4. Decision-making

Paragraphs 38 to 59

38. Local planning authorities should approach decisions on proposed development in a positive and creative way. They should use the full range of planning tools available, including brownfield registers and permission in principle, and work proactively with applicants to secure developments that will improve the economic, social and environmental conditions of the area. Decision-makers at every level should seek to approve applications for sustainable development where possible.

Pre-application engagement and front loading

39. Early engagement has significant potential to improve the efficiency and effectiveness of the planning application system for all parties. Good quality pre-application discussion enables better coordination between public and private resources and improved outcomes for the community.

40. Local planning authorities have a key role to play in encouraging other parties to take maximum advantage of the pre-application stage. They cannot require that a developer engages with them before submitting a planning application, but they should encourage take-up of any pre-application services they offer. They should also, where they think this would be beneficial, encourage any applicants who are not already required to do so by law to engage with the local community and, where relevant, with statutory and non-statutory consultees, before submitting their applications.

41. The more issues that can be resolved at pre-application stage, including the need to deliver improvements in infrastructure and affordable housing, the greater the benefits. For their role in the planning system to be effective and positive, statutory planning consultees will need to take the same early, pro-active approach, and provide advice in a timely manner throughout the development process. This assists local planning authorities in issuing timely decisions, helping to ensure that applicants do not experience unnecessary delays and costs.

42. The participation of other consenting bodies in pre-application discussions should enable early consideration of all the fundamental issues relating to whether a particular development will be acceptable in principle, even where other consents relating to how a development is built or operated are needed at a later stage. Wherever possible, parallel processing of other consents should be encouraged to help speed up the process and resolve any issues as early as possible.

43. The right information is crucial to good decision-making, particularly where formal assessments are required (such as Environmental Impact Assessment, Habitats Regulations assessment and flood risk assessment). To avoid delay, applicants should discuss what information is needed with the local planning authority and expert bodies as early as possible.

44. Local planning authorities should publish a list of their information requirements for applications for planning permission. These requirements should be kept to the minimum needed to make decisions, and should be reviewed at least every 2 years. Local planning authorities should only request supporting information that is relevant, necessary and material to the application in question.

45. Local planning authorities should consult the appropriate bodies when considering applications for the siting of, or changes to, major hazard sites, installations or pipelines, or for development around them.

46. Applicants and local planning authorities should consider the potential for voluntary planning performance agreements, where this might achieve a faster and more effective application process. Planning performance agreements are likely to be needed for applications that are particularly large or complex to determine.

Determining applications

47. Planning law requires that applications for planning permission be determined in accordance with the development plan, unless material considerations indicate otherwise. Decisions on applications should be made as quickly as possible, and within statutory timescales unless a longer period has been agreed by the applicant in writing.

48. Local planning authorities may give weight to relevant policies in emerging plans according to:

(a) the stage of preparation of the emerging plan (the more advanced its preparation, the greater the weight that may be given);

(b) the extent to which there are unresolved objections to relevant policies (the less significant the unresolved objections, the greater the weight that may be given); and

(c) the degree of consistency of the relevant policies in the emerging plan to this Framework (the closer the policies in the emerging plan to the policies in the Framework, the greater the weight that may be given) 22 .

49. However, in the context of the Framework – and in particular the presumption in favour of sustainable development – arguments that an application is premature are unlikely to justify a refusal of planning permission other than in the limited circumstances where both:

(a) the development proposed is so substantial, or its cumulative effect would be so significant, that to grant permission would undermine the plan-making process by predetermining decisions about the scale, location or phasing of new development that are central to an emerging plan; and

(b) the emerging plan is at an advanced stage but is not yet formally part of the development plan for the area.

50. Refusal of planning permission on grounds of prematurity will seldom be justified where a draft plan has yet to be submitted for examination; or – in the case of a neighbourhood plan – before the end of the local planning authority publicity period on the draft plan. Where planning permission is refused on grounds of prematurity, the local planning authority will need to indicate clearly how granting permission for the development concerned would prejudice the outcome of the plan-making process.

Tailoring planning controls to local circumstances

51. Local planning authorities are encouraged to use Local Development Orders to set the planning framework for particular areas or categories of development where the impacts would be acceptable, and in particular where this would promote economic, social or environmental gains for the area.

52. Communities can use Neighbourhood Development Orders and Community Right to Build Orders to grant planning permission. These require the support of the local community through a referendum. Local planning authorities should take a proactive and positive approach to such proposals, working collaboratively with community organisations to resolve any issues before draft orders are submitted for examination.

53. The use of Article 4 directions to remove national permitted development rights should:

  • where they relate to change from non-residential use to residential use, be limited to situations where an Article 4 direction is necessary to avoid wholly unacceptable adverse impacts (this could include the loss of the essential core of a primary shopping area which would seriously undermine its vitality and viability, but would be very unlikely to extend to the whole of a town centre)
  • in other cases, be limited to situations where an Article 4 direction is necessary to protect local amenity or the well-being of the area (this could include the use of Article 4 directions to require planning permission for the demolition of local facilities)
  • in all cases, be based on robust evidence, and apply to the smallest geographical area possible.

54. Similarly, planning conditions should not be used to restrict national permitted development rights unless there is clear justification to do so.

Planning conditions and obligations

55. Local planning authorities should consider whether otherwise unacceptable development could be made acceptable through the use of conditions or planning obligations. Planning obligations should only be used where it is not possible to address unacceptable impacts through a planning condition.

56. Planning conditions should be kept to a minimum and only imposed where they are necessary, relevant to planning and to the development to be permitted, enforceable, precise and reasonable in all other respects. Agreeing conditions early is beneficial to all parties involved in the process and can speed up decision-making. Conditions that are required to be discharged before development commences should be avoided, unless there is a clear justification 23 .

57. Planning obligations must only be sought where they meet all of the following tests 24 :

(a) necessary to make the development acceptable in planning terms;

(b) directly related to the development; and

(c) fairly and reasonably related in scale and kind to the development.

58. Where up-to-date policies have set out the contributions expected from development, planning applications that comply with them should be assumed to be viable. It is up to the applicant to demonstrate whether particular circumstances justify the need for a viability assessment at the application stage. The weight to be given to a viability assessment is a matter for the decision maker, having regard to all the circumstances in the case, including whether the plan and the viability evidence underpinning it is up to date, and any change in site circumstances since the plan was brought into force. All viability assessments, including any undertaken at the plan-making stage, should reflect the recommended approach in national planning guidance, including standardised inputs, and should be made publicly available.

Enforcement

59. Effective enforcement is important to maintain public confidence in the planning system. Enforcement action is discretionary, and local planning authorities should act proportionately in responding to suspected breaches of planning control. They should consider publishing a local enforcement plan to manage enforcement proactively, in a way that is appropriate to their area. This should set out how they will monitor the implementation of planning permissions, investigate alleged cases of unauthorised development and take action where appropriate.


Footnotes

(22) During the transitional period for emerging plans consistency should be tested against the version of the Framework as applicable, as set out in Annex 1.

(23) Sections 100ZA(4-6) of the Town and Country Planning Act 1990 will require the applicant’s written agreement to the terms of a pre-commencement condition, unless prescribed circumstances apply.

(24) Set out in regulation 122(2) of the Community Infrastructure Levy Regulations 2010.