 4 | 17 | 0 |
Table 3: Enforcement action and forecast start dates for occupied high-rise buildings yet to start ACM remediation, 30 November 2024
Of the 21 high-rise occupied buildings yet to start ACM remediation:
- 17 buildings are forecast to start works in 2025, and 8 of these have had local authority enforcement action taken against them.
- Two further buildings without a forecast start date have had local authority enforcement action taken against them.
- The remaining two buildings have been determined as in scope of the ACM monitoring programme in recent months, and the department continues to engage with building owners to ensure their remediation is progressed.
These forecast estimates are based on information provided by building owners and agents and may change as further information is received. These estimates can also change as a result of buildings being newly identified. The department continues to engage with building owners to start remediation works on site as soon as possible, and will continue to support local authorities and fire and rescue services in the use of their enforcement powers.
Figure 8: 96% of buildings are forecast to have started or completed ACM remediation works by the end of December 2024.
ACM remediation progress by year of identification
Figure 9: 99% of buildings identified at 31 December 2022 have started or completed remediation compared to 96% of all buildings in the programme.
Since 31 December 2021, 33 further high-rise residential buildings have been identified with ACM cladding systems unlikely to meet Building Regulations and have moved into scope of the Building Safety Programme. Of these, six buildings were identified in 2022, eight in 2023 and 19 in 2024.
Year of identification | Number of buildings identified | Cumulative number |
---|---|---|
2017-2019 | 428 | 428 |
2020 | 31 | 459 |
2021 | 22 | 481 |
2022 | 6 | 487 |
2023 | 8 | 495 |
2024 | 19 | 514 |
Total | 514 | 514 |
Table 4: Buildings with unsafe ACM cladding by year of identification, 30 November 2024.
ACM remediation by sector
Figure 10: 99% of the 162 social sector residential buildings in the ACM programme have started or completed remediation, compared to 92% of the 252 private sector residential buildings.
Building Safety Fund
Information in this section is correct as at 30 November 2024 and shows a monthly update from the previous publication.
Figure 11: 64% of buildings proceeding with an application for funding in the BSF have started or completed remediation, with 44% having completed remediation.
Remediation Stage | Number of buildings | Percentage | Cumulative Number | Cumulative Percentage |
---|---|---|---|---|
Remediation Complete | 223 | 28% | 223 | 28% |
Remediation Complete awaiting building control sign off | 134 | 17% | 357 | 44% |
Remediation started | 164 | 20% | 521 | 64% |
Remediation plans in place | 141 | 17% | 662 | 82% |
Intent to remediate | 147 | 18% | 809 | 100% |
Total | 809 | 100% | 809 | 100% |
Table 5: Remediation status of buildings within the Building Safety Fund, 30 November 2024.
BSF remediation: key statistics
As at 30 November 2024, 809 buildings were assessed as eligible and are proceeding with an application for funding from the Building Safety Fund. The remaining 2,857 buildings registered with the fund are either ineligible (1,111), withdrawn (1,599), in review or have given insufficient evidence (23), or have transferred to the Cladding Safety Scheme (124).
Of the 2,857 buildings that registered with the Building Safety Fund and are not currently proceeding with an application for funding, 454 buildings which were assessed as eligible have been transferred to developers.
As at 30 November, 124 buildings have transferred to the Cladding Safety Scheme for their remediation (where works have not yet started on site) and are progressing through the CSS process. The number of buildings reported as transferred from the BSF to the CSS in this section of the data release may not be the same as the number of eligible CSS buildings that have transferred from the BSF in the CSS section of the data release. This is because transferred buildings will go through CSS eligibility checks before buildings are included in the eligible CSS figures.
Of the 809 buildings proceeding with an application for funding in the Building Safety Fund:
- 171 buildings (21%) are remaining in the fund with developers set to reimburse the cost of remediation,
- Nine buildings (1%) are anticipated to be transferred to developers
Of the 809 buildings proceeding with an application for funding, 180 buildings have been assessed with a Fire Risk Appraisal for External Walls (FRAEW), and 629 have been assessed under the BSF 2020 CAN criteria. It is possible for a building to submit a new application to the fund after having completed remediation, if it originally applied under the BSF 2020 CAN criteria. Therefore buildings could be double counted. As of 30 November 2024 one building had undertaken remediation work from both application periods, so is double counted. Further details are available in the technical note.
Of the 809 buildings proceeding with an application for funding, 521 buildings (64%) have either started or completed remediation works – an increase of three since the end of October.
Of the 521 buildings that have started or completed remediation as at 30 November 2024:
- 164 buildings (20% of all buildings) have started remediation.
- 357 buildings (44% of all buildings) have completed remediation – an increase of five since the end of October. Of these, 223 buildings (28% of all buildings) have received building control sign off.
There are 288 eligible buildings proceeding with an application for funding that have not started remediation, of which:
- 141 (17% of all buildings) have remediation plans in place
- 147 (18% of all buildings) have reported an intent to remediate
There are an estimated 66,000 dwellings in buildings that are eligible and proceeding with an application for funding in the BSF.
BSF remediation progress over time
Figure 12: 41 more buildings proceeding with an application for funding in the BSF have started or completed remediation since the end of November 2023
Since the end of November 2023:
- 165 fewer eligible buildings are proceeding with an application for funding from the Building Safety Fund.
- 41 more eligible buildings have started or completed remediation, and 145 more eligible buildings have completed remediation.
BSF remediation by tenure
Figure 13: 65% of social sector buildings in the BSF, including buildings with a financial viability claim, have started or completed remediation compared to 64% of private sector buildings.
Social sector buildings receiving full government funding for their remediation due to financial viability claims were, up until May 2024, included in private sector buildings counts. Further detail is available in the accompanying [technical note]https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2024).
Cladding Safety Scheme
Information in this section is correct as at 30 November 2024 and shows a monthly update from the previous publication.
Figure 14: There are 2,538 buildings at different stages of the Cladding Safety Scheme, including 345 buildings with live applications and 492 eligible buildings, of which 46 buildings have started or completed works, with 16 having completed works.
Remediation Stage | Number of buildings | Percentage | Cumulative Number | Cumulative Percentage |
---|---|---|---|---|
Remediation Complete | 16 | 3% | 16 | 3% |
Works started | 30 | 6% | 46 | 9% |
In Programme | 446 | 91% | 492 | 100% |
Total | 492 | 100% | 492 | 100% |
Table 6: Remediation status for buildings within the Cladding Safety Scheme, 30 November 2024
Cladding Safety Scheme: Key statistics
As at the end of November 2024, there were 2,538 buildings in the different stages of the Cladding Safety Scheme (492 eligible buildings and 2,046 pre-eligible buildings). Of the 2,046 pre-eligible buildings:
- 1,701 buildings are in the pre-application stage.
- 345 buildings have a live application and are progressing through the eligibility stages.
There are 492 eligible buildings as at the end of November 2024, an increase of 32 since the end of October. None of the newly eligible buildings this month have been transferred from the BSF. In total, 109 of the eligible buildings in the CSS have been transferred from the BSF.
Of the 492 eligible buildings:
- 464 buildings (94% of eligible buildings) have signed Grant Funding Agreements (GFA) - an increase of 21 since the end of October
- Of these, 313 buildings (64% of all eligible buildings) have received a pre-tender support payment – an increase of 17 since the end of October
- 46 buildings have started or completed remediation works on site – an increase of 15 since the end of October
- Of these, 16 buildings have completed remediation works on site, including those awaiting building control sign-off – an increase of 2 since the end of October.
Four eligible buildings are in Northern Ireland, with the remainder in England.
Height breakdown
Figure 15: Of the 492 eligible buildings in the CSS, 322 are 11-18m and 170 are 18m+.
Tenure breakdown
Figure 16: Of the 492 eligible buildings in the CSS, 369 are private sector buildings and 123 are social sector buildings.
Developer-led remediation
Information in this section received by developers is correct as at 31 October 2024, except for Frasers Developments, who did not submit data within the deadline. For this developer, the data reported in this release uses the data they submitted as at 31 July 2024. Information in this section received from other programmes that relate to developer-led remediation (where cladding remediation is being carried out in a government funded remediation programme and the developer will subsequently pay for the works) is correct as at 30 November 2024.
The estimates in this section include some buildings which are also included in other sections of this data release e.g., those reported under the following sections: ‘ACM Remediation’, ‘Building Safety Fund’, ‘Cladding Safety Scheme’ and ‘Social Housing Sector’.
Figure 17: 49% of buildings in the developer remediation contract have either started or completed remediation works on life-critical fire safety risks, with 25% having completed remediation works.
Remediation Stage | Number of buildings | Percentage | Cumulative Number | Cumulative Percentage |
---|---|---|---|---|
Remediation complete | 357 | 20% | 357 | 20% |
Remediation complete – awaiting building control sign-off | 82 | 5% | 439 | 25% |
Remediation started | 411 | 24% | 850 | 49% |
Remediation not started – plans in place | 430 | 25% | 1280 | 73% |
Remediation not started – no plans in place | 466 | 27% | 1746 | 100% |
Total | 1746 | 100% | 1746 | 100% |
Table 7: Remediation status of buildings requiring works under the developer remediation contract, 30 November 2024. Percentages may not sum to 100% due to rounding.
Developer remediation: key statistics
As at 30 November 2024, 54 developers have signed the developer remediation contract. Between them, there are 4,683 buildings covered by the developer remediation contract. Of which, there are 1,746 buildings identified as having life-critical fire safety risks that will be remediated by developers.
Of the 1,746 buildings identified as having life-critical fire safety risks:
- 439 (25%) are reported to have completed remediation– an increase of 26 since the October data release. Of the 439 buildings that are reported to have completed remediation, 357 buildings (20% of all buildings with defects) are reported to have received building control sign-off.
- 850 (49%) are reported to have started or completed remediation – an increase of 78 since the October data release.
- 430 (25%) are reported to have not started remediation but have plans in place – a decrease of 25 since the October data release.
Although information from developers is received quarterly, these statistics are subject to change and are updated monthly as information from other programmes which relate to remediation is updated monthly.
The 1,746 buildings identified as requiring remediation have an estimated cost of remediation of around £3.7 billion. This is an increase of £0.4bn since reported in the October data release, which is due to an increase in the number of buildings identified with defects, as well as an increase in the average reported remediation cost per building by developers.
There are an estimated 115,000 dwellings in buildings with defects that developers are committed to remediate. Of these, there are an estimated 59,000 dwellings in buildings that are reported as having either started or completed remediation works.
Based on start and completion dates reported by developers, 510 buildings which have not yet started are reportedly expected to start works, and 284 buildings which have not yet completed are reportedly expected to complete their remediation between 1 November 2024 and 31 October 2025.
443 buildings have transferred from the Building Safety Fund to developers, an increase of 2 since the October data release:
- 46 (10%) have completed remediation - an increase of 7 since the October data release. Of these 46, 32 buildings (7% of all buildings) are reported to have received building control sign-off.
- 167 (38%) have started or completed remediation – an increase of 26 since the October data release.
- 126 (28%) are reported to have not started remediation but have plans in place - a decrease of 7 since the October data release.
- 63 (14%) are reported to have not started remediation and have no plans in place – a decrease of 3 since the October data release.
- 87 (20%) have not been identified by developers as having life-critical fire-safety defects – a decrease of 14 since the October data release.
The 443 buildings in the developer remediation contract differs from the 454 reported in the Building Safety Fund section of the data release, due to developers defining buildings differently to in the Building Safety Fund. The same building structures are included in both sections of the release.
Height breakdown
Figure 18: 54% of the 18m+ buildings have started or completed remediation, compared to 42% of the 11-18m buildings.
Cladding defects
Some remediation being undertaken by developers on buildings with life-critical fire safety risks relate to non-cladding defects. When excluding buildings reported to have only non-cladding defects, there are 1,536 buildings which developers have reported as having unsafe cladding. Of these:
- 397 (26%) are reported to have completed remediation - an increase of 13 since the October data release. Of these 397, 331 buildings (22% of all buildings with cladding defects) are reported to have received building control sign-off.
- 790 (51%) are reported to have started or completed remediation - an increase of 72 since the October data release.
- 390 (25%) are reported to have not started remediation but have plans in place - a decrease of 28 since the October data release.
These estimates are subject to change each month due to the monitoring of buildings under the developer remediation contract in other remediation programmes.
Self-reported information
The figures reported for developers above combine information received directly from developers as well as information held by the department from other programmes which relate to remediation. This is to help better estimate a figure for buildings requiring remediation under the developer remediation contract. The figures reported above will also include buildings which are being remediated solely under a government remediation scheme, for which the developer will reimburse taxpayers.
The estimates in this section report on buildings which have been self-reported by developers as requiring remediation to life-critical fire safety risks. Furthermore, this section reports on buildings which are being remediated by the developer directly, rather than being remediated through a government fund and being reimbursed to taxpayers.
Developers have self-reported that 1,492 buildings require life-critical fire safety remediation, which will be directly remediated by the developer. Some of these buildings are being remediated in the BSF or ACM programme, however they are reported to have other non-EWS life-critical fire safety defects which are being remediated by the developer and are therefore included in these statistics. Of these 1,492 buildings being directly remediated by the developer:
- 292 buildings (20%) have completed remediation. Of these, 225 buildings (15% of all buildings with defects) are reported to have received building control sign-off.
- 652 buildings (44%) have started or completed remediation.
- 400 buildings (27%) have not started remediation but have a plan in place.
Further information on the progress developers have made regarding the buildings they’ve reported on is available in the accompanying management information tables.
Social housing sector
Information in this section received by Registered Providers of Social Housing is correct as at 30 September 2024. Information in this section received from other programmes that relate to social housing is correct as at 30 November 2024.
The estimates in this section include some buildings which are also included in other sections of this data release e.g., those reported under the following sections: ‘ACM Remediation’, ‘Building Safety Fund’, ‘Cladding Safety Scheme’ and ‘Developer Remediation’.
From June 2024, the estimates in this section of the release include buildings which have been reported by Registered Providers to have completed remediation since 14 June 2017 but prior to the most recent assessment. They also include social buildings the department has identified in other remediation programmes as having unsafe cladding and are also being monitored in those programmes.
Figure 19: 45% of social buildings identified to have unsafe cladding have started or completed remediation works, with 28% (of identified buildings) having completed remediation works.
Remediation Stage | Number of buildings | Percentage | Cumulative Number | Cumulative Percentage |
---|---|---|---|---|
Remediation complete | 665 | 26% | 665 | 26% |
Remediation complete – awaiting building control sign-off | 63 | 2% | 728 | 28% |
Remediation started | 448 | 17% | 1176 | 45% |
Remediation works planned | 845 | 32% | 2021 | 78% |
Remediation plans unclear from survey | 585 | 22% | 2606 | 100% |
Total | 2606 | 100% | 2606 | 100% |
Table 8: Remediation status of social buildings with unsafe cladding, 30 November 2024.
Social Housing remediation: key statistics
564 registered providers of social housing were invited to respond to this round of a survey on their 11m+ stock. 935 small registered providers were excluded from this round of the survey because they had indicated that they were not the Responsible Entity for any 11m+ residential buildings.
As at 30 November 2024, 2,606 social buildings 11 metres and over in height have been identified as having life-critical fire-safety cladding defects. Of the 2,606 buildings identified with unsafe cladding:
- 1,992 were reported by Registered Providers to have unsafe cladding at the time of their most recent assessment. This could include buildings whose remediation work has been completed but await building control sign off and those awaiting a subsequent assessment to confirm no outstanding life-critical fire-safety defects. Additional information on these buildings is available in the accompanying management information tables, social housing provider release document and the Regulator for Social Housing’s publication on Fire safety remediation in social housing in England.
- 500 were reported by Registered Providers to have unsafe cladding since June 2017 but prior to the most recent assessment, which have since been remediated. Of these, 12 were reported by Registered Providers to have unsafe cladding in the previous survey (as at 30 June 2024) but have since completed remediation.
- 114 were identified under other remediation programmes (BSF, ACM, CSS or developer remediation) as having unsafe cladding and are also being monitored in those programmes.
Of the 2,606 buildings identified to have unsafe cladding:
- 728 buildings (28%) are reported to have completed remediation – an increase of 24 since the October data release. Of these 728, 665 (26% of all buildings with defects) are reported to have received building control sign-off – an increase of 22 buildings since reported in the October data release.
- 1,176 buildings (45%) are reported to have started or completed remediation – this is 120 buildings lower than the number reported in the October data release. The fall in the number reported is driven by Registered Providers making revisions to their data returns following the addition of more detailed questions on start and completion dates. The status of 187 buildings changed to not having cladding defects, or from having started or completed remediation to not having started remediation. In addition, Registered Providers added 67 buildings with cladding defects that have started or completed remediation or updated the status of buildings with cladding defects from not having started remediation to having started or completed remediation.
- 845 buildings (32%) are reported to have not started remediation but have plans in place – an increase of 143 since reported in the October data release.
Although information from registered providers of social housing is received quarterly, these statistics will be updated monthly as information from other programmes which relate to social building remediation is updated monthly.
Height breakdown
Figure 20: 52% of the 18m+ social buildings identified to have unsafe cladding have started or completed remediation, compared to 38% of the 11-18m buildings
Additional information available for individual social housing providers is available in the accompanying management information tables and social housing provider release document.
The estimates in this section exclude three buildings identified with unsafe cladding which have been decanted prior to demolition.
Social Housing remediation: recent assessments
The estimates in this section include buildings self-reported by registered providers in the latest survey (as at 30 September 2024) as having unsafe cladding at the time of their most recent assessment.
Registered Providers reported that 2,492 have been found to have unsafe cladding since June 2017. Of these, 500 completed remediation prior to their most recent building works assessment and 1,992 buildings have been identified with unsafe cladding at the time of the most recent building works assessment. Of the 1,992 buildings:
- 144 buildings (7%) are reported to have completed remediation – an increase of 36 since the October data release. Of these 144, 84 buildings (4% of all buildings with defects) are reported to have received building control sign-off.
- 589 buildings (30%) are reported to have started or completed remediation - this is 107 lower than the number reported in the October data release. This fall in the number reported is driven by Registered Providers making revisions to their data returns following the addition of more detailed questions on start and completion dates. The status of 160 buildings changed to not having cladding defects or from having started or completed remediation to not having started remediation. In addition, Registered Providers added 53 buildings with cladding defects that have started or completed remediation or updated the status of buildings with cladding defects from not having started remediation to having started or completed remediation.
- 831 buildings (42%) are reported to have not started remediation but have plans in place – an increase of 157 since the October data release
Enforcement
Information in this section is correct as of 25th November 2024 and shows a monthly update from the previous publication.
This section includes local authority enforcement action on buildings 11 metres or over in height. Up until June 2024 only enforcement action taken on buildings over 18m in height was reported on.
Local authority enforcement action: key statistics
As of 25th November 2024, enforcement action has been, or is being, taken under the Housing Act against 499 buildings over 11m with unsafe cladding - an increase of 16 since the end of October. Of these, 142 buildings have had 145 inspections with Joint Inspection Team support – an increase of 3 inspections since the end of October.
Of the 499 buildings where a local authority had undertaken an inspection, we are aware that:
- 113 had a Category 1 HHSRS rating
- 333 buildings had a Category 2 HHSRS rating
As several buildings have now had two or more inspections, from August 2024, only the most recent inspection’s category rating is reported on, as this is used to gauge the risks of the buildings in each Local Authority’s portfolio. Additional inspections are still reported as enforcement action.
Of the 499 buildings, we are aware that at least 167 improvement notices, 49 hazard awareness notices and 1 prohibition order have been served to date. Some buildings may have received multiple notices. We understand that 41 of the improvement notices have been subject to appeals.
Accompanying dashboard
An additional interactive dashboard showing the information in this release is available.
Accompanying tables
Additional management information tables are available.
The tables provide data on:
- the remediation progress of high-rise (18 metres and over) residential buildings identified with unsafe Aluminium Composite Material (ACM) cladding systems
- the remediation progress of high-rise residential buildings with unsafe non-ACM cladding systems that are pursuing successful applications from their Building Safety Fund (BSF) Registration
- data on buildings in the Cladding Safety Scheme (CSS)
- the remediation progress of buildings covered by the developer remediation contract, including a developer-by-developer breakdown
- the remediation progress of buildings monitored under the social housing survey, including a provider-by-provider breakdown
- the progress of the Waking Watch Relief Fund and Waking Watch Replacement Fund
- building safety enforcement action undertaken by Local Authorities in England
Related statistics
BRE Testing
Previously, MHCLG published a table on samples received by BRE for testing which has been discontinued as of October 2019 (see Technical Notes). The data table of descriptions of large-scale system tests undertaken by the BRE and the number of buildings with similar cladding systems was discontinued in November 2020.
Developer data
MHCLG has published data provided by developers who have signed the developer remediation contract. This release provides information on the number of buildings in scope of the contract, assessments in place, number of buildings requiring remediation works and status of those works by developer.
English Housing Survey: Feeling Safe from Fire
MHCLG has published the English Housing Survey 2020 to 2021: Feeling Safe from Fire report, providing information on the extent to which people feel safe from fire in their homes.
Estimating the prevalence and costs of external wall system life-safety fire risk in mid-rise residential buildings
MHCLG has published data on the prevalence of external wall system life-safety fire risk in mid-rise (11-18m) residential buildings in England, and the estimated cost as at July 2021 to remediate or mitigate these buildings.
EWS1 requirements on residential buildings in England
MHCLG has published information on estimates of EWS1 requirements on residential buildings in England, including indicative analysis on the cladding coverage of residential buildings and the number of leasehold dwellings in those buildings.
EWS1 (or equivalent) lender data on mortgage valuation for flats
MHCLG publishes quarterly data on the numbers of EWS1 forms (or equivalent) that have been required on mortgage valuations for flats.
Population and Dwelling Numbers
Previously, MHCLG published estimates on population and dwelling numbers of residential buildings in the Building Safety Programme data release. Should these figures change, MHCLG will publish a new update.
RSH publication
On 19 December 2024, the Regulator of Social Housing published findings from the Fire Safety Remediation Survey (FRS) for buildings 11 metres and over in height, which opened to all landlords on 19 September 2024 and closed on 5 December 2024.
Social Housing Provider Data
MHCLG has published data provided by social housing providers on remediation progress of their building stock. This release provides information on the number of buildings, assessments in place, number of buildings requiring remediation works and status of those works by social housing provider.
Waking Watch costs
On 16 October 2020, MHCLG published information on Waking Watch costs based on data collected through a range of external stakeholders from July to September 2020.
Technical note
Please see the accompanying technical notes document for further details.