Building Safety Regulator building control approval application data December 2025 to February 2026
Updated 11 March 2026
Applies to England
All data is correct as of 25 February 2026 and provided by the Building Safety Regulator (BSR).
Gateway 2: Priority headline numbers for new build
| Status | Legacy cases | Innovation Unit | Legacy transitional cases | Total |
|---|---|---|---|---|
| New cases received | 0 | 82 | 0 | 82 |
| Decisions made | 57 | 48 | 3 | 108 |
| Live cases as of 1 Oct | 91 | 27 | 34 | 152 |
| Live cases as of 25 Feb | 3 | 123 | 29 | 155 |
Total number of units in new cases received 15,178
Total number of units in decisions made 23,197
Total number of units in live cases as of 25 February 31,191
Commentary
- In the 12-week rolling period to 25 February, 108 new build applications have been determined with 82 new applications received.
- Legacy cases have reduced to 3 with 18 long-term cases with significant technical challenges transferred to a complex case category. This is where account managers work closely with applicants to try and progress to a successful outcome and to deliver safe homes.
- In the Innovation Unit (IU), we have changed the calculation method this month to better reflect the application progress. This shows that, for applications that successfully pass validation, the approval rate is currently 33% (up from 30% last month). A further 30% of cases are subject to account management interventions, as we continue to work to reach an approval despite the application progressing beyond 12 weeks.
- Over the past 12 weeks new applications representing 15,178 residential units have been received. Applications representing 23,197 units have been determined, of which 10,514 were approvals. There are currently 31,191 units in live cases.
Innovation Unit: new in versus decisions (national)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 11 | 5 | 95 |
| 15 Dec | 21 | 9 | 107 |
| 22 Dec | 7 | 8 | 106 |
| 29 Dec | 1 | 0 | 107 |
| 5 Jan | 5 | 4 | 108 |
| 12 Jan | 4 | 0 | 112 |
| 19 Jan | 7 | 1 | 118 |
| 26 Jan | 7 | 16 | 109 |
| 2 Feb | 6 | 2 | 113 |
| 9 Feb | 3 | 0 | 116 |
| 16 Feb | 9 | 1 | 124 |
| 23 Feb | 1 | 2 | 123 |
Innovation Unit: performance totals (national)
| Description | Total |
|---|---|
| New in | 82 |
| Live | 123 |
| Units approved | 2,336 |
| Units in progress | 26,224 |
Innovation Unit: performance percentages and weeks taken (national)
There were a total of 27 decisions made, taking a median time of 18 weeks.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 4% | 12 |
| Rejections | 33% | 11 |
| Decision made, with account manager | 30% | 25 |
| Approval | 33% | 18 |
Commentary
-
The head of work in the IU has risen slightly to 123. We expect this to rise further before stabilising.
-
In response to stakeholder feedback, we have changed our calculation method this month to better show how applications progress. Invalidation numbers are the ‘new’ applications that have failed validation in the last 12 weeks. The percentages of withdrawn, rejections and approvals are then shown as a proportion of the total number of applications that have passed validation.
-
In total, 11 applications have been approved with the median approval time now at 18 weeks.
-
We have seen the median approval time increase to 18 weeks. This is a consequence of applications that have moved into account management post-12 weeks reaching a successful outcome.
How we are accelerating work to drive down approval times
We are:
- enhancing consistency conventions to address areas of technical dispute between experts
- exploring third-party independent validation of key design elements
- accelerating the onboarding of specialists when needed (for example, geo-spatial engineers or computer modelling specialists)
Legacy cases: new in versus decisions (national)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 0 | 2 | 58 |
| 15 Dec | 0 | 16 | 42 |
| 22 Dec | 0 | 4 | 38 |
| 29 Dec | 0 | 0 | 38 |
| 5 Jan | 0 | 4 | 34 |
| 12 Jan | 0 | 0 | 34 |
| 19 Jan | 0 | 2 | 32 |
| 26 Jan | 0 | 21 | 11 |
| 2 Feb | 0 | 1 | 10 |
| 9 Feb | 0 | 3 | 7 |
| 16 Feb | 0 | 4 | 3 |
| 23 Feb | 0 | 0 | 3 |
Legacy cases: performance (national)
| Description | Total |
|---|---|
| New in | 0 |
| Live | 3 |
| Units approved | 7,127 |
| Units in progress | 895 |
Legacy cases: performance percentages and weeks taken (national)
There were a total of 57 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 4% | 43 |
| Rejections | 12% | 36 |
| Decision made, with account manager | 32% | 37 |
| Approval | 53% | 39 |
Commentary
-
The backlog of legacy new build cases has almost been cleared. From 60 at the start of December to just 3 ‘regular’ cases remaining and a small cohort of 18 technically complex applications which are now being dealt with via a complex case process.
-
The complex case process allows us to work through particularly challenging technical issues with applicants to try and reach successful outcomes and support the delivery of safe homes.
-
This will be the last month that we will report on this category of application in this way.
Remediation: new in versus decisions (national)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 8 | 4 | 299 |
| 15 Dec | 23 | 13 | 309 |
| 22 Dec | 4 | 8 | 305 |
| 29 Dec | 1 | 2 | 304 |
| 5 Jan | 3 | 4 | 303 |
| 12 Jan | 6 | 5 | 304 |
| 19 Jan | 4 | 8 | 300 |
| 26 Jan | 6 | 15 | 291 |
| 2 Feb | 8 | 9 | 290 |
| 9 Feb | 4 | 10 | 284 |
| 16 Feb | 10 | 10 | 284 |
| 23 Feb | 0 | 5 | 279 |
Remediation: performance (national)
| Description | Total |
|---|---|
| New in | 77 |
| Live | 279 |
| Units approved | 5,712 |
| Units in progress | 24,282 |
Remediation: performance percentages and weeks taken (national)
There were a total of 86 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 9% | 38 |
| Rejections | 38% | 23 |
| Decision made, with account manager | 0% | Not applicable |
| Approval | 48% | 31 |
Commentary
-
The level of approvals has increased slightly to 48% while the average approval time has decreased from 34 to 31 weeks.
-
Open remediation cases have declined over the last 12 weeks.
-
We remain focused on closing out older applications submitted at the start of the regime which typically do not contain sufficient detail for a decision and so require significant effort to move through to a successful conclusion.
-
In parallel, we focus on higher -risk projects and those where there is a funding constraint.
-
Remediation applications are often missing important elements of detail needed to demonstrate compliance. In response to this, we will be publishing specific remediation guidance in the coming weeks alongside improved feedback and support for applicants.
-
This month, we will also introduce a more detailed remediation improvement plan which will set out how we intend to bolster resources, improve processes and work with applicants to improve application quality.
-
The batching method continues to be used to support rapid initial assessment of remediation applications.
Gateway 2: All categories (national)
All categories: new in versus decisions (national)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 66 | 58 | 1,204 |
| 15 Dec | 105 | 121 | 1,188 |
| 22 Dec | 37 | 59 | 1,166 |
| 29 Dec | 8 | 11 | 1,163 |
| 5 Jan | 59 | 44 | 1,178 |
| 12 Jan | 60 | 41 | 1,197 |
| 19 Jan | 47 | 49 | 1,195 |
| 26 Jan | 74 | 86 | 1,183 |
| 2 Feb | 62 | 48 | 1,197 |
| 9 Feb | 59 | 37 | 1,219 |
| 16 Feb | 62 | 57 | 1,224 |
| 23 Feb | 16 | 28 | 1,212 |
All categories: performance (national)
| Description | Total |
|---|---|
| New in | 655 |
| Live | 1,212 |
All categories: performance percentages and weeks taken (national)
There were a total of 366 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 14% | 33 |
| Rejections | 17% | 25 |
| Decision made, with account manager | 7% | 33 |
| Approval | 49% | 30 |
Commentary
-
The number of live applications of all categories at gateway 2 remains relatively flat.
-
New applications marginally exceeded the number of decisions made over the past 12 weeks with a total of 639 closed applications against 655 new applications.
-
Category A and B applications account for circa over 75% of gateway 2 volume of decisions.
Gateway 2: Regional distribution
Data as of the 25 February 2026.
Regional gateway 2 applications (London)
| Region | Innovation Unit | Legacy cases | Remediation | Total |
|---|---|---|---|---|
| London | 69 | 2 | 156 | 227 |
| Rest of country | 50 | 1 | 123 | 174 |
Regional gateway 2 applications (rest of England)
| Region | Innovation Unit | Legacy cases | Remediation | Total |
|---|---|---|---|---|
| East | 1 | 0 | 13 | 14 |
| East Midlands | 1 | 0 | 15 | 16 |
| North-east | 1 | 0 | 8 | 9 |
| North-west | 22 | 0 | 31 | 53 |
| South-east | 6 | 0 | 17 | 23 |
| South-west | 3 | 0 | 12 | 15 |
| West Midlands | 3 | 1 | 12 | 16 |
| Yorkshire and The Humber | 13 | 0 | 15 | 28 |
Gateway 2: Innovation Unit (London)
Innovation Unit: new in versus decisions (London)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 7 | 4 | 42 |
| 15 Dec | 14 | 5 | 51 |
| 22 Dec | 5 | 5 | 51 |
| 29 Dec | 1 | 0 | 52 |
| 5 Jan | 4 | 3 | 53 |
| 12 Jan | 3 | 0 | 56 |
| 19 Jan | 5 | 0 | 61 |
| 26 Jan | 5 | 5 | 61 |
| 2 Feb | 3 | 0 | 64 |
| 9 Feb | 0 | 0 | 64 |
| 16 Feb | 4 | 0 | 68 |
| 23 Feb | 1 | 0 | 69 |
Innovation Unit: performance (London)
| Description | Total |
|---|---|
| New in | 52 |
| Live | 69 |
| Units approved | 249 |
| Units in progress | 13,075 |
Innovation Unit: performance percentages and weeks taken (London)
There were a total of 10 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 0% | Not applicable |
| Rejections | 40% | 13 |
| Decision made, with account manager | 30% | 27 |
| Approval | 30% | 12 |
Commentary
-
Around half of the current live IU applications are in London.
-
This also represents around 50% of the overall residential units handled by the IU.
-
10 of the 27 decisions that the IU has made in the last 12 weeks are in London.
-
London approval rates are slightly lower than nationally.
Gateway 2: Legacy cases (London)
Legacy cases: new in versus decisions (London)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 0 | 1 | 34 |
| 15 Dec | 0 | 9 | 25 |
| 22 Dec | 0 | 3 | 22 |
| 29 Dec | 0 | 0 | 22 |
| 5 Jan | 0 | 0 | 22 |
| 12 Jan | 0 | 0 | 22 |
| 19 Jan | 0 | 2 | 20 |
| 26 Jan | 0 | 13 | 7 |
| 2 Feb | 0 | 0 | 7 |
| 9 Feb | 0 | 2 | 5 |
| 16 Feb | 0 | 3 | 2 |
| 23 Feb | 0 | 0 | 2 |
Legacy cases: performance (London)
| Description | Total |
|---|---|
| New in | 0 |
| Live | 2 |
| Units approved | 3,592 |
| Units in progress | 749 |
Legacy cases: performance percentages and weeks taken (London)
There were a total of 33 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 6% | 43 |
| Rejections | 12% | 54 |
| Decision made, with account manager | 33% | 37 |
| Approval | 48% | 44 |
Commentary
-
Legacy cases in London have reduced sharply, mirroring the national picture.
-
From 35 live cases in December 2025, the cohort has reduced to 2, with 12 cases transferred to the complex case category where they will be closely managed.
-
3,592 residential units have been approved.
Gateway 2: Remediation (London)
Remediation: new in versus decisions (London)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 5 | 2 | 163 |
| 15 Dec | 12 | 6 | 169 |
| 22 Dec | 2 | 2 | 169 |
| 29 Dec | 0 | 1 | 168 |
| 5 Jan | 2 | 2 | 168 |
| 12 Jan | 2 | 4 | 166 |
| 19 Jan | 2 | 5 | 163 |
| 26 Jan | 1 | 6 | 158 |
| 2 Feb | 4 | 4 | 158 |
| 9 Feb | 2 | 4 | 156 |
| 16 Feb | 7 | 5 | 158 |
| 23 Feb | 0 | 2 | 156 |
Remediation: performance (London)
| Description | Total |
|---|---|
| New in | 39 |
| Live | 156 |
| Units approved | 3,003 |
| Units in progress | 11,465 |
Remediation: performance percentages and weeks taken (London)
There were a total of 41 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 15% | 36 |
| Rejections | 46% | 27 |
| Decision made, with account manager | 0% | Not applicable |
| Approval | 39% | 37 |
Commentary
-
Open remediation cases in London have decreased slightly over the period from 160 to 156.
-
We recognise that application quality, alongside improvements in BSR processes and resources are needed, and we will be bringing forward a BSR remediation improvement plan in the coming weeks detailing how we intend to achieve this.
Gateway 2: All categories (London)
All categories: new in versus decisions (London)
| Week commencing | New in | Decisions | Total live cases |
|---|---|---|---|
| 8 Dec | 40 | 44 | 762 |
| 15 Dec | 76 | 86 | 752 |
| 22 Dec | 28 | 40 | 740 |
| 29 Dec | 6 | 6 | 740 |
| 5 Jan | 38 | 27 | 751 |
| 12 Jan | 34 | 27 | 758 |
| 19 Jan | 30 | 33 | 755 |
| 26 Jan | 47 | 49 | 753 |
| 2 Feb | 35 | 28 | 760 |
| 9 Feb | 33 | 17 | 776 |
| 16 Feb | 38 | 33 | 781 |
| 23 Feb | 8 | 14 | 775 |
All categories: performance (London)
| Description | Total |
|---|---|
| New in | 413 |
| Live | 775 |
All categories: performance percentages and weeks taken (London)
There were a total of 239 decisions made.
| Description | Percentage | Weeks taken (median) |
|---|---|---|
| Withdrawn | 23% | 49 |
| Rejections | 31% | 27 |
| Decision made, with account manager | 5% | 35 |
| Approval | 41% | 29 |
Commentary
- The number of live London applications of all categories at gateway 2 shows a slight increase, from 766 to 775 over the past 12 weeks.
*A total of 404 applications have been closed, set against 413 new applications received.
- 65% of all decisions across all gateway 2 categories in the past 12 weeks related to London cases.
*Category A and B applications account for around 75% of gateway 2 volume of decisions in London.
Building control: Batching pilot
Batch volumes: cases allocated by batch number
| Batch number | New build | Refurbs | Remediation | Total |
|---|---|---|---|---|
| 1 | 12 | 27 | 10 | 49 |
| 2 | 0 | 32 | 14 | 46 |
| 3 | 8 | 20 | 8 | 36 |
| 4 | 23 | 46 | 18 | 87 |
| 5 | 5 | 33 | 17 | 55 |
| 6 | 4 | 46 | 17 | 67 |
| 7 | 28 | 60 | 42 | 130 |
| 8 | 8 | 33 | 13 | 55 |
| 9 | 9 | 12 | 9 | 30 |
| 10 | 3 | 17 | 19 | 49 |
| 11 | 0 | 24 | 15 | 39 |
| 12 | 11 | 19 | 3 | 33 |
| 13 | 11 | 22 | 26 | 59 |
| 14 | 6 | 19 | 24 | 49 |
| 15 | 12 | 5 | 3 | 20 |
| 16 | 16 | 34 | 19 | 69 |
| 17 | 1 | 0 | 0 | 1 |
| 18 | 10 | 3 | 4 | 17 |
| 19 | 3 | 14 | 17 | 34 |
Commentary
-
The data shown in this and following slides is a subset of the overall data shown on earlier slides – for example, batching is part of the overall process, not additional.
-
A pilot batching process was launched during September 2025, acknowledging that the original multi-disciplinary team (MDT) model was not effective for managing the volume of cases across all categories of application.
-
This new pilot process scales capacity by bundling applications to specialised engineering services suppliers for accelerated assessment, with BSR maintaining regulatory oversight. The primary goal of batching is to accelerate backlog resolution in new build and remediation applications.
-
The first of these mixed-category bundles (26 cases) was sent to suppliers on 30 September 2025. Weekly dispatch of subsequent bundles have been, and continue to be, based on supplier capacity.
-
Initial processing times for applications allocated to batching is significantly quicker than under the previous model.
-
The model follows a process where batches are issued to suppliers, they then have a limited time to accept or reject the cases in the allocation based on their capacity and any conflicts of interest. Once accepted, suppliers then have a defined period to return their assessments for consideration by BSR’s regulatory leads.
Batching pilot performance: new builds
| Issued | Not yet accepted | Accepted | Returned | Decision made |
|---|---|---|---|---|
| 206 | 91 | 115 | 50 | 26 |
Median weeks from issued to return 4
Median weeks from issued to decision 7
Batched new build decisions
| Decision made | Percentage |
|---|---|
| Approval | 27% |
| Approval with requirements | 19% |
| Rejection | 46% |
| Withdrawn | 8% |
Commentary
-
Batching in new builds is being used to support only part of the overall building control application with the majority of the applications being considered by our in-house teams.
-
The batching approach is being used in some cases to access specialist resource to evaluate computational fluid dynamics modelling in support of fire strategies submitted as part of an application.
Batching pilot performance: external remediation
| Issued | Not yet accepted | Accepted | Returned | Decision made |
|---|---|---|---|---|
| 264 | 147 | 117 | 88 | 19 |
Median weeks from issued to return 4
Median weeks from issued to decision 9
Batched remediation decisions
| Decision made | Percentage |
|---|---|
| Approval | 11% |
| Approval with requirements | 5% |
| Rejection | 84% |
| Withdrawn | 0% |
Commentary
-
External remediation often requires a ‘full’ MDT, made up of the 3 core specialisms: registered building inspector (RBI), fire and structural engineers.
-
Batching allows us to allocate remediation applications to one or more suppliers who have these capabilities available (while BSR maintains regulatory oversight) and is distributed across suppliers according to capacity.
Batching pilot performance: refurbishments
| Issued | Not yet accepted | Accepted | Returned | Decision made |
|---|---|---|---|---|
| 504 | 268 | 236 | 189 | 25 |
Median weeks from issued to return 3
Median weeks from issued to decision 8
Batched refurbishment decisions
| Decision made | Percentage |
|---|---|
| Approval | 32% |
| Approval with requirements | 0% |
| Rejection | 64% |
| Withdrawn | 4% |
Commentary
-
As with external remediation, category A refurbishments often require a ‘full’ MDT, made up of the 3 core specialisms: RBI, fire and structural engineers.
-
Batching allows us to allocate these refurbishment applications to one or more suppliers who have these capabilities available and is distributed across suppliers according to capacity.
Gateway 2: Innovation Unit resources
| Role | Actual as of 20 Jan | Forecast February (mid-month) | Forecast March (mid-month) | Forecast April (mid-month) |
|---|---|---|---|---|
| Registered building inspectors | 21 | 25 | 26 | 26 |
| Structural engineers | 18 | 18 | 18 | 18 |
| Fire engineers | 6.6 | 8 | 8 | 8 |
All numbers are full-time equivalent – for example, some people are available to BSR fewer than 5 days per week, so the totals shown are aggregated.
Commentary
-
BSR draws building inspector, fire engineer and structural engineer resources from partner organisations across the public and private sector.
-
These resources were brought in-house within BSR for the first time as part of the IU and allow BSR to have better control over resource allocation and tasking.
-
The provision of sufficient resource of this type is therefore critical to enabling the IU’s work.
-
Class 3 registered building inspectors (RBIs) are the most scarce.
-
We are working to grow capacity to meet demand and to support other application categories such as remediation.