The following summary of planned new and ongoing road improvements over the coming week is correct as of Friday 19 June and could be subject to change due to weather conditions or unforeseen circumstances. All our improvement work is carried out with the aim of causing as little disruption as possible.

This news article was withdrawn on

These bulletins are now sent directly to journalists. Contact the Highways England Press Office directly to be added to the circulation list.

Otherwise you can check on the live roadworks search tool.

M6 Junction 16 Crewe and Junction 18 Holmes Chapel

Work is taking place to repair two bridges, which carry Congleton Road and Betchton Road over the M6. Lane closures and a 50mph limit will be in place along sections of the M6 while the work is taking place. More information is available on the scheme pages.

M6 Junction 17 Sandbach

A major project is being carried out to reduce congestion and allow for faster journey times through junction 17 of the M6, including building a new roundabout and a new link road from the A534 to the M6. Work is taking place overnight between 8pm and 5am during the week, and until 7am at weekends. Some lane closures will also be in place, along with a 40mph speed limit on the A534. More information is available on the scheme pages.

M6 Junction 44 Carlisle

Resurfacing in lane 1 of the southbound carriageway will be taking place this week with the closure of the entry slip road onto the southbound carriageway overnight between 8pm on Wednesday (24 June) until 6am on Thursday (25 June).

M53 Junction 2 Moreton

A project is taking place to upgrade the bridges on the section of the M53 at junction 2, removing weight restrictions and reinstating lanes. The southbound exit and entry slip roads are currently closed to all traffic. A 50mph speed limit and narrow lanes are in place. The scheme is due to be completed by the end of August.

M56 Junction 11 Daresbury

A major project is taking place to tackle congestion at junction 11 of the M56 near Daresbury. Clearly signed diversions will be in place when roads are closed.

M60 Junction 8 Sale to M62 Junction 20 Rochdale

A major scheme is taking place to cut congestion and improve journey times on parts of the M60 and the M62 in Greater Manchester. The scheme will require some overnight closures affecting the full carriageway and slip roads, with a 50mph limit in place for the safety of workers and drivers. The project is due to be completed in Autumn 2017. Further information is available on the scheme pages.

A55/A483 Roundabout, Chester

Drivers travelling between Chester and Wrexham are being encouraged to avoid the roundabout that links the A55 to the A483 while work takes place to upgrade the junction. There are currently lane closures on the roundabout while work takes place to increase the number of lanes from 3 to 4. Weekend working is taking place which will be completed at 5am on Monday (22 June) with the total overnight closure of the westbound bridge (including A55 eastbound exit and westbound entry slip roads). Further overnight work will be taking place this week - more information is available on the scheme pages. The work is due to be completed by Sunday 28 June.

A556 Bowdon to Knutsford

A £192 million project is being carried out to create a new dual carriageway linking the M56 to the M6 in Cheshire. A temporary 40mph speed limit is currently in place between Bucklow Hill and Bowdon, and the new dual carriageway is expected to open in Winter 2016/17. Further information is available on the project pages.

A590 Witherslack

Overnight 8pm to 6am rolling traffic signals and lane closures for electrical works Monday 22 June to Friday 3 July.

A595 Calder Bridge

Resurfacing of the carriageway and footpath as well as drainage repairs will be taking place between Calder Bridge and the junction with the B5345 from Monday 1 June for around 12 weeks. Off-peak temporary traffic lights will be in place during the day for 7 weeks and overnight for the duration of the project. Go to news release dated 26 May 2015.

A66 Keswick

Work to repair drainage along the A66 around the junction with the A591 near Keswick will start on Monday 8 June with temporary traffic lights in use – mainly during off-peak hours. The work is due to be completed on Tuesday 30 June. Go to news release dated 27 May 2015.

A66 Hardhills to Augill Junction

There will be a 24hr lane 1 or 2 closures with a 40mph speed limit with 10mph limit during overnight works to allow for convoy working between 8pm and 6am.

A66 Former Greenacre Filling Station Kirkby Thore

There will be 24hr traffic signals in place for excavations in the footway and carriageway.

General enquiries

Members of the public should contact the Highways England customer contact centre on 0300 123 5000.

Media enquiries

Journalists should contact the Highways England press office on 0844 693 1448 and use the menu to speak to the most appropriate press officer.

Published 19 June 2015