Research and analysis
Table 5: Remediation of ACM buildings funded by the Private Sector Remediation Fund within and outside of London, 31 March 2021
Updated 15 April 2021
Download CSV 358 Bytes
| Category | Number of buildings inside London | Number of buildings outside London |
|---|---|---|
| No contact with delivery partners | 0 | 0 |
| Preparing application | 4 | 0 |
| Eligibility application submitted | 2 | 1 |
| Eligibility approved | 7 | 1 |
| Applications approved: for pre-contract support | 2 | 1 |
| Full cost application submitted | 3 | 0 |
| Applications approved: for full costs | 45 | 34 |
| TOTAL | 63 | 37 |