Table 6: remediation of ACM buildings funded by the Private Sector Remediation Fund within and outside of London, 31 July 2020

Updated 13 August 2020
Download CSV 364 Bytes

Category Number of buildings inside London Number of buildings outside London
No contact with delivery partners 0 0
Preparing application 2 0
Eligibility application submitted 5 1
Eligibility approved 17 10
Applications approved: for pre-contract support 14 9
Full cost application submitted 9 2
Applications approved: for full costs 11 14
TOTAL 58 36