Corporate report

DFID Annual Report and Accounts 2014 to 2015 Results achieved by sector: Infrastructure

Published 16 July 2015

Level 2 of the DRF contains some sector specific infrastructure indicators, such as access to water, sanitation and clean energy which are presented on the WaSH and climate change sector results pages. Level 2 of the DRF also includes a number of other infrastructure indicators from multilateral organisations to which DFID contributes. The latest results from these organisations are shown below.

For more information on DFID’s infrastructure work, please see DFID’s Infrastructure Policy Framework.

1. Results achieved by multilateral organisations

The following results are delivered by multilateral organisations, and fall broadly within the infrastructure sector. The results presented here are based on all funding that the multilateral receives, not just funding from DFID or the UK. These results are presented alongside DFID’s share of core funding to the multilateral organisations, in order to illustrate that DFID contributes a share of those results. Multilateral abbreviations and results sources can be found in the results technical notes.

Indicator Multilateral Reporting period Latest Results DFID’s contribution as a % of total core funding[footnote 1]
People with improved access to transport AfDB[footnote 2]: 2012-2014 19,350,000 12
People benefiting from new or improved electricity connections AfDB[footnote 2] 2012-2014 10,870,000 12
Number of new households connected to electricity AsDB[footnote 2] 2014 70,000 5
Beneficiaries of road projects AsDB[footnote 2] No data – stopped reporting   5
Beneficiaries of road projects CDB[footnote 2] 2014 59,000 22
Roads constructed and rehabilitated (km) IDA FY 2013-14 48,100 11
Kilometres of roads constructed / rehabilitated IFAD 2013 20,100 7
People impacted with improved/ new infrastructure PIDG Cumulative data to 2014 262,000,000 81
  1. The DFID burden share presented here are not suitable to calculate a DFID results attribution of multilateral results. The results presented in this table are achieved through all funding streams that the multilateral receive, not just limited to core funding. 

  2. Burden share relates to the concessionary fund only. The results presented are achieved through concessionary and non-concessionary funds of the Bank.  2 3 4 5