Corporate report

Updated: Delivery timeline

Updated 3 November 2023

  2023/24 2024/25
Discovery • Launch of UK built Magnetometer instrument, on ESA’s JUICE mission to study Jupiter’s moons [DELIVERED] • Flight models of UK built Front End Electronics unit delivered to ESA for Plato mission
  • Completion of Ariel payload module Preliminary Design Review [DELIVERED] • Critical Design Review of Ariel payload module
  • Critical Design Review for MSR Earth Return Orbiter • Initial Euclid Data Release
  • Adoption of ESA gravitational wave mission LISA, finalisation of BC for UK mission leadership roles • Launch of the Halo Lunar Communications System to the Gateway
  • Launch of UK build VIS instrument on ESA’s Euclid dark matter mission • Launch of Lunar Pathfinder
  • Assembly of flight model of UK built Soft X-Ray Imager for SMILE mission • Build of ISS experiments completed
  • Funding agreed for UK teams to compete in study phases of new ESA Science mission candidates • Provisional Design Review for the first European Large Logistics Lander (EL3) mission
  • 1st UK instrument on the Moon • Flight of the European Mass Spectrometer on the LUPEX
  • Annual Exploration Science Call undertaken  
  • Completion of the Particle Vibration Experiment for the ISS [DELIVERED]  
Earth Observation • National Call for ESA InCubed Proposals and selection of projects​ • Climate Services Call
  • Championing UK Earth Observation activities at COP28 with colleagues from ESA Climate Space and UK EO sector • Selection of ESA Earth Explorer 12 Candidates to Phase 0​
  • GLOC conference showcasing UK Space and Climate Action​ [DELIVERED] • CEOI projects delivered
  • Copernicus participation decision taken following new EU negotiations • Microcarb ready for launch
  • Agreement of system consortium for TRUTHS  
  • ESA FEO programme to select ESA Earth Explorer 11 Candidates to Phase A​  
  • CEOI Earth Observation Mission Capabilities Review  
  • CEOI Project - Full funding allocated for this FY  
  • Climate Services Call completed  
  • Completion of Microcarb Assembly, Integration & Test (AIT) in Harwell, UK​  
Innovation • Assessment and award of the Partnership Call, planned funding calls (General x4, 5G x2, Scylight x1) • Launch, assessment and implementation of planned funding calls (General x4, 5G x2, Scylight x1)
  • ARTES BASS – Refresh evaluation and update complete • ARTES BASS – Four proposal decision making panels held
  • ARTES BASS – Four proposal decision making panels held. [DELIVERED] • NSIP – 2nd funding call downselection process complete
  • Moonlight - Assessment and award of the Partnership Call • NSIP – Monitoring and Evaluation Initial data completed
  • NSIP Full Business Case approved • IBF – Phase 2 projects complete
  • NSIP 1st funding calls opened and downselection process complete • SCF design implemented
  • NSIP Monitoring and Evaluation starts • Digital capability explored for consolidation of existing funding programmes
  • NSIP 2nd funding call opened • Implementation of front door consolidation option
  • ETP – combined with NSIP, early-stage/low TRL calls released under NSIP following BC approval [DELIVERED]  
  • GHGSat – SatAppsCatapult contract to create user community for GHGSat archive and new data [DELIVERED]  
  • GHGSat – Procurement of data archive access for UK Govt, including Ordnance Survey, via SatAppsCatapult [DELIVERED]  
  • International Bilateral Programme – Phase 1 funding call and project delivery  
  • International Bilateral Programme – Phase 2 call and start of delivery  
  • SCF market engagement to test preferred option  
  • SCF SOBC PIC/HMT approval of Procurement process for education aspects of SCF for investor partners and companies  
  • Terms and conditions agreed for education providers for SCF  
Inspiration • Remaining Space to Learn funded projects commence • Continuation and conclusion of all funded projects Inspire, learn and skills for space
  • Space to Inspire Full Business Case written and approved Q2: Skills for Space Full Business Case written and approved • Definition, strategy and planning for new astronaut programme
  • Business Engagement Project BC Approved [DELIVERED] • Business Engagement Programme Implementation (funding call)
  • Business Engagement Project Implementation (Awareness and Education)  
Launch Phase 1 • Inspiration Tour (LauncherOne) completed • Sutherland Spaceport construction completed
  • OMV Build Completed • ABL Space Systems Pathfinder Launch – SaxaVord Spaceport (including launch of OMV)
  • D-Orbit Launch of InOrbitNow service • Orbex Pathfinder Launch from Sutherland Spaceport
  • Space Forge Demonstration of reusable on-demand microgravity service • Skyrora 1st and 2nd Stage test complete
  • CSTS (Boost!) – Further contract awards expected as a result of CMIN22 funding.  
  • Orbex demonstration of responsive payload integration  
Launch Phase 2 • Tech Investments Pilot grant programme completed – including: Hyimpulse rocket engine testing [DELIVERED], Gravitilab ISAAC suborbital launch vehicle readiness for prototype [DELIVERED], SmallSpark hybrid rocket propulsion demonstration, SaxaVord launch rail completion • Further launch sector investments – subject to Outline Business Case/Full Business Case approval
    • Further Gate Reviews – subject to Outline Business Case/Full Business Case status
    • Gate 0 (Programme Strategic Assessment) – subject to requirement and Gate 2 review (Phase 2 Outline Business Case)
Levelling Up • Fund Space Cluster development projects, through Local Growth Programme • Conclusion of local growth Monitoring & Evaluation contract
  • UK Space Accelerator 3rd programme area open for applications, and annual repeat of all 3 programme area open calls • Conclusion of Space Cluster development projects
  • SCIF Outline Business Case approved • Conclusion of SCIF projects
  • SCIF Full Business Case approved  
  • SCIF Funding call launched and grants signed  
Space Safety and Sustainability • NSpOC Full Business Case approved • Phase One NSpOC Go-Live
  • SST OBSERVE Pillar: commence installation of enhanced sensor capabilities including Troodos and assessments of UK OSTs • Complete sustainability standards work
  • SST ANALYSE Pillar: commence procurement for enhanced AURORA analysis software (with MoD) • National ADR Mission BC approved
  • SST ALERT Pillar: commence upgrades to MYS service • ADR Technology development conducted
  • Complete ADR Phase B studies • IOSM study work complete
  • Downselect between Astroscale and Clearspace design studies  
  • Commence ADR/ IOSM interopability workstrands  
  • Commence Sustainability underpinning studies activity  
  • Deliver four Space sustainability conferences/events  
*Low Earth Orbit TBC TBC

(*) UK Space Agency programme for LEO, during this period is primarily focussed on policy development, however should additional funding and staffing resource become available, a delivery programme will be brought forward.