Corporate report

Sellafield Ltd Annual Review of Performance 2018 to 2019

A summary of the progress we made in tackling one of the world's most complex decommissioning challenges in the financial year 2018 to 2019.

Documents

Sellafield Ltd Annual Review of Performance 2018/19

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email info@sellafieldsites.com. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

The company, a subsidiary of the Nuclear Decommissioning Authority (NDA), is responsible for the 100-year programme to clean up the Sellafield nuclear site, in Cumbria.

Our Annual Review of Performance 2018/19 details a year of achievement in the hazard and risk reduction programme at the UK’s largest and most complex nuclear site.

Highlights include:

  • completing reprocessing in Thorp and making progress to safely conclude Magnox reprocessing
  • getting our 2 legacy waste facilities ready for retrievals - this means that in 2019/20 we will be removing waste and sludge from all 4 of our legacy ponds and silos
  • awarding a 20-year contract to bring in Project and Programme Partners to help us deliver mission-critical capital projects at Sellafield
  • changing the Sellafield skyline, bringing a redundant ventilation stack to a height where it no longer poses a risk to the surrounding buildings, and starting to demolish the diffuser at the top of the Windscale Pile Chimney
Published 27 June 2019