Press release

Milestone for M25 junction 30/A13 upgrade as next stage of congestion relieving scheme starts

The next stage of an £80m scheme to relieve congestion around junction 30 of the M25 and the A13 corridor near Thurrock in Essex starts next week.

This news article was withdrawn on

This document is no longer current

In October, Highways England announced that work on the upgrade would be completed earlier than planned – bringing it forward from autumn next year to the summer – and that this would be achieved by rescheduling the start of roadworks on the M25. This work will start next week. Work on the A13 has been underway since March.

Work will transfer to the M25 with traffic management being installed and construction work starting from Tuesday 17 November 2015.

The work involved in this stage of the scheme includes:

  • site clearance
  • renewal of boundary fencing
  • statutory diversions implemented
  • installation of new and replacement gantries
  • installation and renewal of traffic signals
  • construction of new concrete central reserve barrier
  • upgrade of CCTV
  • updating street lighting
  • new road markings and signs
  • associated environmental works – ecological and construction of environmental noise barrier
  • new fixed temporary traffic management signs along M25 and A282

To enable this work to take place, narrow lanes and a temporary 50mph speed limit need to be installed. The installation will mean that the anti-clockwise carriageway will be closed overnight, between 10pm and 5.30am, from Tuesday 17 November for 2 nights. A clearly signed diversion will be in place via the link road to M25 junction 30, A13, A128 and the A127.

In addition, the clockwise carriageway will be closed overnight, between 10pm and 5.30am, from Thursday 19 November for 2 nights. A clearly signed diversion will be in place via the A127, A128, A13 and the link road to M25 junction 31.

Once installed the temporary traffic management on the M25/A282 will include:

  • a temporary 50mph speed restriction, enforced by average speed cameras, to maintain the safety of road workers and travelling public
  • narrow lanes
  • hard shoulder running

There will be future carriageway closures for other works including the removal of existing gantries.

The work is part of a major project to increase capacity at this busy junction and help unlock the multi-billion pound regeneration of the Lower Thames Valley. The A13 through the junction is being widened from 3 lanes to 4 in each direction, and the junction itself is being upgraded by adding segregated left turns to and from the M25, and improvements to the other slip roads. Safety barriers, drainage and lighting are also being upgraded and it is estimated that the project will help to reduce accidents by 18%. Work is scheduled to be completed by summer 2016.

General enquiries

Members of the public should contact the Highways England customer contact centre on 0300 123 5000.

Media enquiries

Journalists should contact the Highways England press office on 0844 693 1448 and use the menu to speak to the most appropriate press officer.

Published 13 November 2015