Guidance

Specimen timeline - accessible version

Published 17 December 2025

Applies to England

Specimen timeline for setting up a DRT scheme

This page relates to the guidance for local authorities in England on how to set up and run demand responsive transport (DRT).

The graphic shows an example of a typical timeline to set up and launch a DRT scheme from scratch.

The stages it describes with rough timescales are described in the text below the graphic.

Accessible text description of timeline graphic

Activity starts Activity Duration
Months 1 - 12 Local authority internal clearance process 12 months
Months 1 - 2 Initial planning 2 months
Months 1 - 2 Data analysis - recognition of issue 1 month
Months 1 - 2 Development of scheme design - consult software providers and other LAs which have DRT 3 months
Months 3 – 11 Procurement 8 months
Months 3 - 4 Whether you have existing in-house fleet and drivers or not:

Decide on tech procurement process
Develop tech provider specification
1 month
Months 3 - 4 Only if you have no in-house fleet and drivers:

Develop operator / driver / vehicle specification
2 months
Months 3 - 4 Only if you have no in-house fleet and drivers:

Vehicle purchasing
2 months
Months 5 - 11 Vehicle lead time 6 months
Months 5 - 6 Develop marketing and promotion strategy 4 months
Months 5 - 6 Launch tenders 1 month
Months 5 - 6 If no in-house fleet:

Purchase vehicles
1 month
Months 5 - 6 Payment processor engagement and finalisation of contract 4 months
Months 6 - 12 Pre-launch 6 months
Months 7 - 8 Award tenders 1 month
Months 7 - 8 Work with contractors to set up scheme 2 months
Months 8 - 9 Call centre staff and driver training 3 months
Months 10 - 12 DRT marketing, comms and engagement 3 months
Months 10 - 12 Testing the service 3 months
Months 10 - 12 Vehicle livery / wrap 2 months
Post launch Operating and reviewing Ongoing
Post launch Analysis of data Ongoing
Post launch Service alteration / parameters / algorithm / zone sizes / number of vehicles in a zone Ongoing