Building Safety Programme: monthly data release - August 2019

The 22nd monthly data release from the government’s Building Safety Programme.

Documents

Building Safety Programme: monthly data release - August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Table 1: number of buildings identified with ACM cladding systems unlikely to meet Building Regulations, by tenure – England, 31 August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Table 2: number of buildings with ACM cladding systems unlikely to meet Building Regulations yet to be remediated, by local authority – England, 31 August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Table 3: remediation status of buildings with ACM cladding systems unlikely to meet Building Regulations, by tenure – England, 31 August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Table 4: samples received by BRE for testing – England, 31 August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Table 5: descriptions of large-scale system tests undertaken by the BRE and the number of buildings with similar cladding systems – England, 31 August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Table 6: number of buildings that were identified with ACM cladding systems unlikely to meet Building Regulations, by local authority – England, 31 August 2019

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alternativeformats@communities.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

This data release uses figures current at 31 August 2019 and gives an update on the testing programme for Aluminium Composite Material cladding and progress identifying buildings with unsafe cladding combinations. This is the 22nd in a series of monthly data releases.

Published 12 September 2019