FOI release

Bascule Bridge

Response to a request for information made under the Freedom of Information Act about Bascule Bridge, Lowestoft.

Documents

FOI Response 708728

This file may not be suitable for users of assistive technology. Request an accessible format.

If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email info@highwaysengland.co.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

A request for information was made about the tidal flow system on the Bascule Bridge, Lowestoft. In response, the Highways Agency confirmed that a formal record of tidal flow system failures was kept between June 2008 and October 2012 and that a fault detection system could be in place by 31 March 2015.

Published 23 July 2014