| Category | Number of buildings inside London | Number of buildings outside London |
|---|---|---|
| No contact with delivery partners | 0 | 0 |
| Preparing application | 2 | 3 |
| Eligibility application submitted | 13 | 1 |
| Eligibility approved | 26 | 21 |
| Full cost / pre-contract application submitted | 11 | 8 |
| For pre-contract support | 6 | 3 |
| For full costs | 0 | 1 |
| TOTAL | 58 | 37 |