All data is correct as of 1 November 2026 and provided by the Building Safety Regulator (BSR).
Introduction
As in previous months, this BSR dataset includes information relating to gateway 2 performance, with the London area performance separate. In addition, several new datasets have also been included this month.
Recent trends
We’re continuing to manage the increased volume of applications that we received ahead of the building safety levy coming into effect on 1 October 2026. This involves triaging applications before applying demand management measures. This process is set out in the building safety levy surge handling plan. The current progress of affected applications is in the building safety levy surge update.
We anticipate that all applications will have been through this process by the second week of November. Applications will either proceed through normal assessment or be subject to a demand management measure, such as being placed on an agreed pause.
We have included an overview of older remediation cases. This data shows how applications received in 2026 are improving in quality and progressing more quickly.
As more new build projects are now moving into construction, we’ve included further data on their progress, including projects that have started on site.
From next month, we will include data relating to our investigations and enforcement activities.
Gateway 2: headline numbers for August to October 2026
| Status |
New higher-risk buildings (HRBs) and conversions |
External remediation |
|
| Cases in progress |
183 |
292 |
|
| Invalid or withdrawn |
4 |
15 |
|
| Decisions made |
42 |
122 |
|
| New in |
96 |
90 |
|
| Approval rate |
95% |
93% |
|
| Median approval time |
20 weeks |
32 weeks |
|
| Units approved |
9,453 |
9,956 |
|
| Units in progress |
39,843 |
23,479 |
|
- Median approval time for new build applications shows a decrease to 20 weeks although fluctuation may be expected in line with the changing volume of applications submitted.
- The approval rate for new build applications remains high at 95%.
- 42 new build decisions have been made in the last 12 weeks.
- We saw a notable increase in new build applications in September. There were 64 in total, compared to 34 in August and 17 in July. We are attributing this to applicants submitting applications ahead of the building safety levy coming into effect on 1 October 2026. We have activated contingency plans to deal with this expected surge.
- New applications dropped to 6 in October.
- External remediation median approval times have remained at 32 weeks, while approval rates have increased from 89% to 93%.
- We continue to reduce the overall number of external remediation applications awaiting a decision.
Gateway 2: headline numbers for August to October 2026 – internal works and NHS
| Status |
Higher-risk building (HRB) internal works |
NHS internal works |
| Cases in progress |
1,116 |
34 |
| Invalid or withdrawn |
139 |
7 |
| Decisions made |
218 |
21 |
| New in |
470 |
26 |
| Approval rate |
91% |
86% |
| Median approval time |
30 weeks |
20 weeks |
-
NHS applications continue as a separate category. They have previously been reported on within the HRB internal works dataset.
- These can include a range of building work in hospitals, from maintenance through to new hospital facilities.
- We have been working closely with the NHS to facilitate the specialist nature of their applications.
- The median approval time for NHS applications remains at 20 weeks with an associated approval rate now at 86%.
- Internal works (category A and B) have seen approval rates increase from 85% to 91%, with approval time reducing slightly to 30 weeks. Work continues to improve our efficiency and capacity in relation to this type of application.
Building safety levy surge update
| Application status |
Early surge |
Late surge |
| Validated under normal system – may be subject to demand management action |
50 |
0 |
| Validated under normal system – on pause with agreement of applicant |
2 |
0 |
| Undergoing enhanced validation |
0 |
9 |
| Recommended for rejection – subject to final review |
0 |
8 |
| Poor quality, on pause with agreement of applicant |
0 |
18 |
| Good quality, proceed to detailed assessment |
0 |
6 |
We are actively managing the surge of applications received in August and September. These applications fall into 2 groups.
Early surge applications
52 applications received in between 1 August and 20 September were validated through the standard process.
Late surge applications
- 41 applications received on and after 21 September will go through enhanced validation.
- Of the applications that have undergone enhanced validation, 18 were assessed as poor quality and placed on pause to give the applicant time to improve their application.
- A further 8 are recommended for rejection, but are subject to a final review with the applicant to assess the implications of rejection for each individual scheme.
- The 9 still undergoing validation will complete their assessment by 10 November.
Building safety levy surge handling plan
The levy surge handling plan is made up of 5 stages.
Stage 1: Enhanced validation and initial review
Developers that have not previously made an application are prioritised.
The application is received and undergoes:
- standard validation checks by a case officer
- an enhanced registered building inspector (RBI) review
This step is supported by regulatory leads and can take up to 2 days per application.
The application then goes to a weekly moderation panel review, which:
- looks at the consistency of the approach
- determines the most appropriate route for the application
- considers demand management options
Stage 2: Triage categorisation (first order assurance)
Applications are placed into one of 2 categories.
| Category |
Description |
| 1: Clearly invalid or very poor quality |
These applications have significant omissions or fail to meet basic submission requirements. |
| 2: Questionable quality |
These applications are formally valid but are of insufficient quality to support efficient progression. |
| 3: Good quality |
These applications are well-developed, have a credible approach to compliance and are suitable for progression. |
Stage 3: Demand management measures
The next stage depends on the category the application has been assigned.
| Category |
Measure |
Description |
| 1 |
A. Validation amnesty |
Short period to provide missing documentation (documentary omissions only). |
| |
B. Voluntary pause |
Opportunity to pause while improvements are made. |
| 2 |
B. Voluntary pause |
Opportunity to pause while improvements are made. |
| 3 |
C. Delayed determination |
Agree a delayed determination timetable (through an extension of time). |
| |
D. Prioritisation of multiple applications |
Applicant decides which applications to prioritise. |
Stage 4: Senior management review (second order assurance)
In this stage, senior management will:
- review recommended invalidations or rejections
- consider wider factors such as financial impact, applicant relationship, likelihood of progression, and the nature of the development
- ensure consistent, proportionate and defensible decisions
This may result in:
- the recommendation being upheld
- further work with the applicant
- a face-to-face meeting with the applicant before a formal communication of the outcome
Stage 5: Decision and detailed assessment
Following the senior management review, applications will then be either:
- invalidated or rejected
- progressed to detailed assessment
If progressed, it will go through to the detailed technical assessment with a full multidisciplinary team.
Progressed applications will be prioritised by:
- complexity
- developer priorities
- known deadlines and interdependencies
All application categories
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
|
| 10 August |
48 |
25 |
1,603 |
|
| 17 August |
71 |
50 |
1,624 |
|
| 24 August |
100 |
60 |
1,664 |
|
| 31 August |
41 |
34 |
1,671 |
|
| 7 September |
50 |
46 |
1,675 |
|
| 14 September |
46 |
38 |
1,683 |
|
| 21 September |
79 |
68 |
1,694 |
|
| 28 September |
76 |
62 |
1,708 |
|
| 5 October |
40 |
65 |
1,683 |
|
| 12 October |
44 |
43 |
1,684 |
|
| 19 October |
57 |
56 |
1,685 |
|
| 26 October |
45 |
43 |
1,687 |
|
- There are currently 1,687 gateway 2 applications in progress. This is a decrease of 21 in October.
- These include the new build, external remediation, internal refurbishment and NHS applications.
- Transitional cases are also included. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading.
- Commenced under the previous building control regime, they are generally much more complicated to progress. This is because much of the evidence (which can relate to safety critical aspects) that we now expect at gateway 2 is not available.
- There are currently 62 transitional cases in progress at gateway 2.
New HRBs and conversions (national)
New HRBs and conversions (national): new in versus closed decisions
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
|
| 10 August |
6 |
4 |
135 |
|
| 17 August |
12 |
3 |
144 |
|
| 24 August |
7 |
4 |
147 |
|
| 31 August |
5 |
2 |
150 |
|
| 7 September |
8 |
3 |
155 |
|
| 14 September |
7 |
5 |
157 |
|
| 21 September |
20 |
8 |
169 |
|
| 28 September |
25 |
9 |
185 |
|
| 5 October |
1 |
1 |
185 |
|
| 12 October |
2 |
2 |
185 |
|
| 19 October |
0 |
3 |
182 |
|
| 26 October |
3 |
2 |
183 |
|
| Description |
Total |
| New in |
96 |
| In progress |
183 |
| Units approved |
9,453 |
| Units in progress |
39,843 |
New HRBs and conversions: percentages and weeks taken (national)
In the period, there were:
- 42 decisions made
- 4 invalid or withdrawn applications
- 35 complex cases in progress with a median approval time of 35 weeks
| Description |
Percentage |
Weeks taken (median) |
|
| Rejection rate |
5% |
16 |
|
| Approval rate |
95% |
20 |
|
- Out of 96 applications received over the past 12 weeks, 3 applications were invalidated and 1 was withdrawn. Of the 42 decisions made, 40 were approvals and 2 were rejections.
- This means that the 12-week rolling approval rate (not including invalidations and withdrawals) now stands at 95%, with the median approval time dropping to 20 weeks.
- Complex cases are now tracked separately. While the final decision is included in the rejection or approval totals, their median approval time is now at 35 weeks.
- New applications have dropped significantly from 64 in September to 6 in October. We believe this is a dip following the surge.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
|
| 10 August |
14 |
5 |
348 |
|
| 17 August |
6 |
13 |
341 |
|
| 24 August |
11 |
16 |
336 |
|
| 31 August |
2 |
5 |
333 |
|
| 7 September |
6 |
13 |
326 |
|
| 14 September |
9 |
10 |
325 |
|
| 21 September |
11 |
15 |
321 |
|
| 28 September |
8 |
7 |
322 |
|
| 5 October |
6 |
19 |
309 |
|
| 12 October |
2 |
10 |
301 |
|
| 19 October |
12 |
13 |
300 |
|
| 26 October |
3 |
11 |
292 |
|
| Description |
Total |
|
| New in |
90 |
|
| In progress |
292 |
|
| Units approved |
9,956 |
|
| Units in progress |
23,479 |
|
In the period, there were:
- 122 decisions made
- 15 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
|
| Rejection rate |
7% |
34 |
|
| Approval rate |
93% |
32 |
|
- The rolling 12-week approval rate is 93%, with the median approval time remaining steady at 32 weeks. In November 2025, approval rates stood at 32% with a decision time of 44 weeks.
- Decision times remain above target as we continue to close older cases which have been in the system for some time.
- Only 5 legacy applications from 2024 remain. This includes a set of 4 on one development. This is down from 42 at the start of 2026 and is on track to be cleared by the end of November 2026.
- Applications submitted in 2026 are progressing in approximately 26 weeks with high approval rates.
- We continue to work with the sector to help applicants improve the quality of their applications. The Remediation Toolkit is helping applicants submit stronger applications.
Live gateway 2 applications by submission month
| Month |
Applications |
|
| December 2024 |
5 |
|
| February 2025 |
2 |
|
| January 2025 |
2 |
|
| March 2025 |
1 |
|
| April 2025 |
2 |
|
| May 2025 |
2 |
|
| June 2025 |
3 |
|
| July 2025 |
2 |
|
| August 2025 |
0 |
|
| September 2025 |
3 |
|
| October 2025 |
6 |
|
| November 2025 |
9 |
|
| December 2025 |
9 |
|
| January 2026 |
9 |
|
| February 2026 |
13 |
|
| March 2026 |
22 |
|
| April 2026 |
33 |
|
| May 2026 |
22 |
|
| June 2026 |
29 |
|
| July 2026 |
27 |
|
| August 2026 |
40 |
|
| September 2026 |
27 |
|
| October 2026 |
24 |
|
2026 applications
| Month |
In progress |
Approved |
Median approval weeks |
| January 2026 |
9 |
19 |
27 |
| February 2026 |
12 |
21 |
32 |
| March 2026 |
22 |
26 |
28 |
| April 2026 |
33 |
15 |
20 |
| May 2026 |
22 |
8 |
20 |
| June 2026 |
29 |
6 |
15 |
| July 2026 |
27 |
4 |
15 |
- Most applications submitted before 2026 have no been determined.
- The remaining applications typically require further information from applicants. We continue to work with them to support the progression of their applications.
- In some cases, there are significant delays in applicants responding to BSR requests for information. Several weeks may pass before sufficient information is provided.
- Applications submitted in 2026 currently have a 90% approval rate and a median approval time of 26 weeks.
- There are encouraging signs that approval times are dropping further with more recent applications, but these times are likely to rise slightly over time as the old or legacy applications still in the system are closed.
- Nevertheless, this shows that better-quality applications can currently be determined in around 15 weeks.
HRB internal works (national)
HRB internal works (national): new in versus closed decisions
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
|
| 10 August |
25 |
13 |
1,015 |
|
| 17 August |
51 |
25 |
1,041 |
|
| 24 August |
78 |
37 |
1,082 |
|
| 31 August |
27 |
24 |
1,085 |
|
| 7 September |
32 |
25 |
1,092 |
|
| 14 September |
29 |
21 |
1,100 |
|
| 21 September |
46 |
36 |
1,110 |
|
| 28 September |
37 |
42 |
1,105 |
|
| 5 October |
31 |
41 |
1,095 |
|
| 12 October |
37 |
29 |
1,103 |
|
| 19 October |
40 |
36 |
1,107 |
|
| 26 October |
37 |
28 |
1,116 |
|
| Description |
Total |
|
| New in |
470 |
|
| In progress |
1,116 |
|
HRB internal works: percentages and weeks taken (national)
In the period, there were:
- 218 decisions made
- 139 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
|
| Rejection rate |
9% |
22 |
|
| Approval rate |
91% |
30 |
|
- The approval rate for internal refurbishment works in category A and B has increased to 91%, while the median approval time has fallen to 30 weeks.
- New applications have been received at an average rate of 39 per week over the past 12 weeks.
- The overall combined total is now at 1,116, having increased slightly over the past month.
-
HRB internal work determinations over the past 12 weeks account for around 54% of all gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.
- Work is underway to increase capacity for dealing with internal works, which is expected to happen in the coming months.
NHS internal works (national)
NHS internal works (national): new in versus closed decisions
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
|
| 10 August |
2 |
2 |
36 |
|
| 17 August |
2 |
6 |
32 |
|
| 24 August |
3 |
1 |
34 |
|
| 31 August |
5 |
2 |
37 |
|
| 7 September |
2 |
3 |
36 |
|
| 14 September |
1 |
1 |
36 |
|
| 21 September |
1 |
7 |
30 |
|
| 28 September |
3 |
1 |
32 |
|
| 5 October |
1 |
0 |
33 |
|
| 12 October |
3 |
0 |
36 |
|
| 19 October |
2 |
3 |
35 |
|
| 26 October |
1 |
2 |
34 |
|
| Description |
Total |
|
| New in |
26 |
|
| In progress |
34 |
|
NHS internal works: percentages and weeks taken (national)
In the period, there were:
- 21 decisions made
- 7 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
|
| Rejection rate |
14% |
18 |
|
| Approval rate |
86% |
20 |
|
-
NHS internal works are now split from HRB internal works.
- The approval rate for NHS internal refurbishment is currently 86%.
- The median approval time has reduced to 20 weeks.
- New applications have been received at an average rate of 2 per week over the past 12 weeks.
- Overall work has increased as we received slightly more applications than were closed.
Gateway 2: regional distribution
Data as of 1 November 2026.
Regional gateway 2 applications (London and rest of England)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
NHS |
Transitional |
| London |
110 |
171 |
751 |
18 |
32 |
| Rest of England |
48 |
118 |
343 |
15 |
26 |
Regional gateway 2 applications (rest of England)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
NHS |
Transitional |
| East |
4 |
11 |
44 |
1 |
1 |
| East Midlands |
0 |
10 |
26 |
2 |
1 |
| North East |
0 |
10 |
34 |
2 |
2 |
| North West |
17 |
30 |
48 |
2 |
11 |
| South East |
8 |
23 |
44 |
3 |
3 |
| South West |
6 |
24 |
78 |
3 |
4 |
| West Midlands |
10 |
2 |
37 |
0 |
1 |
| Yorkshire and The Humber |
3 |
8 |
32 |
2 |
3 |
New HRBs and conversions (London)
New HRBs and conversions (London): new in versus closed decisions
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 10 August |
6 |
1 |
89 |
| 17 August |
10 |
3 |
96 |
| 24 August |
2 |
2 |
96 |
| 31 August |
3 |
1 |
98 |
| 7 September |
4 |
2 |
100 |
| 14 September |
4 |
4 |
100 |
| 21 September |
12 |
8 |
104 |
| 28 September |
12 |
5 |
111 |
| 5 October |
1 |
1 |
111 |
| 12 October |
1 |
2 |
110 |
| 19 October |
0 |
1 |
109 |
| 26 October |
3 |
2 |
110 |
| Description |
Total |
| New in |
58 |
| In progress |
110 |
| Units approved |
6,733 |
| Units in progress |
21,997 |
New HRBs and conversions: percentages and weeks taken (London)
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
3% |
23 |
| Approval rate |
97% |
20 |
- Around 60% of in progress new build applications are in London.
- This also represents around 55% of the overall new build residential units handled by BSR.
- 29 of the 40 new build decisions made in the last 12 weeks are in London.
- London approval rates are 97%. This figure shows significant work to resolve outstanding complex cases.
- Approval time for non-complex cases is 20 weeks, in line with the national average.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 10 August |
6 |
3 |
189 |
| 17 August |
3 |
4 |
188 |
| 24 August |
9 |
8 |
189 |
| 31 August |
1 |
0 |
190 |
| 7 September |
2 |
8 |
184 |
| 14 September |
5 |
3 |
186 |
| 21 September |
5 |
8 |
183 |
| 28 September |
6 |
4 |
185 |
| 5 October |
5 |
12 |
178 |
| 12 October |
1 |
4 |
175 |
| 19 October |
6 |
9 |
172 |
| 26 October |
1 |
2 |
171 |
| Description |
Total |
| New in |
50 |
| In progress |
171 |
| Units approved |
4,881 |
| Units in progress |
13,180 |
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
2% |
24 |
| Approval rate |
98% |
39 |
- Open remediation cases in London have dropped over the period from 186 to 171.
- Progress has been made since the announcement of the BSR remediation improvement plan in April 2026. There are now 5 legacy applications from 2024 remaining, down from 42 at the start of 2026.
- The median approval time in weeks, based on the rolling total, shows our effort to close older applications, but these continue to affect overall median approval times.
- Applications submitted in 2026 are being determined much more quickly.
- London approval rates of 98% are slightly higher than they are nationally.
HRB internal works (London)
HRB internal works (London): new in versus closed decisions
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 10 August |
23 |
9 |
681 |
| 17 August |
31 |
17 |
695 |
| 24 August |
65 |
17 |
743 |
| 31 August |
18 |
20 |
741 |
| 7 September |
16 |
20 |
737 |
| 14 September |
21 |
17 |
741 |
| 21 September |
32 |
23 |
750 |
| 28 September |
31 |
35 |
746 |
| 5 October |
24 |
28 |
742 |
| 12 October |
24 |
24 |
742 |
| 19 October |
29 |
24 |
747 |
| 26 October |
21 |
17 |
751 |
| Description |
Total |
| New in |
335 |
| In progress |
751 |
HRB internal works: percentages and weeks taken (London)
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
8% |
23 |
| Approval rate |
92% |
32 |
- The approval rate for internal refurbishment works in category A and B is currently 92%, with a median approval time of 32 weeks. This is in line with the national average.
- The overall combined total is less than the expected total of between 850 and 900. It has been steady at between 740 and 750 over the past 2 months.
-
HRB internal work determinations over the past 12 weeks account for around 63% of gateway 2 decisions. These applications include all internal refurbishment works, except NHS applications.
NHS internal works (London)
NHS internal works (London): new in versus closed decisions
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 10 August |
2 |
0 |
17 |
| 17 August |
0 |
4 |
13 |
| 24 August |
1 |
0 |
14 |
| 31 August |
3 |
0 |
17 |
| 7 September |
0 |
2 |
15 |
| 14 September |
1 |
0 |
16 |
| 21 September |
1 |
1 |
16 |
| 28 September |
2 |
0 |
18 |
| 5 October |
0 |
0 |
18 |
| 12 October |
1 |
0 |
19 |
| 19 October |
0 |
1 |
19 |
| 26 October |
0 |
0 |
18 |
| Description |
Total |
| New in |
11 |
| In progress |
18 |
NHS internal works: percentages and weeks taken (London)
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
14% |
18 |
| Approval rate |
86% |
20 |
-
NHS internal works have been split from HRB internal works.
- The approval rate for NHS internal refurbishment works is currently 86%, with a median approval time of 20 weeks.
Building control resources
Building control resources: people working on building control applications
| Week commencing |
Internal resources |
External resources |
Total resources |
| 10 August |
142 |
245 |
387 |
| 17 August |
141 |
239 |
380 |
| 24 August |
141 |
247 |
388 |
| 31 August |
134 |
250 |
384 |
| 7 September |
149 |
272 |
421 |
| 14 September |
151 |
278 |
429 |
| 21 September |
156 |
281 |
437 |
| 28 September |
147 |
279 |
426 |
| 5 October |
139 |
279 |
418 |
| 12 October |
129 |
272 |
401 |
| 19 October |
177 |
279 |
456 |
| 26 October |
131 |
243 |
374 |
| Description |
Total |
| Internal resources |
175 |
| External resources |
514 |
| Integrated resources |
62 |
Building control resources: resource breakdown
Internal resources
| Description |
Total |
| Regulatory leads |
103 |
| Principal regulatory leads |
19 |
| Case officers |
50 |
| Case officer managers |
2 |
| Administrative officers |
1 |
External resources
| Description |
Total |
| Registered building inspectors (RBIs) |
245 |
| Fire service professionals |
115 |
| Structural engineers |
116 |
| Specialists |
38 |
Integrated resources
| Description |
Total |
| Registered building inspectors (RBIs) |
36 |
| Fire service professionals |
6 |
| Structural engineers |
24 |
- Sufficient internal, external and integrated resources are essential for BSR to meet demand. By the end of 2026, we expect to have doubled the overall number of operational regulatory staff compared to August 2025. We are also growing our integrated resource teams.
- 175 internal staff members have been or are currently involved.
- 514 people from external organisations have been or are currently involved.
- Of the 491 people sourced or seconded from external organisations, 62 are integrated into BSR’s Innovation Unit or external remediation teams.
Building control integrated resources
BSR has several specialist resources working as part of an integrated workforce in the new build and external remediation teams. We are growing this capacity to meet demand and reduce processing times.
| Resource |
Full-time equivalent as of 3 November (FTE) |
Headcount as of 3 November |
Forecast December (FTE) |
Forecast January (FTE) |
Forecast February (FTE) |
| Registered building inspectors |
24.6 |
36 |
28 |
30 |
35 |
| Structural engineers |
22 |
24 |
23 |
23 |
26 |
| Fire service professionals and engineers |
5.6 |
6 |
5.6 |
5.6 |
10.6 |
Full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.
In build: progress of new build projects to site
| Project stage |
Applications |
Residential units |
| Gateway 2 in progress |
183 |
39,843 |
| Approved, not in build |
96 |
24,833 |
| Approved, in build |
114 |
24,689 |
As the population of new build projects passing through gateway 2 has increased, BSR has been tracking the progress of those that move to commencement.
This chart shows both the number of applications and the associated number of residential units broken down into applications that have been:
- submitted to gateway 2 that have not yet been decided
- approved at gateway 2 but have not yet commenced on site
- approved and have commenced on site
Major change requests
Data as of 1 November 2026.
In build: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 10 August |
17 |
8 |
200 |
| 17 August |
18 |
22 |
196 |
| 24 August |
9 |
7 |
198 |
| 31 August |
11 |
15 |
194 |
| 7 September |
18 |
11 |
201 |
| 14 September |
11 |
11 |
201 |
| 21 September |
16 |
3 |
214 |
| 28 September |
15 |
17 |
212 |
| 5 October |
24 |
13 |
223 |
| 12 October |
20 |
13 |
230 |
| 19 October |
17 |
7 |
240 |
| 26 October |
12 |
10 |
242 |
| Application type |
Live major change requests |
New in |
Closed |
Median weeks to close |
| New HRBs and conversions |
109 |
109 |
80 |
7 |
| External remediations |
32 |
27 |
20 |
16 |
|
HRB internal works |
75 |
42 |
29 |
26 |
|
NHS applications |
23 |
10 |
8 |
16 |
-
BSR recognises that timely processing of major change requests during build is vital to ensure construction can continue.
- There are currently 242 live major change requests. 137 requests have been closed in the period, including 137 shown in the data tables and zero transitional requests.
- The median closure time for new build projects is currently at 7 weeks, just one week more than the statutory target.
- Transitional major change requests make up the remaining 3 of the 242 not shown on the data tables, with zero new in and zero closed.
Gateway 3 applications from August to October 2026
Data as of 1 November 2026.
Gateway 3 applications: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 10 August |
4 |
1 |
135 |
| 17 August |
9 |
6 |
138 |
| 24 August |
9 |
3 |
144 |
| 31 August |
5 |
3 |
146 |
| 7 September |
4 |
4 |
146 |
| 14 September |
1 |
7 |
140 |
| 21 September |
6 |
2 |
144 |
| 28 September |
11 |
5 |
150 |
| 5 October |
6 |
0 |
156 |
| 12 October |
6 |
5 |
157 |
| 19 October |
4 |
3 |
158 |
| 26 October |
0 |
3 |
155 |
| Application type |
In progress |
Units |
Approvals |
New in |
| New HRBs and conversions |
0 |
0 |
0 |
0 |
| External remediation |
7 |
549 |
3 |
4 |
|
HRB internal works |
109 |
Not applicable |
24 |
54 |
|
NHS internal works |
13 |
Not applicable |
1 |
4 |
- No new build projects that have passed through gateway 2 have reached gateway 3.
- Inspection regime for new build projects has highlighted a small amount of building work that deviates from designs agreed in gateway 2. BSR will take a rigorous approach to ensure that safety is not compromised.
- Of the 379 gateway 3 applications received, 288 are internal refurbishments. Most of the remainder are transitional cases (44) and NHS internal refurbishments (28).
- Over the past 12 weeks, 42 gateway 3 applications have closed. 31 were approved with 11 invalidated. Of the 31 the majority were internal refurbishments (24), with remediation (3), transitional (3) and NHS internal refurbishments (1), making up the remaining approvals.
- This is an important area for BSR, particularly for new build projects, and we expect determination times to reduce as new processes are introduced and more resource is found.
Investigation and enforcement
BSR takes a proportionate, risk-based approach to investigation and enforcement. Where there is suspicion that a duty or requirement under the Building Act 1984, Building Safety Act 2022 or relevant secondary legislation may have been breached, BSR may open an investigation, with a particular focus on issues that could lead to fire spread or structural failure. Reports and referrals are triaged according to risk, ensuring the most serious building safety concerns are prioritised and addressed first.
Enforcement is a core regulatory function, with activity currently concentrated within occupied high-rise residential buildings and building control. Investigations can lead to a range of outcomes, including warnings, contravention letters, compliance notices and where appropriate, prosecution. Where there is sufficient evidence and it is in the public interest to do so, cases will be escalated for prosecution consideration, supporting a robust, proportionate and effective regulatory response that promotes compliance, drives improvements in building safety and protects residents.
As part of our commitment to transparency and accountability, BSR will soon publish data relating to its investigation and enforcement activities. This will provide greater visibility of regulatory interventions, helping to build confidence in building safety.