Skip to main content
Transparency data

Building Safety Regulator building control approval application data March to May 2026

Updated 9 June 2026

Applies to England

All data is correct as of 30 May 2026 and provided by the Building Safety Regulator (BSR).

Gateway 2: Priority headline numbers for new build

Status Legacy cases Innovation Unit Complex cases Transitional cases Total
New cases received 0 64 0 0 64
Decisions made, withdrawn and invalid 14 33 21 7 75
Cases in progress as of 1 Oct 91 27 0 34 152
Cases in progress as of 1 June 0 122 14 42 178

​ Total number of units in new cases received 13,964

​ Total number of units in decisions made 14,928

​ Total number of units in cases in progress as of 1 June 38,775

Commentary

  • In the 12-week rolling period to 29 May, 31 new build Innovation Unit (IU) applications have been determined with 64 new applications received. The number of approvals since the data series began has reached 43.​
  • Of the 31 decisions made in the 12-week rolling period, 28 were approvals and 3 were rejections. This means that the 12-week rolling approval rate now stands at 90%, with a median approval time of 22 weeks, reflecting the significant effort to work through issues and to enable safe homes.​
  • We have reduced the number of legacy, long-term cases to 5. These have significant technical challenges and have been managed as ‘complex cases’ since February. This is where account managers work closely with applicants to try to achieve a successful outcome.​
  • 9 in progress IU cases are deemed complex cases, as we continue to work closely with applicants to reduce rejections and reach an approval despite technical challenges.​
  • Transitional cases now stand at 42, reflecting our acceptance of projects that were previously managed by Assent Building Control which ceased trading in late 2025.​
  • Over the past 12 weeks new applications for 13,964 residential units have been received. This has been outstripped by decisions, with applications for 14,928 units being determined, of which 9,499 (64%) were approvals. There are currently 38,775 units in in progress cases.

Innovation Unit (national)

Innovation Unit: new in versus closed decisions (national)​

Week commencing New in Closed decisions Total cases in progress
9 Mar 7 4 116
16 Mar 9 1 124
23 Mar 2 8 118
30 Mar 3 3 118
6 Apr 3 1 120
13 Apr 4 1 123
20 Apr 3 2 124
27 Apr 10 5 129
4 May 5 4 130
11 May 5 4 131
18 May 10 4 137
25 May 3 9 131

Innovation Unit: performance totals (national)​

Description Total
New in 64
In progress 131
Units approved 3,002 ​
Units in progress 30,369 ​

Innovation Unit: performance percentages and weeks taken (national)​

In the period, there were:

  • 31 decisions made
  • 15 invalid or withdrawn applications
  • 9 complex cases in progress with a median approval time of 33 weeks
Description Percentage Weeks taken (median) ​​
Rejections 10% 28
Approval 90% 22

Commentary

  • Out of 64 applications received over the past 12 weeks, 8 applications were invalidated and 7 withdrawn.​
  • Of the 31 decisions made, 28 were approvals and 3 were rejections.​
  • This means that the 12-week rolling approval rate (not including invalidations and withdrawals) has risen to 90% with the median approval time remaining at 22 weeks.​
  • IU approvals now stand at 43 in total.​
  • Complex cases are now tracked separately and, whilst the final decision is included in the rejection or approval totals, their median approval time is now at 33 weeks.​
  • We continue to work closely with industry on a shared understanding of compliance as we seek to reduce the number of complex cases in the system.​
  • New applications have been received at an average rate of around 6 per week over the past 12 weeks, which, using the current median determination period of 22 weeks suggests that our head of work should be 130 to 140, plus a small number of complex cases.​
  • The overall combined head of work reflects that expectation – currently sitting at 131, having risen slowly over the past 3 months.

Remediation (national)

Remediation: new in versus closed decisions (national)

Week commencing New in Closed decisions Total in progress cases
9 Mar 13 10 324
16 Mar 4 10 318
23 Mar 15 11 322
30 Mar 19 6 335
6 Apr 6 2 339
13 Apr 7 3 343
20 Apr 15 3 355
27 Apr 9 13 351
4 May 8 6 353
11 May 6 4 355
18 May 10 7 358
25 May 7 6 359

Remediation: performance (national)

Description Total
New in 119
In progress 359
Units approved 5,030
Units in progress 32,340

Remediation: performance percentages and weeks taken (national)

In the period, there were:

  • 67 decisions made
  • 14 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Rejections 21% 32
Approval 79% 39

Commentary

  • The 12-week approval rate has risen to 79% with the median approval time falling to 39 weeks as we successfully make decisions on older applications which have been in the system for some time.​
  • 16 legacy applications made in 2024 now remain, and approval rates in 2026 have exceeded the 65% target. A further 10 of the legacy 2024 applications are on track to be determined in June.
  • We also continue to work closely with the sector to help applicants improve the quality of applications and data shows that applications submitted in October to December 2025 are progressing through the system faster than earlier applications. However, the average approval time in weeks based on the rolling total includes older 2024 to 2025 applications being cleared, hence the high figure.​
  • We have already published updated guidance for applications and more detailed resources focusing on common issues that result in rejection will be published in the coming weeks.​

All categories (national)

All categories new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
9 Mar 94 67 1,475
16 Mar 71 61 1,485
23 Mar 63 55 1,493
30 Mar 59 40 1,512
6 Apr 47 42 1,517
13 Apr 50 37 1,530
20 Apr 62 62 1,530
27 Apr 65 68 1,527
4 May 78 51 1,554
11 May 71 126 1,499
18 May 52 90 1,461
25 May 38 54 1,445

All categories: performance (national)

Description Total
New in 750
In progress 1,445

All categories: performance percentages and weeks taken (national)

In the period, there were:

  • 358 decisions made
  • 396 invalid or withdrawn applications
  • 14 complex cases in progress with a median approval time of 33 weeks
Description Percentage Weeks taken (median)
Rejections 25% 25
Approval 75% 32

Commentary

  • The overall approval rate for applications of all categories has risen to 75%.​
  • The number of ‘in progress’ applications of all categories at gateway 2 has fallen by more than 100 over the last month.​
  • Decisions exceeded the number of new applications over the past 12 weeks. With a total of 754 closed applications against 750 new applications.​
  • Category A and B determinations over the past 3 months account for circa 67% of gateway 2 volume of decisions. These applications include all internal refurbishment works as well as NHS applications.

Gateway 2: Regional distribution​

Data as of the 30 May 2026.​

Regional gateway 2 applications (London)​

Region Innovation Unit Legacy cases Remediation Total
London 90 4 201 295
Rest of country 50 1 157 208

Regional gateway 2 applications (rest of England)​

Region Innovation Unit Legacy cases Remediation Total
East 0 0 21 21
East Midlands 0 0 11 11
North-east 1 0 8 9
North-west 26 0 49 75
South-east 9 0 29 38
South-west 4 1 13 18
West Midlands 6 0 12 18
Yorkshire and The Humber 4 0 14 18

Innovation Unit (London)

Innovation Unit: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
9 Mar 3 2 72
16 Mar 2 0 74
23 Mar 1 3 72
30 Mar 2 3 71
6 Apr 3 1 73
13 Apr 3 1 75
20 Apr 2 1 76
27 Apr 5 2 79
4 May 4 3 80
11 May 5 2 83
18 May 7 3 87
25 May 3 3 87

Innovation Unit: performance (London)

Description Total
New in 40
In progress 87
Units approved 2,109
Units in progress 17,486

Innovation Unit: performance percentages and weeks taken (London)

In the period, there were:

  • 19 decisions made
  • 5 invalid or withdrawn applications
  • 3 complex cases in progress
Description Percentage Weeks taken (median)
Rejections 0% Not applicable
Approval 100% 22

Commentary

  • Around 66% of in progress IU applications are in London.​
  • This also represents around 58% of the overall residential units handled by the IU.​
  • 19 of the 31 decisions that the IU has made in the last 12 weeks are in London.​
  • London approval rates are 100%, significantly higher than nationally. This figure reflects significant work to resolve outstanding complex cases.​
  • Approval time for non-complex cases matches the national average of 22 weeks.​

Remediation (London)

Remediation: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
9 Mar 4 4 178
16 Mar 4 6 176
23 Mar 9 8 177
30 Mar 7 3 181
6 Apr 0 1 180
13 Apr 3 1 182
20 Apr 13 2 193
27 Apr 1 8 186
4 May 6 2 190
11 May 4 1 193
18 May 8 3 198
25 May 6 3 201

Remediation: performance (London)

Description Total
New in 65
In progress 201
Units approved 1,294
Units in progress 17,597

Remediation: performance percentages and weeks taken (London)

In the period, there were:

  • 36 decisions made
  • 6 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Rejections 33% 32
Approval 67% 51

Commentary

  • Open remediation cases in London have increased over the period from 178 to 201.​
  • We announced the BSR remediation improvement plan in April 2026. We have already made progress with 16 legacy 2024 applications now remaining, down from 42 at the start of 2026.​
  • 2026 approval rates already exceed the 65% target for 2026 at 67%.​
  • London approval rates of 67% are slightly lower than they are nationally.​

All categories (London)

All categories: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
9 Mar 54 43 931
16 Mar 27 40 918
23 Mar 43 34 927
30 Mar 33 31 929
6 Apr 26 31 924
13 Apr 34 23 935
20 Apr 44 32 947
27 Apr 32 39 940
4 May 42 31 951
11 May 35 81 905
18 May 36 48 893
25 May 30 29 894

All categories: performance (London)

Description Total
New in 436
In progress 894

All categories: performance percentages and weeks taken (London)

In the period, there were:

  • 234 decisions made
  • 238 invalid or withdrawn applications
  • 7 complex cases in progress
Description Percentage Weeks taken (median)
Rejections 21% 28
Approval 79% 33

Commentary

  • The number of in progress London applications of all categories at gateway 2 has decreased slightly over the past month, from 951 to 894.​
  • A total of 472 applications have been closed, set against 436 new applications received.​
  • 65% of all decisions across all gateway 2 categories in the past 12 weeks related to London cases.​
  • Category A and B determinations in London over the past 3 months account for circa 73% of gateway 2 volume of decisions in London. These applications include all internal refurbishment works as well as NHS applications.​

Building control: Batching pilot

Batch volumes: cases allocated by batch number

Batch number New build Refurbishment Remediation Total
1 11 33 10 54
2 0 32 14 46
3 8 20 8 36
4 22 45 18 85
5 5 34 17 56
6 4 46 17 67
7 32 86 42 160
8 14 51 18 83
9 9 21 10 40
10 10 42 21 73
11 0 30 14 44
12 12 47 4 63
13 11 27 26 64
14 6 18 24 48
15 12 30 18 60
16 23 32 19 74
17 0 30 8 38
18 10 10 12 32
19 13 21 25 59
20 4 17 16 37
21 5 27 5 37
22 14 18 23 55
23 7 15 23 45
24 5 23 16 44
25 15 31 21 67
26 1 6 1 8
27 8 26 11 45
28 0 35 10 45
29 0 17 0 17
30 0 11 0 11
31 3 6 0 9
32 0 0 0 0
33 2 11 0 13

Commentary

  • Batching is part of the overall process, not additional. So, the data shown in this and following sections is a subset of the data shown in earlier sections. ​
  • This pilot process scales capacity by bundling applications to specialised engineering services suppliers for accelerated assessment, with BSR maintaining regulatory oversight. The primary goal of batching is to accelerate backlog resolution in newbuild and remediation applications.​
  • The first of these mixed-category bundles (26 cases) was sent to suppliers on 30 September 2025. Weekly dispatch of subsequent bundles is based on supplier capacity.​
  • The model follows a process where batches are issued to suppliers, they then have a limited time to accept or reject the cases in the allocation based on their capacity and any conflicts of interest. Once accepted, suppliers then have a defined period to return their assessments for consideration by BSR’s regulatory leads.​
  • New submissions have dropped off in recent weeks as suppliers at are capacity with earlier batching work and we have grown our in-house multidisciplinary team (MDT) capacity.​

Batching pilot performance: new builds

Issued Not yet accepted Accepted Returned Decision made
257 60 197 126 60

​ Median weeks from issued to return 5

​ Median weeks from issued to decision 12

Batched new build decisions

Decision made Percentage
Approval 28%
Approval with requirements 35% ​
Rejection 32%
Withdrawn 5%

Commentary

  • Batching in new builds is being used to support only some building control applications. Most are considered by our in-house teams.​
  • The batching approach is being used in some cases to access specialist resource to evaluate computational fluid dynamics (CFD) modelling in support of fire strategies submitted as part of an application. ​
  • Approvals (or approval with requirements) for batching assessments relating to new build decisions sit at 56%.​

Batching pilot performance: external remediation

Issued Not yet accepted Accepted Returned Decision made
408 171 237 140 49

​ Median weeks from issued to return 4

​ Median weeks from issued to decision 14

Batching pilot performance: external remediation

Issued Not yet accepted Accepted Returned Decision made
408 171 237 140 49

​ Median weeks from issued to return 4

​ Median weeks from issued to decision 14

Batched remediation decisions

Decision made Percentage
Approval 39%
Approval with requirements 6%​
Rejection 51%
Withdrawn 4%

Commentary

  • External remediation often requires a ‘full’ MDT, made up of the 3 core specialisms: registered building inspector (RBI), fire and structural engineers.​
  • Batching allows us to allocate remediation applications to one or more suppliers who have these capabilities available (while BSR maintains regulatory oversight) and is distributed across suppliers according to capacity.​
  • Batching is proving effective in speeding up early assessment and decision, which means rejections are coming through more strongly as approvals typically take longer. The steady-state approval rates are therefore more representative.

Batching pilot performance: refurbishments

Issued Not yet accepted Accepted Returned Decision made
899 305 594 445 153

​ Median weeks from issued to return 4

​ Median weeks from issued to decision 13

Batched refurbishment decisions

Decision made Percentage
Approval 56% ​
Approval with requirements 1%​
Rejection 38%  
Withdrawn 5%

Commentary

  • As with external remediation, category A refurbishments often require a ‘full’ MDT, made up of the 3 core specialisms: RBI, fire and structural engineers.​
  • Batching allows us to allocate these refurbishment applications to one or more suppliers who have these capabilities available and is distributed across suppliers according to capacity.​
  • Batching is proving effective in speeding up early assessment and decision, which means rejections are coming through more strongly as approvals typically take longer. The overall gateway 2 steady-state approval rates are therefore more representative.​

Innovation unit resources

Role Actual as of 31 May Forecast June (mid-month) Forecast July (mid-month) Forecast Aug (mid-month)
Registered building inspectors 20.7 24.3 31 32
Structural engineers 18.2 18.2 22.2 22
Fire engineers 8 8.5 9 9.4

All numbers are full-time equivalent – for example, some people are available to BSR fewer than 5 days per week, so the totals shown are aggregated.

Commentary

  • BSR draws building inspector, fire engineer and structural engineer resources from partner organisations across the public and private sector.​
  • These resources were brought in-house within BSR for the first time as part of the IU and allow BSR to have better control over resource allocation and tasking.​
  • The provision of sufficient resource of this type is therefore critical to enabling the IU’s work.​
  • Class 3 RBIs are the scarcest professional resource.​
  • We are working to grow capacity to meet demand and to support other application categories such as remediation, including supporting with additional HR resource to enable this. Increasing capacity remains both a priority and a challenge for BSR.​

Gateway 2: Data tables

National data

Innovation Unit Remediation All categories
In progress 131 359 1,445
New in 64 119 750
Decisions made 31 67 358
Invalid and withdrawn 15 14 396
Rejections 2 14 88
Complex rejections 1 0 1
Rejection % 10 21 25
Rejection weeks 28 32 25
Approvals 16 53 249
Complex approvals 12 0 20
Approval % 90 79 75
Approval weeks 22 39 32
Complex approval weeks 33 Not applicable 33
In progress units 30,369 32,340  
Approved units 3,002 5,030 Not applicable

London data

Innovation Unit Remediation All categories
In progress 87 201 894
New in 40 65 436
Decisions made 19 36 234
Invalid and withdrawn 5 6 238
Rejections 0 12 50
Complex rejections 0 0 0
Rejection % 0 33 21
Rejection weeks Not applicable 0 28
Approvals 12 24 174
Complex approvals 7 0 10
Approval % 100 67 79
Approval weeks 22 51 33
Complex approval weeks 35 Not applicable 33
In progress units 17,486 17,597 Not applicable
Approved units 2,109 1,294 Not applicable