Two persons overboard from the standby safety vessel Vos Tracker during maintenance of the fast rescue craft

Location: North Sea.

Completed preliminary assessment (PA) summary 3/25: Vos Tracker 

Synopsis

At 0800 on 25 August 2025, the deck crew of the offshore emergency rescue and response vessel Vos Tracker conducted a toolbox talk to discuss the day’s maintenance tasks. Planned work included the replacement of the lifting strops for the two fast rescue craft (FRC). The weather was good, with a low swell and light winds from the south-south-east.

Although the planned work was initially scheduled for the afternoon, the crew decided to change the FRC lifting strops before midday. A second toolbox talk was held to discuss the strop change. By 1125, the starboard side FRC strop change was completed without issue.

Coxswain A then boarded the port side FRC and disconnected the lifting stops (Figure 1) after the bosun had lowered the davit hook. The FRC was now secured to its cradle only by two bowsing in pennants forward and aft. Coxswain A then progressed changing the aft lifting strops.

Vos Tracker PA summary: figure 1

At about 1125, coxswain B boarded the port FRC to change the forward strops. Coxswain B found that the lifting strop’s shackle pin was tight and moved aft and outboard in the FRC to collect some tools. In doing so, the combined weight of the two coxswains unbalanced the FRC on its narrow cradle. The FRC tilted, then slipped overboard at 1135. The carabiner connecting the aft bowsing in pennant parted as the FRC skewed and fell. The coxswains jumped into the water and their personal flotation devices automatically inflated. Both narrowly missed being struck by the FRC as it hit the water.

The bosun immediately sounded the general alarm, and the master announced “Man overboard” over Vos Tracker’s public address system. The crew mustered, lifebuoys were deployed and the starboard side FRC was launched. Meanwhile, coxswain B climbed aboard the port side FRC and it was brought alongside Vos Tracker by the vessel’s crew. By 1144, coxswain A had been recovered from the water into the starboard FRC. Both FRCs were subsequently recovered. The port side FRC had sustained hull damage that required a replacement when Vos Tracker berthed 2 days later. Both coxswains were unharmed in the accident.

Findings

  • The FRC cradle had a narrow outboard arm (Figure 2), which did not adequately support the FRC when there was the combined weight of two people standing on the outboard side of the FRC.

  • The FRCs were unsecured once the davit hook lifting strops were removed.

  • No risk assessment was in place for the lifting strop change and no permit to work for working at height had been raised as required by the vessel’s safety management system.

  • Neither coxswain A nor coxswain B was wearing a safety harness and either a fall arrest or fall restraint tether while working in the FRC.

  • The toolbox talks for the FRC strop change were ineffective, and evidence suggested that these were a compliance exercise.

  • The successful change of the strops on the starboard side FRC, and previous strop changes in the same manner, had led the crew to believe that their methodology was safe.

  • There was no effective supervision of the task due to distraction and hurried execution to complete the work before the watch changeover at midday.

Vos Tracker PA summary: figure 2

Actions taken

The operator, Vroon Offshore Services Limited, has:

  • introduced a procedure and task-specific risk assessment for FRC strop changes
  • updated its toolbox talk record card
  • reviewed and upgraded the FRC securing arrangements on Vos Tracker and sister vessels
  • issued a fleetwide safety alert
  • instigated a safety campaign across its fleet of 30 vessels.
Ship particulars
Vessel’s name Vos Tracker
Flag UK
Classification society Lloyd’s Register
IMO number 9391907
Type Standby safety vessel
Registered owner Offshore Support Vessels VI Limited
Manager Vroon Offshore Services Limited
Operator Vroon Offshore Services Limited
Construction Steel
Year of build 2007
Length overall 48.2m
Registered length Not applicable
Gross tonnage 851
Minimum safe manning 12
Authorised cargo Passengers
Voyage particulars
Port of departure Aberdeen, Scotland
Port of arrival Leith, Scotland
Type of voyage Coastal
Cargo information Not applicable
Manning 12
Marine casualty information
Date and time 25 August 2025 at 1135
Type of marine casualty or incident Less Serious Marine Casualty
Location of incident 58°18’.1N 000°11.0E
Place on board Main deck
Injuries/fatalities None
Damage/environmental impact Fast rescue craft hull damage; no environmental impact
Ship operation On passage
Voyage segment Mid-water
External & internal environment Clear, good visibility; wind, south-south-east force 3; northerly 1m swell
Persons on board 12

Updates to this page

Published 27 November 2025